Question

Milner Manufacturing uses a job-order costing system. On May 1, the company has a balance in Work in Process Inventory of $3,
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Journal entry

No General Journal Debit Credit
1 Work in process 10650
Manufacturing overhead 1160
Direct material 11810
(To record material requisition)
2 Work in process 13150
Manufacturing overhead 1680
Wages payable 14830
(To record labor)
3 Work in process (13150*60%) 7890
Manufacturing overhead 7890
(To record overhead assigned)
4 Finished goods 7702
Work in process 7702
(To record completion)
Add a comment
Know the answer?
Add Answer to:
Milner Manufacturing uses a job-order costing system. On May 1, the company has a balance in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Milner Manufacturing uses a job-order costing system. On May 1, the company has a balance in...

    Milner Manufacturing uses a job-order costing system. On May 1, the company has a balance in Work in Process Inventory of $3,800 and two jobs in process: Job No. 429 $2,120, and Job No. 430 $1,680. During May, a summary of source documents reveals the following: Job Number Labour Time Tickets 429 Materials Requisition Slips $2,350 39 3,830 $2,020 430 3,410 7.720 4.470 431 General use $10,650 1.160 $11.810 $13,150 1,680 $14,830 Milner Manufacturing applies manufacturing overhead to jobs at...

  • ACO2 Lamar Manufacturing uses a job order cost accounting system. On May 1, the company has a balance in Work in Proces...

    ACO2 Lamar Manufacturing uses a job order cost accounting system. On May 1, the company has a balance in Work in Process Inventory of $3,200 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,200. During May, a summary of source documents reveals the following. Materials Requisition Slips Labor Time Tickets Job Number 429 430 431 General use $2,500 3,600 4,400 $2,200 3,000 7,600 $10,500 1,800 $12,300 $12,800 1,950 $14,750 Lamar Manufacturing applies manufacturing overhead to...

  • Stine Company uses a job order cost system. On May 1, the company has a balance...

    Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $2,500 $1,900 430 3,500 3,000 431 4,400 $10,400 7,600 $12,500 General use 800 1,200 $11,200 $13,700 Stine Company applies manufacturing overhead to jobs at...

  • Mint Manufacturing uses a job order cost accounting system. On May 1, the company has a...

    Mint Manufacturing uses a job order cost accounting system. On May 1, the company has a balance in Work in Process Inventory of $5,500 and two jobs in process: Job No. 429, $3,000 and Job No. 430, $2,500. During May, a summary of source documents reveals the following:      For                                               Materials Requisition Slips             Labor Time Tickets             Job No. 429                                             $ 3,500                                      $ 4,400             Job No. 430                                                 2,600                                          3,400             Job No. 431                                                 3,400                                          4,200             Job No. 432                                                 3,000                                          4,000...

  • Stine Company uses a job order cost system. On May 1, the company has a balance...

    Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,240 and two jobs in process: Job No. 429 $2,580, and Job No. 430 $1,660. During May, a summary of source documents reveals the following Job Number 429 Materials Requisition Slips $3,040 3.680 4,710 $11.430 940 430 Labor Time Tickets $2,100 3,300 8,100 $13,500 1.360 $14,860 431 General use $12,370 Stine Company applies manufacturing overhead to jobs at...

  • E16-2 Stine Company uses a job order cost system. On May 1, the company has a...

    E16-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number 429 430 431 General use Materials Requisition Slips $2,500 3,500 4,400 $10,400 800 $11,200 Labor Time Tickets $1,900 3,000 7,600 $12,500 1,200 $13,700 Stine Company applies manufacturing overhead to jobs...

  • Exercise 2-2 Stine Company uses a job order cost system. On May 1, the company has...

    Exercise 2-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,920 and two jobs in process: Job No. 429 $2,600, and Job No. 430 $1,320. During May, a summary of source documents reveals the following. Materials Labor Time Job Number Requisition Slips Tickets 429 $3,040 $2,300 430 4,020 3,400 431/ 4,740 $11,800 7,900 $13,600 General use 900 1,310 $12,700 $14,910 Stine Company applies manufacturing overhead to...

  • Stine Company uses a job order cost system. On May 1, the company has a balance...

    Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,610 and two jobs in process: Job No. 429 $2,140, and Job No. 430 $1,470. During May, a summary of source documents reveals the following Materials Requisition Slips Labor Time Tickets Job Number 429 430 431 General use $2,940 4,090 4,920 $2,060 3,600 8,060 $11,950 930 $12,880 $13,720 1,590 $15,310 Stine Company applies manufacturing overhead to jobs at...

  • E2-2 Stine Company uses a job order cost system. On May 1, the company has a...

    E2-2 Stine Company uses a job order cost system. On May 1, the company has a balance Prepare in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and manugfa Job No. 430 $1,500. During May, a summary of source documents reveals the following. (LO 1, 2 Materials Labor Time Tickets Job Number 429 430 431 General use Requisition Slips $2,500 3,500 4,400 $1,900 3,000 7,600 $10,400 800 $11,200 $12,500 1,200 $13,700 Stine Company...

  • Stine Company uses a job order cost system. On May 1, the company has a balance...

    Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,240 and two jobs in process: Job No. 429 $2,580, and Job No. 430 $1,660. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $3,040 $2,100 430 3,680 3,300 431 4,710 $11,430 8,100 $13,500 General use 940 1,360 $12,370 $14,860 Stine Company applies manufacturing overhead to jobs at...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT