Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $130,700 Fixed factory overhead 52,250 Standard: 7,000 hrs. at $24 168,000 If productive capacity of 100% was 11,000 hours and the total factory overhead cost budgeted at the level of 7,000 standard hours was $187,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $4.75 per hour. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Variance Amount Favorable/Unfavorable Variable factory overhead controllable variance $ Fixed factory overhead volume variance Total factory overhead cost variance.
1. Variable Factory Overhead Controllable Variance .
Actual Variable Factory Overhead Cost incurred | $130,700 |
Budgeted Variable Factory Overhead for 7,000 Hrs | |
( 7,000 ×( $24 - $ 4.75) | $134,750 |
Variance -- Favourable | $ (4,050) |
2.Fixed Factory Overhead Volume Variance
Productive Capacity at 100 % | 11,000 Hrs |
Standard for amount produced | 7,000 hrs |
Productive Capacity not used | 4,000 hrs |
Standard Fixed Factory Overhead Rate | $4.75 |
Variance - Unfavourable | $19,000 |
3. Total Factory Overhead Cost varance
Variance ( Unfavorable ) = $ 14,950
Explanation;
Actual overhead - Applied Overhead = Total Overhead Variance
($130,700 + $52,250 ) - $168,000 = $ 14,950 ( UF)
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
5 Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $191,800 Fixed factory overhead 52,250 Standard: 7,000 hrs. at $33 231,000 If productive capacity of 100% was 11,000 hours and the total factory overhead cost budgeted at the level of 7,000 standard hours was $250,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $198,600 Fixed factory overhead 63,250 245,000 Standard: 7,000 hrs. at $35 If productive capacity of 100% was 11,000 hours and the total factory overhead cost budgeted at the level of 7,000 standard hours was $268,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $202,000 Fixed factory overhead 46,750 Standard: 7,000 hrs. at $34 238,000 If productive capacity of 100% was 11,000 hours and the total factory overhead cost budgeted at the level of 7,000 standard hours was $255,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $181,600 Fixed factory overhead 57,750 Standard: 7,000 hrs. at $32 224,000 If productive capacity of 100% was 11,000 hours and the total factory overhead cost budgeted at the level of 7,000 standard hours was $245,000, urs and the total factory overhead cost budgeted at the level of 7,000 standard hours was $245,000, determine the variable factory overhead controllable...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 4,000 computers: Variable factory overhead $105,700 Actual: Fixed factory overhead 40,500 4,000 hrs. at $34 Standard: 136,000 If productive capacity of 100 % was 6,000 hours and the factory overhead cost budgeted at the level of 4,000 standard hours was $149,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 3,000 computers: Actual: Variable factory overhead $64,700 Fixed factory overhead 18,750 Standard: 3,000 hrs. at $26 78,000 If productive capacity of 100% was 5,000 hours and the factory overhead cost budgeted at the level of 3,000 standard hours was $85,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $166,800 Fixed factory overhead 45,500 Standard: 8,000 hrs. at $25 200,000 If productive capacity of 100% was 13,000 hours and the total factory overhead cost budgeted at the level of 8,000 standard hours was $217,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $124,200 Fixed factory overhead 52,000 Standard: 8,000 hrs. at $20 160,000 If productive capacity of 100% was 13,000 hours and the total factory overhead cost budgeted at the level of 8,000 standard hours was $180,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 3,000 computers: Actual: Variable factory overhead $97,500 Fixed factory overhead 27,500 Standard: 3,000 hrs. at $39 117,000 If productive capacity of 100% was 5,000 hours and the total factory overhead cost budgeted at the level of 3,000 standard hours was $128,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 5,000 computers: Actual: Variable factory overhead $107,900 Fixed factory overhead 30,000 Standard: 130,000 5,000 hrs. at $26 If productive capacity of 100% was 8,000 hours and the total factory overhead cost budgeted at the level of 5,000 standard hours was $141,250, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...