Question

Mr. S. Berlusconi, the finance manager of Zeffira Company ((ZC), is evaluating two mutually exclusive investment...

Mr. S. Berlusconi, the finance manager of Zeffira Company ((ZC), is evaluating two mutually exclusive investment projects, project L and project K. The expected life of project L is six years and that of project K is three years. ZC is planning to replicate investment project K for another three years.   The expected cash inflows and outflows of the projects are provided in the following table:

Project K

Project L

Year

Cash Flow

Year

Cash Flow

0

($25,000)

0

($30,000)

1

20,000

1

25,000

2

20,000

2

25,000

3

20,000

3

25,000

4

25,000

5

25,000

6

25,000

ZC uses a weighted average cost of capital of 12% for both projects.

  1. Which project do you advise Mr. Berlusconi to select using NPV, without adjustment for the life of the projects?
  2. To adjust for their life difference, you use the replacement chain and the Equivalent Annual Annuity (EAA). Which project do you advise Mr. Berlusconi to pick now?
  3. You must explain how you come up with answers in (a) and (b) in writing in 5 lines. Show your work.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Project K 1.12
a b a*b
Year Cashflow PV factor 12% [1/(1+r)]^n PV
0                               (25,000.00) 1.000                               (25,000.00)
1                                20,000.00 0.893                                17,857.14
2                                20,000.00 0.797                                15,943.88
3                                20,000.00 0.712                                14,235.60
Total 2.402                                23,036.63
NPV of project (a)                                23,036.63 $
Total PV factor (b) 2.402
EAA (a/b)                                   9,590.60 $
Project L 1.12
a b a*b
Year Cashflow PV factor 12% [1/(1+r)]^n PV
0                               (30,000.00) 1.000                               (30,000.00)
1                                25,000.00 0.893                                22,321.43
2                                25,000.00 0.797                                19,929.85
3                                25,000.00 0.712                                17,794.51
4                                25,000.00 0.636                                15,887.95
5                                25,000.00 0.567                                14,185.67
6                                25,000.00 0.507                                12,665.78
Total 4.111                                72,785.18
NPV of project (a)                                72,785.18 $
Total PV factor (b) 4.111
EAA (a/b)                                17,704.98 $
Project K Project L
NPV                                23,036.63                                       72,785.18
EAA                                  9,590.60                                       17,704.98
1. Considering NPV, Project L has more NPV. So it should be undertaken
2. Considering EAA, Project L has more annual inflow tha project K, SO project L should be undertaken

More NPV give more value to the company

But we have to consider the life of project also.

If two projects have different life, then NPV is not suitable.

Then we have to find out EAA.

Notes:
EAA = NPV / total pv factor
In total PV factor, 0th year factor will not be considered
NPV = Discounted inflow - Initial investment
Add a comment
Know the answer?
Add Answer to:
Mr. S. Berlusconi, the finance manager of Zeffira Company ((ZC), is evaluating two mutually exclusive investment...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 19. You are evaluating two mutually exclusive projects, A and B, with equal investment of $5,000,...

    19. You are evaluating two mutually exclusive projects, A and B, with equal investment of $5,000, required rate of return of 8%, and following cash flows in years 1-3 (for project A) and 1-5 (for project B) Year 1 Year 2 Year 3 Year 4 Year 5 Project A 18001700 3200 Project B 1200 1280 1350 1400 2200 Which project will you prefer and why? A. Project A since it reports higher NPV of 806.5 B. Project B since it...

  • Mulroney Corp. is considering two mutually exclusive projects. Both require an initial investment of $10,000, and...

    Mulroney Corp. is considering two mutually exclusive projects. Both require an initial investment of $10,000, and their risks are average for the firm. Project X has an expected life of 2 years with after-tax cash inflows of $6,000 and $8,000 at the end of Years 1 and 2, respectively. Project Y has an expected life of 4 years with after-tax cash inflows of $4,000 at the end of each of the next 4 years. The firm

  • (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive...

    (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A Project B Cash Flow Cash Flow $(102,000) $(102,000) 40,000 40.000 40.000 40,000 0 40,000 215,000 If the appropriate discount rate on these projects is 9 percent, which would be chosen and why? The NPV of Project Ass (Round to the nearest cont.)

  • 13. Problem 12.13 (Unequal Lives) eBook Haley's Crockett Designs Inc. is considering two mutually exclusive projects....

    13. Problem 12.13 (Unequal Lives) eBook Haley's Crockett Designs Inc. is considering two mutually exclusive projects. Both projects require an initial investment of $11,000 and are typical average-risk projects for the firm. Project A has an expected life of 2 years with after-tax cash inflows of $6,000 and $10,000 at the end of Years 1 and 2, respectively. Project B has an expected life of 4 years with after-tax cash inflows of $5,000 at the end of each of the...

  • 9. Unequal project lives Globex Corp. has to choose between two mutually exclusive projects. If it...

    9. Unequal project lives Globex Corp. has to choose between two mutually exclusive projects. If it chooses project A, Globex Corp. will have the opportunity to make a similar investment in three years. However, if it chooses project B, it will not have the opportunity to make a second investment. The following table lists the cash flows for these projects. If the firm uses the replacement chain (common life) approach, what will be the difference between the net present value...

  • Projects A and B are mutually exclusive. Project A costs $10,000 and is expected to generate...

    Projects A and B are mutually exclusive. Project A costs $10,000 and is expected to generate cash inflows of $4,000 for 4 years. Project B costs $10,000 and is expected to generate a single cash flow in year 4 of $20,000. The cost of capital is 17.5%. What is the NPV of the project you should accept? Group of answer choices $865.73 $492.49 $3,911.49 $354.94

  • Newtown Corp. has to choose between two mutually exclusive projects. If it chooses project A, Newtown...

    Newtown Corp. has to choose between two mutually exclusive projects. If it chooses project A, Newtown Corp. will have the opportunity to make a similar investment in three years. However, if it chooses project B, it will not have the opportunity to make a second investment. The following table lists the cash flows for these projects. If the firm uses the replacement chain (common life) approach, what will be the difference between the net present value (NPV) of project A...

  • Axis Corp. is considering an investment in the best of two mutually exclusive projects. Project Kelvin...

    Axis Corp. is considering an investment in the best of two mutually exclusive projects. Project Kelvin involves an overhaul of the existing system; it will cost $35,000 and generate cash inflows of $20,000 per year for the next 3 years. Project Thompson involves replacement of the existing system; it will cost $220,000 and generate cash inflows of $50,000 per year for 6 years. Using a cost of capital of 11%, calculate each project's NPV, and make a recommendation based on...

  •    Yong Importers, an Asian import company, is evaluating two mutually exclusive projects, A and B. The...

       Yong Importers, an Asian import company, is evaluating two mutually exclusive projects, A and B. The relevant cash flows for each project are given in the table below. The cost of capital for use in evaluating each of these equally risky projects is 10 percent. initial investment               project a                   project b                                            $350,000                  $425,000 year                                              cash inflows (cf) 1                                         140,000                  175,000 2                                         165,000                   150,000 3                                          190,000                  125,000 4                                                                         100,000 5                                                                         75,000 6                                                                         50,000 Which project should be chosen on the basis of...

  • 4. Unequal project lives Galaxy Corp. has to choose between two mutually exclusive projects. If it...

    4. Unequal project lives Galaxy Corp. has to choose between two mutually exclusive projects. If it chooses project A, Galaxy Corp. will have the opportunity to make a similar investment in three years. However, if it chooses project B, it will not have the opportunity to make a second investment. The following table lists the cash flows for these projects. If the firm uses the replacement chain (common life) approach, what will be the difference between the net present value...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT