Computation of NPV at a MARR of 10%
Year Expected Cash Flow Discounting Factor -10% Discounted Cash Flow
0 -$300 1.00 -$300
1 $120 0.909 $109
2 $150 0.826 $124
3 $150 0.751 $113
4 $110 0.683 $75
5 $100 0.621 $62
NPV $183

a) The NV of the project at a MARR of 10% is summation of Cash outflow and cash inflow i.e.$183.

b) Computation of variance of NPV

Variance = Square root of Standard Deviation (SD) i.e. (SD)2

Year Standard Deviation Discounting Factor -10% Discounted Standard Deviation
0 -$20 1.00 -$20
1 $10 0.909 $9.09
2 $15 0.826 $12.39
3 $20 0.751 $15.02
4 $25 0.683 $17.08
5 $30 0.621 $18.63
NPV $52.21

Variance of the NPV is $52.21 X $52.21= $2725.88

c) determination of the probability that the NPV exceed $200.

If the cash flows are normally distributed, the probability will computed in the following steps:

1. Compute Z value by using the following formula i.e. Z= (Desired Value - Expected Mean)/Standard Deviation

If the Z value is positive, it means that fallen in "Right Tail" and if value is negative that falls under "Left Tail'

2. Identify the table value corresponding to the computed Z value

3. The probability can be find with above Z value either deduct or add the Z value to 0.5

In the given question

The desired value is $200 , The expected mean is nothing but NPV i.e.arrived in a) - $183.

The standard deviation of the project is as follows:

Year Standard Deviation Discounting Factor -10% Discounted Standard Deviation
1 $10 0.909 $9.09
2 $15 0.826 $12.39
3 $20 0.751 $15.02
4 $25 0.683 $17.08
5 $30 0.621 $18.63
Standard Deviation $72.21

Z= (200-183)/72.21

=0.235 which is a positive falls under Right Tail

The table value of 0.235 is 0.09095, thi value to be added to 0.5 i.e.(0.5+0.09095)*100 = 59.095

The probability that NPV exceed $200 is 59.095%

Add a comment
Know the answer?
Add Answer to:
a) What is the NPV of the project at a MARR of 10%? b) What is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cornell Enterprises is considering a project that has the following cash flow and WACC data. What is the project's NPV?...

    Cornell Enterprises is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that a project's projected NPV can be negative, in which case it will be rejected. WACC: 10.00% Year 0 1 2 3 Cash flows -$1,050 $450 $460 $470

  • NPV A project has annual cash flows of $8,000 for the next 10 years and then...

    NPV A project has annual cash flows of $8,000 for the next 10 years and then $10,500 each year for the following 1 years. The R of this 20-year ro ec firm's WACC is 10%, what is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations s 12.45% f the

  • (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product...

    (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product line that currently consists of skateboards to include gas-powered skateboards, and you feel you can sell 12,000 of these per year for 10 years (after which time this project is expected to shut down with solar powered skateboards taking over). The gas skateboards would sell for $110 each with variable costs of $45 for each one produced, and annual fixed costs associated with production...

  • (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product...

    (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product line that currently consists of skateboards to include gas-powered skateboards, and you feel you can sell 9,000 of these per year for 10 years after which time this project is expected to shut down with solar-powered skateboards taking over). The gas skateboards would sell for $120 each with variable costs of $30 for each one produced, and annual fixed costs associated with production would...

  • x P12-14 (similar to) Question Help (Related to Checkpoint 12.1) (Calculating project cash flows and NPV)...

    x P12-14 (similar to) Question Help (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product line that currently consists of skateboards to include gas-powered skateboards, and you feel you can sell 8,000 of these per year for 10 years after which time this project is expected to shut down with solar-powered skateboards taking over). The gas skateboards would sell for $120 each with variable costs of $30 for each one produced, and annual...

  • Calculate the net present value ​(NPV​) for a 20​-year project with an initial investment of ​$10...

    Calculate the net present value ​(NPV​) for a 20​-year project with an initial investment of ​$10 comma 000 and a cash inflow of ​$2 comma 000 per year. Assume that the firm has an opportunity cost of 14​%. Comment on the acceptability of the project The​ project's net present value is ____

  • (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product...

    (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product line that currently consists of skateboards to include gas-powered skateboards, and you feel you can sell 7,000 of these per year for 10 years (after which time this project is expected to shut down with solar-powered skateboards taking over). The gas skateboards would sell for $80 each with variable costs of $50 for each one produced, and annual fixed costs associated with production would...

  • P12-14 (similar to) is Question Help (Related to Checkpoint 12.1) (Calculating project cash flows and NPV)...

    P12-14 (similar to) is Question Help (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product line that currently consists of skateboards to include gas-powered skateboards, and you feel you can sell 9,000 of these per year for 10 years (after which time this project is expected to shut down with solar-powered skateboards taking over). The gas skateboards would sell for $130 each with variable costs of $50 for each one produced, and annual...

  • (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product...

    (Related to Checkpoint 12.1) (Calculating project cash flows and NPV) You are considering expanding your product line that currently consists of skateboards to include gas-powered skateboards, and you feel you can sell 11,000 of these per year for 10 years after which time this project is expected to shut down with solar-powered skateboards taking over). The gas skateboards would sell for $70 each with variable costs of $50 for each one produced, and annual fixed costs associated with production would...

  • 3a, b and c please help 3. (30pt) A company considers the following 4 projects: Project...

    3a, b and c please help 3. (30pt) A company considers the following 4 projects: Project Capital Investment in year 0$10,000$6,000 A В С D $4,000 $8,000 -$2,000 $5,000 $1,600 $1,300$1,500 $4,000 $5,000 $8,000 $1,200 Net Cash Flow in 1 year Net Cash Flow in year 2 $4,000 $8,000 $10,200 Net Cash Flow in year The MARR is 10% per year. The company has a $20,000 budget for the capital investment in year 0. a) (10pt) Find NPV8 of 4...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT