Question

1) A company incurred the following costs: Purchase price of land Survey fees Payment for demolition of old building on land
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1 Cost of Land 270000+4000+20000+2000 $296,000 Answer : B 9 2 0 Answer C Debit Cashfor $23,000, Debit Accumalated Depreceiati

Add a comment
Know the answer?
Add Answer to:
1) A company incurred the following costs: Purchase price of land Survey fees Payment for demolition...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1) A company incurred the following costs: Purchase price of land Survey fees Payment for demolition...

    1) A company incurred the following costs: Purchase price of land Survey fees Payment for demolition of old building on land Back property taxes on land Paving costs for parking lot Fence around perimeter of land Lights in parking lot Signs for new business $270,000 4,000 20,000 2,000 60,000 15,000 90,000 5,000 What is the cost of the land? A) $270,000. B) $296,000. C) $356,000. D) $294,000. E) None of the above. 2) Equipment costing $40,000with a book value of...

  • A company incurred the following costs: Purchase price of land Survey fees Payment for demolition of...

    A company incurred the following costs: Purchase price of land Survey fees Payment for demolition of old building on land Back property taxes on land Paving costs for parking lot Fence around perimeter of land Lights in parking lot Signs for new business What is the cost of the land? $290,000 6,000 20,000 3,000 70,000 15,000 90,000 5,000 O A. $316,000 O B. $290,000 O C. $319,000 OD. $389,000

  • A company incurred the following costs: $230,000 Purchase price of land Survey fees Payment for demolition...

    A company incurred the following costs: $230,000 Purchase price of land Survey fees Payment for demolition of old building on land Back property taxes on land Paving costs for parking lot Fence around perimeter of land Lights in parking lot Signs for new business 8,000 30,000 5,000 70,000 15,000 90,000 5,000 What is the cost of the land? O A. $273,000 O B. $230,000 C. $268,000 O D. $343,000 Click to select your answer.

  • Journal Entries for Plant Assets During the first few days of the year, Coast Company entered...

    Journal Entries for Plant Assets During the first few days of the year, Coast Company entered into the following transactions: 1 Purchased a parcel of land with a building on it for $900,000 cash. The building, which will be used in operations, has an estimated useful life of 25 years and a salvage value of $60,000. The assessed valuations for property tax purposes show the land at $80,000 and the building at $720,000. 2 Paid $31,200 for the construction of...

  • At December 31, 2017, Grand Company reported the following as plant assets. Land $ 4,360,000 Buildings...

    At December 31, 2017, Grand Company reported the following as plant assets. Land $ 4,360,000 Buildings $28,130,000 Less: Accumulated depreciation—buildings 12,490,000 15,640,000 Equipment 48,640,000 Less: Accumulated depreciation—equipment 5,290,000 43,350,000     Total plant assets $63,350,000 During 2018, the following selected cash transactions occurred. April 1 Purchased land for $2,050,000. May 1 Sold equipment that cost $1,020,000 when purchased on January 1, 2014. The equipment was sold for $612,000. June 1 Sold land purchased on June 1, 2008 for $1,560,000. The land cost...

  • During the first few days of the year, Jules Company entered into the following transactions: 1...

    During the first few days of the year, Jules Company entered into the following transactions: 1 Purchased a parcel of land with a building on it for $900,000 cash. The building, which will be used in operations, has an estimated useful life of 20 years and a salvage value of $60,000. The assessed valuations for property tax purposes show the land at $80,000 and the building at $720,000. 2 Paid $31,200 for the construction of an asphalt parking lot for...

  • please help with these accouting questions! IV ab X X APA 1 Styles Styles Pane Sensiti...

    please help with these accouting questions! IV ab X X APA 1 Styles Styles Pane Sensiti 7. Burke Company purchases land for $180,000 cash. Burke assumes $5,000 in property taxes due on the land. The title and attorney fees totaled $2,000. Burke has the land graded for $4,400. They paid $20,000 for paving of a parking lot. What amount does Burke record as the cost for the land? A) $186,400. B) $211,400 C) $191,400 D) $180,000. 8. Ramirez Company acquires...

  • Determine property, plant, and equipment costs. (LO 1) E10-2 Benedict Company incurred the following costs. 1....

    Determine property, plant, and equipment costs. (LO 1) E10-2 Benedict Company incurred the following costs. 1. Sales tax on factory machinery purchased 2. Painting of and lettering on truck immediately upon purchase 3. Installation and testing of factory machinery 4. Real estate broker's commission on land purchased Insurance premium paid for first year's insurance on new truck 6. Cost of landscaping on property purchased 7. Cost of paving parking lot for new building constructed 8. Cost of clearing, draining, and...

  • At December 31, 2022, Blue Corporation reported the following plant assets. Land $4,548,000 Buildings $26,520,000 18,078,300...

    At December 31, 2022, Blue Corporation reported the following plant assets. Land $4,548,000 Buildings $26,520,000 18,078,300 8,441,700 Less: Accumulated depreciation-buildings Equipment Less: Accumulated depreciation equipment Total plant assets 60,640,000 7,580,000 53,060,000 $66,049,700 During 2023, the following selected cash transactions occurred. Apr. 1 Purchased land for $3,335,200. May 1 Sold equipment that cost $909.600 when purchased on January 1, 2016. The equipment was sold for $257.720. June 1 Sold land for $2.425,600. The land cost $1.516,000. July 1 Purchased equipment for...

  • 1. Custom Banners pays $300,000 cash for a group purchase of land, building, and equipment. At...

    1. Custom Banners pays $300,000 cash for a group purchase of land, building, and equipment. At the time of acquisition, the land has a market value of $119,000, the building $204,000, and the equipment $17.000. Journalize the lump-sum purchase. First, refer to the information provided and calculate the ratio of each asset's market value to the total for all assets combined. Then, complete the table and calculate the assigned cost for each asset. Total Percentage of Total Market Purchase Price...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT