Question

During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available.

2017

2018

2019

Costs incurred to date $434,300 $859,560 $1,073,000
Estimated costs to complete 575,700 242,440 –0–
Billings to date 301,000 897,000 1,610,000
Collections to date 271,000 817,000 1,428,000

A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2017 $ 258,000

Gross profit recognized in 2018 $ 138,240

Gross profit recognized in 2019 $ 140,760

B) Prepare all necessary journal entries for 2018.

Prepare all necessary journal entries for 2018. (Credit account titles are automatically indented whe incurred use account Ma

C) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

Entry field with correct answer

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) Gross profit recognized (Percentage-of-completion method) : 2017 2018 2019 $1,610,000 $1,610,000 $1,610,000 Contract price

Add a comment
Know the answer?
Add Answer to:
During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...

  • C) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method...

    C) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used. During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2017 $434,300 575,700 301,000 271,000 2018 $859,560 242,440 897,000 817,000 2019 $1,073,000 -0- 1,610,000 1,428,000 Prepare all necessary journal entries for 2018. (Credit...

  • During 2020, Bramble Company started a construction job with a contract price of $1,610,000. The job...

    During 2020, Bramble Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...

  • During 2017, Crane Company started a construction job with a contract price of $ 1,610,000. The...

    During 2017, Crane Company started a construction job with a contract price of $ 1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $ 366,300 $ 772,100 $ 1,063,000 Estimated costs to complete 623,700 330,900 –0– Billings to date 300,000 909,000 1,610,000 Collections to date 271,000 807,000 1,424,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017...

  • Exercise 18-33 During 2017, Marin Company started a construction yob with a contract price of $1,610,000....

    Exercise 18-33 During 2017, Marin Company started a construction yob with a contract price of $1,610,000. The job was completed in 2019. The following information is available, 2017 2018 2019 Costs incurred to date $405,900 $766,500 51,076,000 Estimated costs to complete 584,100 328,500 Brings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage of completion method is used. Gross proft recognized in 2017 Gross...

  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

  • During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job...

    During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $380,000 $847,770 $1,069,000 Estimated costs to complete 620,000 253,230 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 272,000 812,000 1,418,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...

  • During 2020, Pearl Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Pearl Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 –0– Billings to date 301,000 892,000 1,590,000 Collections to date 268,000 816,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...

  • During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job...

    During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $380,000 $847,770 $1,069,000 Estimated costs to complete 620,000 253,230 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 272,000 812,000 1,418,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...

  • During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT