Question

Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended...

Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended 30 November 2018 was based on 200,000 units of output. Each unit requires two standard hours of manufacturing labor for completion. Total overhead was budgeted at $900,000 for the year, and the budgeted fixed overhead rate was $3 per unit of output. Both fixed and variable overhead are allocated to the product on the basis of direct manufacturing labor-hours. The actual data for the fiscal year ended 30 November 2018 are as follows: actual production in units, 198,000; actual direct manufacturing labor-hours, 440,000; actual variable overhead, $352,000; actual fixed overhead, $575,000.

The Cyberdyne fixed overhead spending variance for FY2018 is closest to:

a.

$19,000 F

b.

$19,000 U

c.

$25,000 F

d.

$25,000 U

The Cyberdyne output level variance for FY2018 is closest to:

a.

$25,000 F

b.

$55,000 U

c.

$19,000 F

d.

$6,000 U

The Cyberdyne variable overhead spending variance for FY2018 is closest to:

a.

$20,000 U

b.

$20,000 F

c.

$22,000 U

d.

$22,000 F

The Cyberdyne variable overhead efficiency variance for FY2018 is closest to:

a.

$33,000 U

b.

$35,520 F

c.

$66,000 U

d.

$35,200 U

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

working notes:

First calculate the budgeted fixed and variable overhead

budgeted fixed overhead = $3 per unit of output

so budgeted fixed overhead = 200,000 units \times $3 per unit

= $600,000

Total budgeted overhead = $900,000

Budgeted Variable Overhead = Total budgeted overhead - Budgeted Fixed Overhead

   = $900,000 - $600,000

= $300,000

now we calculate standard hours for actual output

Standard Hours for Actual Output = 198,000 units \times 2 hours per unit

=$396,000

Now we calculate Budgeted overhead rate

Budgeted overhead rate =Budgeted Overhead \div Budgeted hours

= $900,000 \div *400,000 hours

= $2.25 per hour

*200,000 units \times 2 hours per unit = 400,000 hours

1.  Cyberdyne fixed overhead spending variance for financial year 2018 is closest to

Fixed overhead spending variance = Budgeted fixed overhead - Actual fixed Overhead

  =$600,000 - $575,000

= $25,000(F)

so (C) option is correct

2. Cyberdyne Output level Variance for FY 2018

Output level Variance = (Actual unit Produced - Budgeted Unit Produced) \times Budgeted Overhead Rate

= (198,000 units - 200,000 units) \times $2.25

   = $4,500(U)

so (D) option is correct

According to options The Closest answer is $6,000(U) but the exact answer is $4,500(U)

3. Cyberdyne Variable Overhead Spending variance for FY 2018

Variable Overhead Spending Variance = (Standard variable absorption rate - Actual Variable Rate) \times Actual hours

= (0.75a - 0.80b) \times 440,000 hours

= -0.05 \times 440,000 hours

= $22,000 (U)

a. $300,000 \div 400,000 hours = $0.75

b. $352,000 \div 440,000 hours = $0.80

Option (C) is correct

4. cyberdyne Variable Overhead Effeciency Variance

Variable Overhead Effeciency Variance = (Standard Hours for Actual Output - Actual Hours ) \times standard variable overhead rate

= (396,000 units -440,000 units) \times $0.75

= - 44,000 units \times $0.75

= $33,000(U)

so (A) Option is Correct

Add a comment
Know the answer?
Add Answer to:
Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended...

    Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended 30 November 2018 was based on 200,000 units of output. Each unit requires two standard hours of manufacturing labor for completion. Total overhead was budgeted at $900,000 for the year, and the budgeted fixed overhead rate was $3 per unit of output. Both fixed and variable overhead are allocated to the product on the basis of direct manufacturing labor-hours. The actual data for the...

  • Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended...

    Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended 30 November 2018 was based on 200,000 units of output. Each unit requires two standard hours of manufacturing labor for completion. Total overhead was budgeted at $900,000 for the year, and the budgeted fixed overhead rate was $3 per unit of output. Both fixed and variable overhead are allocated to the product on the basis of direct manufacturing labor-hours. The actual data for the...

  • ABC Company has the following standards and flexible budget data: Standard Variable Overhead Rate $5.40 Per...

    ABC Company has the following standards and flexible budget data: Standard Variable Overhead Rate $5.40 Per direct labour hour Standard quantity of direct labor $1.80 hours per unit of output Budgeted fixed overhead rate $100,000 Budgeted Output 25,000 units Standard Variable Overhead $10.80 per unit Standard Fixed Overhead $3.60 per unit Actual Results for November are given below: Actual Output 30,000 units Actual variable overhead $360,000 Actual Fixed Overhead $106,000 Actual Direct Labor 56,000 hours REQUIRED: A) Variable manufacturing overhead...

  • 1. Colina Production Company uses a standard costing system. The following information pertains to the current...

    1. Colina Production Company uses a standard costing system. The following information pertains to the current year. Direct labor hours is the driver used to assign overhead costs to products. Actual production 5,500 units Actual factory overhead costs ($16,500 is fixed) $40,125 Actual direct labor costs (11,250 hours) $131,625 Standard direct labor for 5,500 units: Standard hours allowed 11,000 hours Labor rate $12.00 The factory overhead rate is based on an activity level of 10,000 direct labor hours. Standard cost...

  • The Maxit Corporation has a standard costing system in which variable manufacturing overhead is assigned to...

    The Maxit Corporation has a standard costing system in which variable manufacturing overhead is assigned to production on the basis of standard machine-hours. The following data are available for July: Actual variable manufacturing overhead cost incurred: $25,700 Actual machine-hours worked: 3,000 hours Variable overhead rate variance: $5,520 U Total variable overhead spending variance: $7,700 U The variable overhead efficiency variance for July is: Multiple Choice $13,220 F $13,220 U $2,180 U $2,180 F Tharaldson Corporation makes a product with the...

  • Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total...

    Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2016. calculate the following variances: Material Price Variance Materials Quantity Variance Total Materials Variance...

  • Use the following information for the next three questions. Oak Company uses a standard costing system....

    Use the following information for the next three questions. Oak Company uses a standard costing system. Manufacturing overhead costs are applied to products on the basis of direct labor hours. The standard cost card shows that 5 direct labor hours at the hourly rate of $25 per hour are required per unit of product. Oak Company had the following data for March: Actual Budgeted Units produced 22,000 20,000 Direct labor hours 105,000 100,000 Variable overhead costs $91,000 $80,000 Fixed overhead...

  • Wilson Products uses standard costing. It allocates manufacturing overhead (both variable and fixed) to products on...

    Wilson Products uses standard costing. It allocates manufacturing overhead (both variable and fixed) to products on the basis of standard direct manufacturing labor-hours (DLH). The actual costs, compared with the annual budget and 1/12 of the annual budget, are as follows: El (Click the icon to view the data.) More Info Requirement Wilson Products develops its manufacturing overhead rate from the current annualCalculate the following amounts for Wilson Products for May 2017 for 2017 is based on budgeted out1. Total...

  • Chojnowski Incorporated makes a single product-a cooling coil used in commercial retngerators. The company has a st...

    Chojnowski Incorporated makes a single product-a cooling coil used in commercial retngerators. The company has a standard cost system in which it applies overhead to this product based on the standard labor-hours allowed for the actual output of the period. Data concerning the most recent year appear below Budgeted (Planned) Overhead: Budgeted variable manufacturing overheadS 82,450 Budgeted fixed manufacturing overhead 325,975 25,000 units 20,000 units Budgeted production Actual production 1.70 DLH Standard Hours needed per Product Unit Actual variable manufacturing...

  • Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total...

    Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2016. Solve for: Variable Overhead Spending Variance Variable Overhead Efficiency Variance Variable Overhead Total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT