Items Land Buildings Other accounts
Excavation cost for new building $23,000
Architect fees for building plans 33,000
Full payment to Building contractor 640,000
Cost of Real estate purchased as a plant site 280,000
Cost of parking lots and driveways 29,000
Accrued real estate taxes paid 3,170
Installation cost of fences 6,800
Cost of demolishing building 31,000
Real estate paid for the current year 6,400
Less: proceeds from salvage of demolished building -12,000
Total $302,170 $696,000 $42,200

Kindly give thumbs up if u like my answer...thanks!!!!

Add a comment
Know the answer?
Add Answer to:
Problems: Set A 19.1A (LOI), Peete Company was organized on January 1. During the first year...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT