Question

Homework - Chapter 2 Saved 5 Exercise 2-10 Applying Overhead Cost to a Job [LO2-2] 14.28 points Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,200 for direct materials, $8,700 for direct labor, and $5,655 for overhead on its job cost sheet Job W, which is still in process at year-end, shows charges of $2,900 for direct materials and $4,100 for direct labor. Required: 1a. Should any overhead cost be applied to Job W at year-end? eBook Yes O No Print References b. How much overhead cost should be applied to Job W? Overhead cost i. This is a numeric cell, so please enter numbers only. 2. How will the costs included in Job Ws job cost sheet be reported within Sigma Corporations financial statements at the end of the year? O Raw Materials Work-in-Process O Finished Goods

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1a) Yes, overhead should be applied on Job W

1b) Overhead rate = 5655/8700 = 65% of direct labor cost

Overhead cost on job W = 4100*65% = $2665

2) Job W should be included in financial statement as work in process

So answer is b) Work in process

Add a comment
Know the answer?
Add Answer to:
Homework - Chapter 2 Saved 5 Exercise 2-10 Applying Overhead Cost to a Job [LO2-2] 14.28...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 2-10 Applying Overhead Cost to a Job [LO2-2] Sigma Corporation applies overhead cost to jobs...

    Exercise 2-10 Applying Overhead Cost to a Job [LO2-2] Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,200 for direct materials, $9,700 for direct labor, and $5,820 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $3,600 for direct materials and $5,800 for direct labor. Required: 1a. Should any overhead...

  • Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V,...

    Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,200 for direct materials, $9,900 for direct labor, and $6,435 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $2,900 for direct materials and $4,800 for direct labor. Required: 1a. Should any overhead cost be applied to Job W at year-end? Yes...

  • Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V,...

    Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,700 for direct materials, $9,600 for direct labor, and $5,376 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $2,900 for direct materials and $4,100 for direct labor. Check my work 3 Required: la. Should any overhead cost be applied to Job...

  • Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost

    Exercise 2-10 Applying Overhead Cost to a Job (LO2-2) Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,500 for direct materials, $9,000 for direct labor, and $5,130 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $3,300 for direct materials and $5.500 for direct labor. Required: 1a. Should any overhead cost be applied...

  • Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost Job V,...

    Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost Job V, which was started and completed during the Current period, shows charges of $6.200 for direct materials. $8.200 for direct labor, and $5.822 for overhead on its job cost sheet Job W, which is still in process at year-end, shows charges of $4,300 for direct materials and $5,100 for direct labor Required: 10. Should any overhead cost be applied to Job Wat year-end? Yes O...

  • 10 Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job...

    10 Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $6.700 for direct materials. $8,100 for direct labor, and $5.994 for overhead on its job cost sheet Job W, which is still in process at year-end, shows charges of $3,200 for direct materials and $5.800 for direct labor. Required: 1a. Should any overhead cost be applied to Job Wat year-end? Yes...

  • Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V,...

    Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,000 for direct materials, $8,000 for direct labor, and $6,000 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $2,500 for direct materials and $4,000 for direct labor. Required: 1a. Should any overhead cost be applied to Job W at year-end? 1b. How much overhead...

  • Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V,...

    Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,700 for direct materials, $9.900 for direct labor, and $5,742 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $2,900 for direct materials and $4,700 for direct labor. Required: 1a. Should any overhead cost be applied to Job Wat year-end? Yes No...

  • Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V,...

    Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $6,800 for direct materials, $9,500 for direct labor, and $5,985 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $4,200 for direct materials and $4,800 for direct labor. Required: 1a. Should any overhead cost be applied to Job W at year-end? Yes...

  • Show how to get to the answers please Sigma Corporation applies overhead cost to jobs on...

    Show how to get to the answers please Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,300 for direct materials, $9,300 for direct labor, and $6,138 for overhead on its job cost sheet. Job W which is still in process at year-end, shows charges of $4,200 for direct materials and $5,100 for direct labor. Required: 1a. Should any overhead cost...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT