Answer #1
Schedule of cost of goods manufactured
Direct Materials:
Beginning Raw materials $3,05,000
Add:Purchase of raw materials $6,07,000
Total Raw materials available $9,12,000
Less:Ending raw materials inventory $2,77,200
Raw materials used in production $6,34,800
Direct Labor $5,62,000
Factory Overhead:
Indirect labor $60,600
Machinery Depreciation $36,000
Heat, Light and Power $12,900
Supplies $8,100
Property Taxes $8,720
Miscallenous Costs $16,300
Toatl Factory Overhead Cost $1,42,620
Total manufaturing costs $13,39,420
Add:Beginning WIP inventory $2,14,200
$15,53,620
Less:Ending WIP inventory $2,38,600
Cost of goods manufactured $13,15,020
Schedule of cost of goods sold
Beginning Finished goods inventory $1,62,800
Add:Cost of goods manufactured $13,15,020
Cost of goods available for sale $14,77,820
Less:Finished goods inventory $1,90,500
Unadjusted cost of goods sold $12,87,320
Add a comment
Know the answer?
Add Answer to:
Instructions Cost data for Mix-A-Lot Manufacturing Company for the month ended March 31, 2016, are as...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Statement of cost of goods manufactured for a manufacturing company Instructions Amount Descriptions Statement of Cost...

    Statement of cost of goods manufactured for a manufacturing company Instructions Amount Descriptions Statement of Cost of Goods Manufactured Cost of Goods Sold Instructions Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories Materials ÖNOWN January 1 $305,000 214,200 162,800 January 31 $277,200 238,600 190,500 Work in process Finished goods Direct labor January 31 $562,000 607,000 Materials purchased during the month Factory overhead incurred during the month: Indirect labor Machinery depreciation Heat, light,...

  • Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories...

    Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories January 1 January 31 Materials $310,000 $276,600 238,400 Work in process 215,200 Finished goods 162,800 190,100 January 31 Direct labor $565,000 604,800 Materials purchased during the month Factory overhead incurred during the month: Indirect labor 60,440 Machinery depreciation 35,000 Heat, light, and power 13,600 Supplies 8,540 Property taxes 8,860 Miscellaneous costs 16,400 Required: a. Prepare a cost of goods manufactured statement for January. Refer...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company for the month ended March 31 are as follows: March 1 March 31 Inventories Materials $182,000 $163,800 Work in process 123,760 111,380 Finished goods 94,640 111,380 Direct labor $327,600 Materials purchased during March 349,440 Factory overhead incurred during March: Indirect labor 34,940 Machinery depreciation 21,110 Heat, light, and power 7,280 Supplies 5,820 Property taxes 5,100 Miscellaneous costs 9,460 a. Prepare a cost of goods...

  • Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories...

    Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories January 1 January 31 Materials $307,000 $277,600 Work in process 214,000 238,400 Finished goods 163,000 187,000 January 31 Direct labor $566,000 Materials purchased during the month 607,200 Factory overhead incurred during the month: Indirect labor 60,860 Machinery depreciation 35,000 Heat, light, and power 12,800 Supplies 8,400 Property taxes 8,200 Miscellaneous costs 16,360 Required: a. Prepare a cost of goods manufactured statement for January. Refer...

  • Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories January 1...

    Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories January 1 January 31 Materials $224,500 152,660 Work in process Finished goods $199,810 135,870 133,870 116,740 $404,100 431,040 43,100 Direct labor Materials purchased during January Factory overhead incurred during January: Indirect labor Machinery depreciation Heat, light, and power Supplies Property taxes Miscellaneous costs 26,040 8,980 7,180 6,290 11,670 a. Prepare a cost of goods manufactured statement for January Sandusky Manufacturing Company Statement of Cost...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company for the...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories January 1 January 31 Materials $154,000 $132,440 Work in process 103,180 88,730 Finished goods 78,540 88,730 Direct labor $277,200 Materials purchased during January 295,680 Factory overhead incurred during January: Indirect labor 29,570 Machinery depreciation 17,860 Heat, light, and power 6,160 Supplies 4,930 Property taxes 4,310 Miscellaneous costs 8,010 a. Prepare a cost of goods...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company for the month ended March 31 are as follows: Inventories March 1 March 31 Materials $142,000 $123,540 95,140 82,770 Work in process Finished goods 72,420 82,770 Direct labor $255,600 272,640 Materials purchased during March Factory overhead incurded during March: Indirect labor 27,260 16,470 Machinery depreciation Heat, light, and power 5,680 4,540 Supplies Property taxes 3,980 7,380 Miscellaneous costs a. Prepare a cost of goods...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company for the month ended March 31 are as follows: Inventories March 1 March 31 Materials $212,000 $182,320 Work in process 1 44,160 123,980 Finished goods 110,240 122,150 S. Direct labor Materials purchased during March Factory overhead incurred during March: $381,600 407,040 Indirect labor Machinery depreciation Heat, light, and power Supplies Property taxes Miscellaneous costs a. Prepare a cost of goods manufactured statement for March....

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company for the month ended March 31 are as follows: March 1 March 31 Inventories Materials $ 142,000 $123,540 Work in process 95,140 82,770 Finished goods 72,420 82,770 Direct labor $255,600 272,640 Materials purchased during March Factory overhead incurred during March: Indirect labor 27,260 Machinery depreciation 16,470 Heat, light, and power 5,680 4,540 Supplies 3,980 Property taxes Miscellaneous costs 7,380 a. Prepare a cost of...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company for the month ended March 31 are as follows: Inventories March 1 March 31 Materials $165,150 $183,500 122,950 110,650 Work in process Finished goods 93,590 110,650 $330,300 352,320 35,230 Direct labor Materials purchased during March Factory overhead incurred during March: Indirect labor Machinery depreciation Heat, light, and power Supplies Property taxes Miscellaneous costs 21,290 7,340 5,870 5,140 9,540 a. Prepare a cost of goods...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT