Question

Carla Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures wer

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

ANSWER:

Date Amount Period weighted average accumulated expenditure
March 1 $2088000 10 months $2088000 x (10/12) = $1740000
June 1 $1236000 7 months $1236000 x (7/12) = $721000
December 31 $3060460 0 months $3060460 x (0/12) = 0
Total $6384460 $2461000


therefore, weighted average accumulated expenditure = $2461000

Add a comment
Know the answer?
Add Answer to:
Carla Company is constructing a building. Construction began on February 1 and was completed on December...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT