Question

A static budget, based upon production of 10,000 units, showed an estimated direct labor budget of...

A static budget, based upon production of 10,000 units, showed an estimated direct labor budget of $30,000 and depreciation budget of $20,000. Direct labor costs are fully variable. The actual direct labor and depreciation costs were $28,000 and $19,000 for 8,000 units.

Which total amount should be shown in the flexible budget for direct labor and depreciation costs?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Flexible Budget Cost for Direct Labor =($30000 /10000 units) x 8000 actual units = $ 24,000

Flexible Budget Cost for Depreciation = Fixed cost = Same as Budgeted = $ 20,000

Total Flexible Budget cost = 24000 + 20000 = $ 44,000

Add a comment
Know the answer?
Add Answer to:
A static budget, based upon production of 10,000 units, showed an estimated direct labor budget of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT