Question

8.

Problem 10-21 Cost-Cutting Proposals (LO2] Masters Machine Shop is considering a four-year project to improve its production​​​​​​

Below is MACRS Schedule

Year 1 2 Property Class Three-Year Five-Year 33.33% 20.00% 44.45 32.00 14.81 19.20 7.41 11.52 11.52 5.76 ܚ Seven-Year 14.29%

0 0
Add a comment Improve this question Transcribed image text
Answer #1


solution: annual pretax cost saving 202,000.00 202,000.00 202,000.00 202,000.00 Less; Depreciation* - 96,000.00 - 153,600.00

Add a comment
Know the answer?
Add Answer to:
8. ​​​​​​ Below is MACRS Schedule Problem 10-21 Cost-Cutting Proposals (LO2] Masters Machine Shop is considering...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $401,000 is estimated to result in $147,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table) and it will have a salvage value at the end of the project of $48,000. The press also requires an initial investment in spare parts inventory of $15,300, along with an additional $2,300 in inventory for each succeeding year...

  • CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press fo...

    CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $401,000 is estimated to result in $147,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table) and it will have a salvage value at the end of the project of $48,000. The press also requires an initial investment in spare parts inventory of $15,300, along with an additional $2,300 in inventory for each succeeding year...

  • CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $419,000 is estimated to result in $156,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table) and it will have a salvage value at the end of the project of $57,000. The press also requires an initial investment in spare parts inventory of $16,200, along with an additional $3,200 in inventory for each succeeding year...

  • Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a...

    Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $555,858 is estimated to result in $195,308 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $91,853. The shop's tax rate is 30 percent. What is the OCF for year 4? (Round your final answer to the nearest dollar amount. Omit the...

  • Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a...

    Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $573,039 is estimated to result in $238,224 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $99,519. The shop's tax rate is 33 percent. What is the OCF for year 4? (Round your final answer to the nearest dollar amount. Omit the...

  • Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a...

    Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $503,562 is estimated to result in $203,421 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $105,027. The shop's tax rate is 34 percent. What is the after-tax salvage value of this asset? (Round your final answer to the nearest dollar amount....

  • An asset used in a four-year project falls in the five-year MACRS class for tax purposes....

    An asset used in a four-year project falls in the five-year MACRS class for tax purposes. The asset has an acquisition cost of $4,850,000 and will be sold for $1,425,000 at the end of the project. If the tax rate is 21 percent, what is the aftertax salvage value of the asset? Refer to Table 10.7. Year O VOO AWN Property Class Three-Year Five-Year 33.33% 20.00% 44.45 32.00 14.81 19.20 7.41 11.52 11.52 5.76 Seven-Year 14.29% 24.49 17.49 12.49 8.93...

  • 10 Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a...

    10 Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $390,000 is estimated to result in $148,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $48,000. The press also requires an initial investment in spare parts inventory of $21,000, along with an additional $3,150 in inventory for each succeeding year of...

  • Masters Machine Shop is considering a four-year project to improve its production efficiency

    Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $445,000 is estimated to result in $181,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $73,000. The press also requires an initial investment in spare parts inventory of $32,000, along with an additional $3,700 in inventory for each succeeding year of the...

  • Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $470,000 is estimated to result in $196,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $72,000. The press also requires an initial investment in spare parts inventory of $37,000, along with an additional $3,950 in inventory for each succeeding year of the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT