The city of Waterbourne has made it a strategic goal to enhance livability in the city. The city has decided to undertake a p

0 0
Add a comment Improve this question Transcribed image text
Answer #1

using Excel

Years Cash Flow
Investment utilities for path Water utilities Sponsorship Net cash flow
0 -291107.00 -2,91,107
1 -13323 129866 116543
2 -13572 137658 124086
3 -13821 145917 132096
4 -14070 154672 140602
5 -14319 -14319
6 -14568 -14568
7 -14817 -14817
8 -15066 -15066
9 -52269 -15315 -67584
10 -212042 -15564 -24599 -252205
11 -15813 -27305 -43118
12 -16062 -30308 -46370
13 -16311 -33642 -49953
14 -16560 -37343 -53903
15 -16809 -41451 -58260
16 -17058 -46010 -63068
17 -17307 -51071 -68378
18 -17556 -56689 -74245
19 -76752 -17805 -62925 -157482
20 -18054 -69847 -87901
21 -18303 -77530 -95833
22 -18552 -86058 -104610
23 -18801 -95525 -114326
24 -19050 -106033 -125083
25 -19299 -117696 -136995
26 -19548 -130643 -150191
27 -19797 -145013 -164810
28 -20046 -160965 -181011
29 -20295 -178671 -198966
NPW -6,31,856

Showing formula in excel

Years Cash Flow
Investment utilities for path Water utilities Sponsorship Net cash flow
0 -291107 =B3+C3+D3+E3
1 -13323 =129866 =B4+C4+D4+E4
2 =C4-249 =E4*1.06 =B5+C5+D5+E5
3 =C5-249 =E5*1.06 =B6+C6+D6+E6
4 =C6-249 =E6*1.06 =B7+C7+D7+E7
5 =C7-249 =B8+C8+D8+E8
6 =C8-249 =B9+C9+D9+E9
7 =C9-249 =B10+C10+D10+E10
8 =C10-249 =B11+C11+D11+E11
9 -52269 =C11-249 =B12+C12+D12+E12
10 -212042 =C12-249 -24599 =B13+C13+D13+E13
11 =C13-249 =D13*1.11 =B14+C14+D14+E14
12 =C14-249 =D14*1.11 =B15+C15+D15+E15
13 =C15-249 =D15*1.11 =B16+C16+D16+E16
14 =C16-249 =D16*1.11 =B17+C17+D17+E17
15 =C17-249 =D17*1.11 =B18+C18+D18+E18
16 =C18-249 =D18*1.11 =B19+C19+D19+E19
17 =C19-249 =D19*1.11 =B20+C20+D20+E20
18 =C20-249 =D20*1.11 =B21+C21+D21+E21
19 -76752 =C21-249 =D21*1.11 =B22+C22+D22+E22
20 =C22-249 =D22*1.11 =B23+C23+D23+E23
21 =C23-249 =D23*1.11 =B24+C24+D24+E24
22 =C24-249 =D24*1.11 =B25+C25+D25+E25
23 =C25-249 =D25*1.11 =B26+C26+D26+E26
24 =C26-249 =D26*1.11 =B27+C27+D27+E27
25 =C27-249 =D27*1.11 =B28+C28+D28+E28
26 =C28-249 =D28*1.11 =B29+C29+D29+E29
27 =C29-249 =D29*1.11 =B30+C30+D30+E30
28 =C30-249 =D30*1.11 =B31+C31+D31+E31
29 =C31-249 =D31*1.11 =B32+C32+D32+E32
NPW =NPV(6%,F4:F32)+F3
Add a comment
Know the answer?
Add Answer to:
The city of Waterbourne has made it a strategic goal to enhance livability in the city....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The city of Waterbourne has made it a strategic goal to enhance livability in the city. The city has decided to undertak...

    The city of Waterbourne has made it a strategic goal to enhance livability in the city. The city has decided to undertake a project that will occur in two phases. During the first phase, the city will connect several of the parks with walking paths. During the second phase, the city will add water features or splash fountains to several of the parks. The initial cost of the project will be $381,944. Annual utilities for maintaining the walking paths and...

  • Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will have a lifespan of 12...

    Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will have a lifespan of 12 years. If successful, the state will pay Swanson $131,078 at the end of each year, increasing the payment by $28,943 each subsequent year. The project will have expenses of $46,352 per year. Part way through the project, Swanson will need to rent some special equipment at a cost of $2,985 per year, with the cost decreasing by 10% each...

  • Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will have a lifespan of 10...

    Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will have a lifespan of 10 years. If successful, the state will pay Swanson $135,051 at the end of each year, increasing the payment by $33,708 each subsequent year. The project will have expenses of $42,529 per year. Part way through the project, Swanson will need to rent some special equipment at a cost of $3,801 per year, with the cost decreasing by 9% each...

  • Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will have a lifespan of 10...

    Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will have a lifespan of 10 years. If successful, the state will pay Swanson $116,193 at the end of each year, increasing the payment by $31,646 each subsequent year. The project will have expenses of $49,293 per year. Part way through the project, Swanson will need to rent some special equipment at a cost of $3,112 per year, with the cost decreasing by 8% each...

  • Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will...

    Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will have a lifespan of 12 years. If successful, the state will pay Swanson $147,656 at the end of each year, increasing the payment by $34,885 each subsequent year. The project will have expenses of $47,147 per year. Part way through the project, Swanson will need to rent some special equipment at a cost of $3,373 per year, with the cost decreasing by 8% each...

  • Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will...

    Swanson Brothers, Inc. is putting together a bid for a multi-year state project. The project will have a lifespan of 10 years. If successful, the state will pay Swanson $129,868 at the end of each year, increasing the payment by $31.525 each subsequent year. The project will have expenses of $48,172 per year. Part way through the project, Swanson will need to rent some special equipment at a cost of $3,937 per year, with the cost decreasing by 8% each...

  • Prepare journal entries for each of the following transactions entered into by the City of Loveland....

    Prepare journal entries for each of the following transactions entered into by the City of Loveland. (If no entry is required for a transaction/event, select "No Journal Entry Required" in the first account field.) Fund/ Governmental Transaction Activlies General Journal Debit Credit 1. The city received a donation of land that is to be used by Parks and Recreation to develop a public park. At the time of the donation, the land had an acquisition value of $5.200,000 and was...

  • Prepare journal entries for each of the following transactions entered into by the City of Loveland....

    Prepare journal entries for each of the following transactions entered into by the City of Loveland. (If no entry is required for a transaction/event, select "No Journal Entry Required" in the first account field.) Transaction Fund / Governmental Activties General Journal Debit Credit 1. The city received a donation of land that is to be used by Parks and Recreation to develop a public park. At the time of the donation, the land had an acquisition value of $5,200,000 and...

  • Prepare journal entries for each of the following transactions entered into by the City of Loveland....

    Prepare journal entries for each of the following transactions entered into by the City of Loveland. (If no entry is required for a transaction/event, select "No Journal Entry Required" in the first account field.) Transaction Fund / Governmental Activties General Journal Debit Credit 1. The city received a donation of land that is to be used by Parks and Recreation to develop a public park. At the time of the donation, the land had an acquisition value of $5,200,000 and...

  • A major city in Eastern Canada is planning to build a new wastewater treatment plant to...

    A major city in Eastern Canada is planning to build a new wastewater treatment plant to accommodate the increasing water consumption of the city, Plant construction will start in 2018 and is going to take five years at a cost of $30 million per year. After construction is completed, the cost of operation, maintenance is expected to be $2 million for the first year, and to increase by 1% per year thereafter. The salvage/scrap value of the wastewater treatment plant...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT