Selected accounts with a credit amount omitted are as follows
Work in Process | |||||
Apr. 1 | Balance | 7,500 | Apr. 30 | Goods finished | X |
30 | Direct materials | 51,700 | |||
30 | Direct labor | 193,700 | |||
30 | Factory overhead | 58,110 |
Finished Goods | |||||
Apr. 1 | Balance | 13,600 | |||
30 | Goods finished | 304,000 |
What was the balance of Work in Process as of April 30?
a.$7,010
b.$13,600
c.$58,110
d.$304,000
Work in Process, Apr 1 Balance | 7500 |
Add: Direct materials | 51700 |
Add: Direct labor | 193700 |
Add: Factory overhead | 58110 |
Total cost of Work in Process | 311010 |
Less: Goods finished | -304000 |
Balance of Work in Process as of April 30 | 7010 |
Option A $7,010 is correct |
Selected accounts with a credit amount omitted are as follows Work in Process Apr. 1 Balance...
Calculator Selected accounts with a credit amount omitted are as follows Work in Process Apr. 1 30 Goods finished Balance Direct materials Direct labor Factory overhead 6,000 Apr. 30 53,300 191,600 57,480 Finished Goods Apr. 1 Balance 14,300 30 Goods finished 303,300 What was the balance of Work in Process as of April 30? TVT a. $303,300 b. $14,300 c. $57,480 d. $5,080
Selected accounts with a credit amount omitted are as follows Work in Process 7,000 Apr. 30 56,400 Apr. 1 Balanc Goods finished 30 Direct materials 30 Direct labor 30 Factory overhead 193,900 58,170 Finished Goods Apr. 1 Balance 12,700 Goods finished 304,400 30 What was the balance of Work in Process as of April 30? Oa. $304,400 Ob. $58,170 Oc. $11,070 od, $12,700
Selected accounts with a credit amount omitted are as follows Goods finished Apr. 1 30 Balance Direct materials Direct labor Factory overhead Work in Process 6,900 Apr. 30 65,800 194,000 58,200 30 Finished Goods Apr. 1 Balance 14,800 Goods finished 308,900 What was the balance of Work in Process as of April 30? a. $14,800 b. $16,000 c. $308,900 d. $58,200
Selected accounts with a credit amount omitted are as follows Goods finished Apr. 1 30 Balance Direct materials Direct labor Factory overhead Work in Process 6,700 Apr. 30 53,000 191,200 57,360 30 30 Finished Goods Apr. 1 Balance 15,200 30 Goods finished 307,300 What was the balance of Work in Process as of April 307 Oa. $57,360 Ob. $960 Oc. $15,200 Od. $307,300
Selected accounts with some amounts omitted are as follows Work in Process Aug. 1 Balance 271,500 Aug. 31 Goods finished 179,600 31 Direct materials X 31 Direct labor 46,700 31 Factory overhead X Factory Overhead Aug. 1 – 31 Costs incurred 117,800 Aug. 1 Balance 16,000 31 Applied X If the balance of Work in Process at August 31 is $214,400, what was the amount debited to Work in Process for factory overhead in August,...
Selected accounts with some amounts omitted are as follows Work in Process Oct. 1 Balance 23,400 Oct. 31 Goods finished X 31 Direct materials 91,000 31 Direct labor 161,800 31 Factory overhead X Finished Goods Oct. 1 Balance 12,800 31 Goods finished 344,400 If the balance of Work in Process on October 31 is $202,900, what was the amount of factory overhead applied in October? a.$388,100 b.$271,100 c.$91,000 d.$161,800
Selected accounts with some amounts omitted are as follows: Work in Process Oct. 1 Balance 24,800 Oct. 31 Goods finished X 31 Direct materials 90,400 31 Direct labor 196,600 31 Factory overhead X Finished Goods Oct. 1 Balance 12,500 31 Goods finished 343,100 If the balance of Work in Process on October 31 is $198,000, what was the amount of factory overhead applied in October? a.$229,300 b.$419,400 c.$90,400 d.$196,600
Selected accounts with a credit amount omitted are as followsWork in ProcessApr. 1Balance7,700 Apr. 30Goods finishedX 30Direct materials67,200 30Direct labor190,600 30Factory overhead57,180 Finished GoodsApr. 1Balance12,300 30Goods finished309,900 What was the balance of Work in Process as of April 30?a.$12,780b.$12,300c.$309,900d.$57,180
Selected accounts with some amounts omitted are as follows Work in Process Aug. 1 Balance 252,100 Aug. 31 Goods finished 162,800 31 Direct materials X 31 Direct labor 43,300 31 Factory overhead X Factory Overhead Aug. 1 – 31 Costs incurred 118,900 Aug. 1 Balance 14,100 31 Applied X If the balance of Work in Process on August 31 is $202,900, what was the amount debited to Work in Process for factory overhead in August, assuming a factory overhead rate...
Selected accounts with some amounts omitted are as follows Work in Process Aug. 1 Balance 252,100 Aug. 31 Goods finished 162,800 31 Direct materials X 31 Direct labor 43,300 31 Factory overhead X Factory Overhead Aug. 1 – 31 Costs incurred 118,900 Aug. 1 Balance 14,100 31 Applied X If the balance of Work in Process on August 31 is $202,900, what was the amount debited to Work in Process for factory overhead in August, assuming a factory overhead rate...