Answer : $111,152
For January :1000 Units
Variable overhead cost per Unit = (62000-35,960)/1000= 26.04
Fixed overhead = 35,960
Varaible Administrative cost Per Unit = 7,800 / 1,000 =7.80
Fixed Administrative cost= 39000- 7,800 = $31,200
For MArch : 1300 Units
Total Overhead cost = (35,960)+(26.04*1300) = $69,812
Total Adminstraive Cost = 31,200+(7.80*1300) = $41,340
Total Estimated Cost = 69,812+41340 = $111,152(Answer)
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected...
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,500 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs Total fixed overhead costs Total administrative costs Total variable administrative costs $60,000 39,000 39,000 8,190 What is X Company's estimate of total costs in March [round unit costs to two decimal places]?...
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,500 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs Total fixed overhead costs Total administrative costs Total variable administrative costs $69,000 31,740 33,000 8,250 What is X Company's estimate of total costs in March [round unit costs to two decimal places]?...
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,500 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs Total fixed overhead costs Total administrative costs Total variable administrative costs $52,000 29,120 31,000 7,440 What is X Company's estimate of total costs in March [round unit costs to two decimal places)?...
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,350 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs $62,000 Total fixed overhead costs 39,680 Total administrative costs 32,000 Total variable administrative costs 7,680 What is X Company's estimate of total costs in March [round unit costs to two decimal places]?
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,500 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs Total fixed overhead costs Total administrative costs Total variable administrative costs $62,000 27,900 35,000 9,800 What is X Company's estimate of total costs in March [round unit costs to two decimal places)?
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,450 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs $52,000 Total fixed overhead costs 31,200 Total administrative costs 39,000 Total variable administrative costs 9,360 What is X Company's estimate of total costs in March [round unit costs to two decimal places]?
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,300 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs $59,000 Total fixed overhead costs 33,040 Total administrative costs 34,000 Total variable administrative costs 8,500 What is X Company's estimate of total costs in March [round unit costs to two decimal places]?
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,300 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs Total fixed overhead costs Total administrative costs Total variable administrative costs $56,000 33,600 40,000 12,000 What is X Company's estimate of total costs in March [round unit costs to two decimal places]?
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,300 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs Total fixed overhead costs Total administrative costs Total variable administrative costs $60,000 38,400 35,000 8,750 What is X Company's estimate of total costs in March [round unit costs to two decimal places]?...
X Company wants to estimate total costs (overhead plus administrative) in March, when production is expected to be 1,400 units. It analyzed January costs to determine the parameters of the overhead and administrative cost functions. January production was 1,000 units and costs were as follows: Total overhead costs $56,000 Total fixed overhead costs 31,920 Total administrative costs 38,000 Total variable administrative costs 10,640 What is X Company's estimate of total costs in March [round unit costs to two decimal places]?