Question

Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1 Estimated variable manufacturing overhead $430,000
(215,000 x $2.00)
Estimated total fixed manufacturing overhead $3,655,000
Estimated total manufacturing overhead cost $4,085,000
Predetermined overhead rate = Estimated Total manufacturing overhead cost ÷ Estimated Total amount of the allocation
= $4,085,000 ÷ 215,000 labor-hours
= $19.00 per direct labor-hour
2 Direct materials $1,610
Direct labor cost $1,155
Manufacturing overhead $1,558
Total manufacturing cost $4,323
Add a comment
Know the answer?
Add Answer to:
Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses ajo border...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses ajo border costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 215,000 $3,655,000 2.00 Required 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold to the customer...

  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: company contine system with a Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 220,000 $ 3,960,000 $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was...

  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 165,000 $ 1,980,000 $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold to...

  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production 185,000 Fixed manufacturing overhead cost $2,960,000 Variable manufacturing overhead cost per machine-hour $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold to the...

  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: points Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 200,000 $ 2,800,000 $ 2.00 eBook Hint Print Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started,...

  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 210,000 $ 3,360,000 $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold to...

  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed and acturing overhead cost Variable manufacturing overhead cost per machine-hour $ $ 170.000 1,700,000 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold...

  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 220,000 $ 3,960,000 $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold to...

  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job- order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 165,000 $ 1,980,000 $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold...

  • Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...

    Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 165,000 $ 1,980,000 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold to the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT