Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company’s products follows.
Standard: Est. production volume, 3000 units
Direct-material cost, $25 per Unit
Direct Labor per unit, 3 hrs at $12 per hr
Enhanced: Est. production volume, 4000 units
Direct material cost, $40 per Unit
Direct Labor per unit, 4 hrs at $12 per hr
Ontario’s overhead of $800,000 can be identified with three
major activities: order processing ($150,000), machine processing
($560,000), and product inspection ($90,000). These activities are
driven by number of orders processed, machine hours worked, and
inspection hours, respectively. Data relevant to these activities
follow.
Orders Processed Machine Hrs
Worked Inspection Hrs
Standard
300
18000
2000
Enhanced
200
22000
8000
500
40000
10000
Top management is very concerned about declining profitability
despite a healthy increase in sales volume. The decrease in income
is especially puzzling because the company recently undertook a
massive plant renovation during which new, highly automated
machinery was installed—machinery that was expected to produce
significant operating efficiencies.
3. Ontario’s selling prices are based heavily on cost.
a) by using direct-labor hrs as an application base,
which product is overcosted and which product is undercosted?
Calculate the amount for the cost distortion for each product. Be
sure to show formulas in within the cells.
b) Is it possible that overcosting and undercosting
(i.e., cost distortion) and the subsequent determination of selling
prices are contributing to the company’s profit woes?
Explain.
DATA INPUT |
||||
Anticipated overhead |
||||
Anticipated direct labor |
hours |
|||
Rate |
||||
Standard |
||||
Estimated production volume |
units |
|||
Direct-material cost |
per unit |
|||
Direct labor per unit |
hours at |
per hour |
||
Enhanced |
||||
Estimated production volume |
units |
|||
Direct-material cost |
per unit |
|||
Direct labor per unit |
hours at |
per hour |
||
Order |
Machine |
Product |
||
Processing |
Processing |
Inspection |
||
Overhead |
||||
Orders |
Machine Hours |
Inspection |
||
Processed |
Worked |
Hours |
||
Standard |
||||
Enhanced |
||||
Total |
As per existing method overhead allocation is carried out on the base of labour hours, so let us calculate overhead allocation rate per labour hour :
Calculation of overhead allocation per labour hour
1 | Total Overhead | 800,000 | ||
2 | Total Labour Hours | |||
3 | Standard (3000*3) | 9,000 | ||
4 | Enhanced (4000*4) | 16,000 | 25,000 | |
5 | Overhead allocation rate per labour hour (1/5) | 32 |
On the basis of overhead allocation rate per labour hour let us work out total overhead allocation product wise :
Existing Overhead allocation on labour hour basis
Particulars | Standard | Enhanced | |
6 | Labour Hour (As per 3,4) | 9,000 | 16,000 |
7 | Overhead allocation per hour (As per 5) | 32 | 32 |
8 | Total overhead allocation (6*7) | 288,000 | 512,000 |
We have provided 3 different activities which actually contributes overhead, let us calculate overhead rate for respective activity :
Overhead rate calculation as per Activity wise
Activities | Order processing | Machine Processing | Inspection | |
9 | Total Cost | 150,000 | 560,000 | 90,000 |
10 | Total hours | 500 | 40,000 | 10,000 |
11 | Activity rate per hour (9/10) | 300 | 14 | 9 |
The overhead is actually determined by respective activity unit & hence that will result in more appropriate allocation which is worked out as under
Overhead allocation as per activity rate
Standard | |||||
Order processing | Machine Processing | Inspection | Total | ||
12 | Hours | 300 | 18,000 | 2,000 | |
13 | Rate (As per 11) | 300 | 14 | 9 | |
14 | Overhead allocation (12*13) | 90,000 | 252,000 | 18,000 | 360,000 |
Enhanced | |||||
Order processing | Machine Processing | Inspection | Total | ||
15 | Hours | 200 | 22,000 | 8,000 | |
16 | Rate (As per 11) | 300 | 14 | 9 | |
17 | Overhead allocation (15*16) | 60,000 | 308,000 | 72,000 | 440,000 |
The comparison of overhead allocation under both method provide us under allocation and over allocation. The figure reported in bracket shows over allocation :
Comparison of total overhead allocation under both method
Products | Standard | Enhanced | |
18 | Overhead allocation on labour hour basis (As per 8) | 288,000 | 512,000 |
19 | Overhead allocation on activity wise hour basis (As per 14 & 17) | 360,000 | 440,000 |
20 | (Over allocation) / Under allocation (19-18) | 72,000 | (72,000) |
Q.1 a) by using direct-labor hrs as an application base, which product is overcosted and which product is undercosted? Calculate the amount for the cost distortion for each product. Be sure to show formulas in within the cells.
Response to Q.1 : As per above calculation Rs.72000 is over allocated to enhanced product and Rs.72000 under allocated to Standard product
Q.2 : Is it possible that overcosting and undercosting (i.e., cost distortion) and the subsequent determination of selling prices are contributing to the company’s profit woes? Explain.
Response to Q.2 : Let us calcuate overhead rate per product under both method
Comparison of Overhead allocation per Unit
Products | Standard | Enhanced | |
21 | Volume | 3,000 | 4,000 |
22 | Overhead allocation per unit under labour hour basis (18/21) | 96 | 128 |
23 | Overhead allocation per unit under activity wise basis (19/21) | 120 | 110 |
24 | Difference (23-22) | 24 | (18) |
The selling price of product is determined on the basis of cost incurred. Especially the selling price of Enhanced would be distorted when calculated on existing overhead allocation on labour hour basis because it considers cost lower by 24 & hence even volume of standard increases it will result into lower profitability
Please provide feedback on this answer by comment and voting positive.
Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...
Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company’s products follows. Standard: Est. production volume, 3000 units Direct-material cost, $25 per Unit Direct Labor per unit, 3 hrs at $12 per hr Enhanced: Est. production volume, 4000 units Direct material cost, $40 per Unit ...
Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. points Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour eBook Enhanced: Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit, 4 hours at...
Ontario, Inc. manufactures two products, Standard and Enhanced, and applies Overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. points Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour eBook Enhanced: Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit, 4 hours at...
Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. 5 points Standard: Estimated production volume, 3.000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour eBook Enhanced: Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit. 4 hours...
Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. 5 points Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour eBook Enhanced Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit, 4 hours...
Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour Enhanced: Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit, 4 hours at $12 per...
Ontario, Inc, manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour Enhanced Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit 4 hours at $12 per...
Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company's products follows. Standard: Estimated production volume, 3,000 units Direct-material cost, $25 per unit Direct labor per unit, 3 hours at $12 per hour Enhanced Estimated production volume, 4,000 units Direct-material cost, $40 per unit Direct labor per unit 4 hours at $12 per...
QUESTION 1 (25 marks) Nilam Sdn. Bhd. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. The anticipated overhead and direct labor time for the upcoming period is RM800,000 and RM25,000 hours respectively. The information about the company's products follows: Estimated production volume Direct material cost Direct labor per unit Standard 3,000 units RM 25 per unit 3 hours at RM12 per hour Enhanced 4,000 units RM 40 per unit 4 hours at RM12...
(25 marks) Nilam Sdn. Bhd. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. The anticipated overhead and direct labor time for the upcoming period is RM800,000 and RM25,000 hours respectively. The information about the company's products follows: Estimated production volume Direct material cost Direct labor per unit Standard 3,000 units RM 25 per unit 3 hours at RM12 per hour Enhanced 4,000 units RM 40 per unit 4 hours at RM12 per hour...