Question

A project has multiple IRRs because of multiple inflows and outflows throughout the project's life. Which...

A project has multiple IRRs because of multiple inflows and outflows throughout the project's life. Which should you use in determining whether or not to accept the project, the highest, the lowest, or the intermediate IRR? Discuss your answer

0 0
Add a comment Improve this question Transcribed image text
Answer #1

In case of a project with single IRR, it is always preferred to accept the project if IRR is greater than required rate of return or hurdle rate. In case of a project with multiple IRR,  it is not exactly clear which IRR to compare with the hurdle rate. Multiple IRR rates defines the range (Highest,lowest or intermediate) of IRR within which NPV is positive so in this situation of multiple IRR and invalid assumption of IRR i.e. reinvestment of cash flow at a rate equal to IRR, it is always preferred to take your decision related to project using NPV method

Add a comment
Know the answer?
Add Answer to:
A project has multiple IRRs because of multiple inflows and outflows throughout the project's life. Which...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which...

    MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which costs $2 million. Cash inflows of $12.5 million would occur at the end of Year 1. The land must be returned to its natural state at a cost of $11 million, payable at the end of Year 2. Plot the project's NPV profile. The correct sketch is -Select-ABCDItem 1 . Should the project be accepted if WACC = 10%? -Select-YesNoItem 2 Should the project...

  • MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which...

    MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which costs $2.5 million. Cash inflows of $13 million would occur at the end of Year 1. The land must be returned to its natural state at a cost of $11 million, payable at the end of Year 2. a. Plot the project's NPV profile. B NEY NPV Miliens of Dulles Men of Dole 200 3000WACC) 80 200 300 400 WACC) 200 300 400 WACC)...

  • MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which...

    MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which costs $1.5 million. Cash inflows of $13.5 million would occur at the end of Year 1. The land must be returned to its natural state at a cost $11 million, payable at the end of Year 2. a. Plot the project's NPV profile. NPV i Millions of Dollas) NPV (Millions of Dollas) | *** ****** NPV Millions of Dollar) | ********* * *** non...

  • о от сорта със MULTIPLE IRRS AND MIRR A mining company is deciding whether to open...

    о от сорта със MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which costs $2 million. Cash inflows of $13.5 million would occur at the end of Year 1. The land must be returned to its natural state at a cost of $12 million, payable at the end of Year 2. a. Plot the project's NPV profile. T NPV (Mors Mort of Dolea) 1 MUNDO! TO OUNG 05 TO 200 300 400 WACC(%)...

  • If a project has _________ IRR(s), we should __________ . Assume this project is competing with...

    If a project has _________ IRR(s), we should __________ . Assume this project is competing with other projects that the firm is evaluating. A. a single; accept the project any time IRR > WACC B. multiple, assume that the highest IRR is correct. C. multiple, assume that the lowest IRR is correct. D. multiple, assume that the average of the IRR’s is a reasonable estimate. E. multiple, we should not rely on the IRR criterion.

  • You are considering a project for which you estimate a large initial cash outflow, followed by...

    You are considering a project for which you estimate a large initial cash outflow, followed by several years of cash inflows. During your capital budgeting analysis, you realize that a state environmental law will require you to remove all underground equipment at the end of the project. Assume that the cost of complying with this law makes your Incremental Free Cash Flow number in the final year of the project negative. How might this change your use and/or interpretation of...

  • A project has an initial cost of $44,700, expected net cash inflows of $15,000 per year...

    A project has an initial cost of $44,700, expected net cash inflows of $15,000 per year for 12 years, and a cost of capital of 13%. What is the project's NPV? (Hint: Begin by constructing a time line.) Do not round your intermediate calculations. Round your answer to the nearest cent. A project has an initial cost of $60,000, expected net cash inflows of $14,000 per year for 9 years, and a cost of capital of 8%. What is the...

  • A mining company is deciding whether to open a strip mine, which costs $2 million. Cash...

    A mining company is deciding whether to open a strip mine, which costs $2 million. Cash inflows of $13 million would occur at the end of Year 1. The land must be returned to its natural state at a cost of $11.5 million, payable at the end of Year 2. Plot the project's NPV profile.     a. The correct sketch is -Select A, B, C, D Should the project be accepted if WACC = 10%? -Select-Yes or No Should the...

  • A proposed capital budgeting project has initial cash outflows, followed by cash inflows, which are then...

    A proposed capital budgeting project has initial cash outflows, followed by cash inflows, which are then followed by more cash outflows. We call these types of cash flows: Group of answer choices None of these are correct. non-normal cash flows. mutually-exclusive cash flows. normal cash flows. reflective cash flows.

  • If the net cash flows for a project change signs more than once a. The project...

    If the net cash flows for a project change signs more than once a. The project should never be accepted b. The project may have more than one IRR; the highest IRR should be used to determine whether to accept the project c. The project may have more than one IRR; the NPV method should be used to determine whether to accept the project d. All projects should be ranked according to their payback period to determine which project should...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT