Question

Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...

Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company’s products follows.

Standard: Est. production volume, 3000 units
   Direct-material cost, $25 per Unit
   Direct Labor per unit, 3 hrs at $12 per hr
Enhanced: Est. production volume, 4000 units
   Direct material cost, $40 per Unit
   Direct Labor per unit, 4 hrs at $12 per hr

Ontario’s overhead of $800,000 can be identified with three major activities: order processing ($150,000), machine processing ($560,000), and product inspection ($90,000). These activities are driven by number of orders processed, machine hours worked, and inspection hours, respectively. Data relevant to these activities follow.
               Orders Processed   Machine Hrs Worked       Inspection Hrs
Standard                300           18000               2000
Enhanced               200           22000               8000
500           40000               10000

Top management is very concerned about declining profitability despite a healthy increase in sales volume. The decrease in income is especially puzzling because the company recently undertook a massive plant renovation during which new, highly automated machinery was installed—machinery that was expected to produce significant operating efficiencies.

3. Ontario’s selling prices are based heavily on cost.
   a) by using direct-labor hrs as an application base, which product is overcosted and which product is undercosted? Calculate the amount for the cost distortion for each product. Be sure to show formulas in within the cells.
   b) Is it possible that overcosting and undercosting (i.e., cost distortion) and the subsequent determination of selling prices are contributing to the company’s profit woes? Explain.

DATA INPUT

Anticipated overhead

Anticipated direct labor

hours

Rate

Standard

Estimated production volume

units

Direct-material cost

per unit

Direct labor per unit

hours at

per hour

Enhanced

Estimated production volume

units

Direct-material cost

per unit

Direct labor per unit

hours at

per hour

Order

Machine

Product

Processing

Processing

Inspection

Overhead

Orders

Machine Hours

Inspection

Processed

Worked

Hours

Standard

Enhanced

Total

0 0
Add a comment Improve this question Transcribed image text
Answer #1

As per existing method overhead allocation is carried out on the base of labour hours, so let us calculate overhead allocation rate per labour hour :

Calculation of overhead allocation per labour hour

1 Total Overhead         800,000
2 Total Labour Hours
3 Standard (3000*3)             9,000
4 Enhanced (4000*4)           16,000           25,000
5 Overhead allocation rate per labour hour (1/5)                   32

On the basis of overhead allocation rate per labour hour let us work out total overhead allocation product wise :

Existing Overhead allocation on labour hour basis

Particulars Standard Enhanced
6 Labour Hour (As per 3,4)             9,000           16,000
7 Overhead allocation per hour (As per 5)                   32                  32
8 Total overhead allocation (6*7)         288,000         512,000

We have provided 3 different activities which actually contributes overhead, let us calculate overhead rate for respective activity :

Overhead rate calculation as per Activity wise

Activities Order processing Machine Processing Inspection
9 Total Cost         150,000         560,000           90,000
10 Total hours                 500           40,000           10,000
11 Activity rate per hour (9/10)                 300                  14                     9

The overhead is actually determined by respective activity unit & hence that will result in more appropriate allocation which is worked out as under

Overhead allocation as per activity rate

Standard
Order processing Machine Processing Inspection Total
12 Hours                 300           18,000             2,000
13 Rate (As per 11)                 300                  14                     9
14 Overhead allocation (12*13)           90,000         252,000           18,000 360,000
Enhanced
Order processing Machine Processing Inspection Total
15 Hours                 200           22,000             8,000
16 Rate (As per 11)                 300                  14                     9
17 Overhead allocation (15*16)           60,000         308,000           72,000        440,000

The comparison of overhead allocation under both method provide us under allocation and over allocation. The figure reported in bracket shows over allocation :

Comparison of total overhead allocation under both method   

Products Standard Enhanced
18 Overhead allocation on labour hour basis (As per 8)         288,000         512,000
19 Overhead allocation on activity wise hour basis (As per 14 & 17)         360,000         440,000
20 (Over allocation) / Under allocation (19-18)           72,000         (72,000)

Q.1  a) by using direct-labor hrs as an application base, which product is overcosted and which product is undercosted? Calculate the amount for the cost distortion for each product. Be sure to show formulas in within the cells.

Response to Q.1 : As per above calculation Rs.72000 is over allocated to enhanced product and Rs.72000 under allocated to Standard product

Q.2 : Is it possible that overcosting and undercosting (i.e., cost distortion) and the subsequent determination of selling prices are contributing to the company’s profit woes? Explain.

Response to Q.2 : Let us calcuate overhead rate per product under both method

Comparison of Overhead allocation per Unit

Products Standard Enhanced
21 Volume             3,000             4,000
22 Overhead allocation per unit under labour hour basis (18/21)                   96                128
23 Overhead allocation per unit under activity wise basis (19/21)                 120                110
24 Difference (23-22)                   24                 (18)

The selling price of product is determined on the basis of cost incurred. Especially the selling price of Enhanced would be distorted when calculated on existing overhead allocation on labour hour basis because it considers cost lower by 24 & hence even volume of standard increases it will result into lower profitability  

Please provide feedback on this answer by comment and voting positive.

Add a comment
Know the answer?
Add Answer to:
Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...

    Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company’s products follows. Standard: Est. production volume, 3000 units                     Direct-material cost, $25 per Unit                     Direct Labor per unit, 3 hrs at $12 per hr Enhanced: Est. production volume, 4000 units                      Direct material cost, $40 per Unit                     ...

  • Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...

    Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. points Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour eBook Enhanced: Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit, 4 hours at...

  • Ontario, Inc. manufactures two products, Standard and Enhanced, and applies Overhead on the basis of direct-labor...

    Ontario, Inc. manufactures two products, Standard and Enhanced, and applies Overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. points Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour eBook Enhanced: Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit, 4 hours at...

  • Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...

    Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. 5 points Standard: Estimated production volume, 3.000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour eBook Enhanced: Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit. 4 hours...

  • Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...

    Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. 5 points Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour eBook Enhanced Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit, 4 hours...

  • Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...

    Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour Enhanced: Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit, 4 hours at $12 per...

  • Ontario, Inc, manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...

    Ontario, Inc, manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour Enhanced Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit 4 hours at $12 per...

  • Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...

    Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour Enhanced Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit 4 hours at $12 per...

  • QUESTION 1 (25 marks) Nilam Sdn. Bhd. manufactures two products, Standard and Enhanced, and applies overhead...

    QUESTION 1 (25 marks) Nilam Sdn. Bhd. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. The anticipated overhead and direct labor time for the upcoming period is RM800,000 and RM25,000 hours respectively. The information about the company's products follows: Estimated production volume Direct material cost Direct labor per unit Standard 3,000 units RM 25 per unit 3 hours at RM12 per hour Enhanced 4,000 units RM 40 per unit 4 hours at RM12...

  • (25 marks) Nilam Sdn. Bhd. manufactures two products, Standard and Enhanced, and applies overhead on the...

    (25 marks) Nilam Sdn. Bhd. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. The anticipated overhead and direct labor time for the upcoming period is RM800,000 and RM25,000 hours respectively. The information about the company's products follows: Estimated production volume Direct material cost Direct labor per unit Standard 3,000 units RM 25 per unit 3 hours at RM12 per hour Enhanced 4,000 units RM 40 per unit 4 hours at RM12 per hour...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT