Question

Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical...

  1. Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis

    Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows:

    Standard Costs Actual Costs
    Direct materials 238,000 lbs. at $5.30 235,600 lbs. at $5.20
    Direct labor 17,500 hrs. at $16.40 17,900 hrs. at $16.80
    Factory overhead Rates per direct labor hr.,
    based on 100% of normal
    capacity of 18,260 direct
    labor hrs.:
    Variable cost, $4.10 $71,030 variable cost
    Fixed cost, $6.50 $118,690 fixed cost

    Each unit requires 0.25 hour of direct labor.

    Required:

    a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

    Direct Material Price Variance $
    Direct Materials Quantity Variance $
    Total Direct Materials Cost Variance $

    b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

    Direct Labor Rate Variance $
    Direct Labor Time Variance $
    Total Direct Labor Cost Variance $

    c. Determine variable factory overhead controllable variance, the fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

    Variable factory overhead controllable variance $
    Fixed factory overhead volume variance $
    Total factory overhead cost variance $

Check My Work

1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
a Material price variance=Actual quantity of material used*(Actual rate of material-Standard rate of material)
If the answer is negative, variance is favorable.Otherwise unfavorable.
Actual material used=235600 lbs.
Standard rate of material=$ 5.30 per pound
Actual rate of material=$ 5.20 per pound
Material price variance=235600*(5.30-5.20)=23560=$ 23560 (Unfavorable)
Material Quantity variance=Standard rate of material*(Actual quantity consumed-Standard quantity)
If the answer is negative, variance is favorable.Otherwise unfavorable.
Standard rate of material=$ 5.30 per pound
Standard quantity=238000 lbs.
Actual material used=235600 lbs.
Material quantity variance=5.30*(235600-238000)=-12720=$ 12720 (Favorable)
Total material cost variance=Material price variance+Material quantity variance
If the answer is negative, variance is favorable.Otherwise unfavorable.
Total material cost variance=23560+-12720=10840=$ 10840 (Unfavorable)
b Labor rate variance=Actual hours worked*(Actual rate of labor-Standard rate of labor)
If the answer is negative, variance is favorable.Otherwise unfavorable.
Actual hours worked=17900 hours
Standard rate of labor=$ 16.40 per hour
Actual rate of labor=$ 16.80 per hour
Labor rate variance=17900*(16.80-16.40)=7160=$ 7160 (Unfavorable)
Labor time variance=Standard rate of labor*(Actual hours worked-Standard hours)
If the answer is negative, variance is favorable.Otherwise unfavorable.
Standard rate of labor=$ 16.40 per hour
Standard hours=17500 hours
Actual hours worked=17900 hours
Direct labor time variance=16.40*(17900-17500)=6560=$ 6560 (Unfavorable)
Total labor cost variance=Labor rate variance+labor time variance
If the answer is negative, variance is favorable.Otherwise unfavorable.
Total labor cost variance=7160+6560=13720=$ 13720 (Unfavorable)
c Total factory overhead cost budgeted:
$
Variable cost (18260*4.10) 74866
Fixed cost (18260*6.50) 118690
Total 193556
Fixed factory overhead budgeted=18260*6.50=$ 118690
Variable factory overhead budgeted=$ 74866
Variable factory overhead controllable variance=Actual variable factory overhead-Budgeted variable factory overhead based on standard hours allowed
If the answer is negative, variance is favorable.Otherwise unfavorable.
Variable factory overhead controllable variance=71030-(17500*4.10)=71030-71750=-720=$ 720 (Favorable)
Fixed factory overhead volume variance=Absorbed fixed overhead-Budgeted fixed overhead
If the answer is negative, variance is unfavorable.Otherwise favorable.
Absorbed fixed overhead=Actual hours*rate per hour=17900*6.50=$ 116350
Fixed factory overhead volume variance=116350-118690=-2340=$ 2340 (Unfavorable)
Total factory overhead cost variance=Budgeted factory overhead-Actual factory overhead
If the answer is negative, variance is unfavorable.Otherwise favorable.
Total factory overhead cost variance=193556-(71030+118690)=193556-189720=3836=$ 3836 (Favorable)
Add a comment
Know the answer?
Add Answer to:
Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT