Geraldine Consultants, Inc. is considering a project that has the following cash flows: Year Cash Flow 0 -$1,000 1 400 2 300 3 500 4 400 The company's WACC is 10%. What are the project's payback, internal rate of return, and net present value? Select one: a. Payback = 2.6, IRR = 21.22%, NPV = $300. b. Payback = 2.4, IRR = 21.22%, NPV = $260. c. Payback = 2.6, IRR = 24.12%, NPV = $300. d. Payback = 2.4, IRR = 10.00%, NPV = $600. e. Payback = 2.6, IRR = 21.22%, NPV = $260.
Year | Cash flows | Cumulative Cash flows |
0 | (1000) | (1000) |
1 | 400 | (600) |
2 | 300 | (300) |
3 | 500 | 200 |
4 | 400 | 600 |
Payback period=Last period with a negative cumulative cash flow+(Absolute value of cumulative cash flows at that period/Cash flow after that period).
=2+(300/500)
=2.6 years
Let irr be x%
At irr,present value of inflows=present value of outflows.
1000=400/1.0x+300/1.0x^2+500/1.0x^3+400/1.0x^4
Hence x=irr=21.22%(Approx).
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=400/1.1+300/1.1^2+500/1.1^3+400/1.1^4
=$1260(Approx)
NPV=Present value of inflows-Present value of outflows
=$1260-$1000
=$260(Approx)
Hence the correct option is:
e. Payback = 2.6, IRR = 21.22%, NPV = $260.
Geraldine Consultants, Inc. is considering a project that has the following cash flows: Year Cash Flow...
Alpha Enterprises, Inc. is considering a project that has the following cash flows: Year Cash Flow 0 -$1,000 1 500 2 300 3 700 4 400 The company’s WACC is 10%. What is the project’s ordinary payback?
Warnock Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that a project's projected NPV can be negative, in which case it will be rejected. WACC: 10.00% Year0123Cash flows-$1,050$500$400$300 a. -$29.61 b. -$40.27 c. -$39.09 d. - $39.48 e. -$47.38
Warnock Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that a project's projected NPV can be negative, in which case it will be rejected. VACC: 10.00% Year Cash flows$1,050 500 $400 $300 a. -$39.09 O b. -$40.27 O c. -$39.48 d. -$47.38 O e. -$29.61
Alpha Enterprises, Inc. is considering a project that has the following cash flows: Year: Cash Flow; 0: -$1,000 1: 500 2: 300 3: 900 4: 400 The company’s WACC is 10%. What is the project’s ordinary payback? Enter your answer rounded to two decimal places.
Ellmann Systems is considering a project that has the following cash flow and WACC data. The WACC is 7%. The CF0 = -$1,000, CF1 = $331, CF2 = $473, and CF3 = $597. What is the project's NPV? Computer Consultants Inc. is considering a project that has the following cash flow and WACC data. The WACC is 10.2%. The CF0 = -$1,000, CF1 = $450, CF2 = $450, and CF3 = $450. What is the project's MIRR? Garner Inc. is...
Nichols Inc. is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's IRR can be less than the cost of capital or negative, in both cases it will be rejected. Year 0 1 2 3 4 5 Cash flows −$1,250 $325 $325 $325 $325 $325 a. 10.92% b. 9.43% c. 11.47% d. 10.40% e. 9.91% Westwood Painting Co. is considering a project that has the following cash flow and cost...
1. Frye Foods is considering a project that has the following cash flow data. What is the project's IRR? Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your answer is 0.12345 or 12.345% then enter as 12.35 in the answer box. Year: 0 1 2 3 4 5 Cash flows: -$1,150 $325 $325 $325 $325 $325 2.Van Auken Inc. is considering a project that has the following cash flows:...
Harry's Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that if a project's projected NPV is negative, it should be rejected. WACC: 9.50% Year Cash flows $1,000 $300 $300 S 300 $300 S300 a) 0179.26 Ob) 0135.20 OC) 0120.01 d) 0151.91 e) 0133.68
Babcock Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Enter your answer rounded to two decimal places. Do not enter $ or comma in the answer box. For example, if your answer is $12,300.456 then enter as 12300.46 in the answer box. WACC: 12% Year: 0 1 2 3 Cash flows: -$1,250 $400 $500 $600
Babcock Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Enter your answer rounded to two decimal places. Do not enter $ or comma in the answer box. For example, if your answer is $12,300.456 then enter as 12300.46 in the answer box. WACC: 10% Year: 0 1 2 3 Cash flows: -$1,250 $400 $500 $600