CALCULAITON OF THE EQUIVALENT UNITS OF PRODUCTION IN THE MONTH OF JUNE | ||||
Particulars | Units | % Complete | Equivalent Units | |
Opening Inventory (Pending for completion) | 900 | 10% | 90 | |
Add: Lamps Transferred to Finished Goods | 5000 | 100% | 5000 | |
Ending , Work-in-process | 1100 | 30% | 330 | |
Total Equivalent units | 5420 | |||
Total Equivalent units in the month of June | ||||
Cost Categories | ||||
Body Materials | 5420 | Units | ||
Wiring materials | 5420 | Units | ||
Labour & Overhead | 5420 | Units | ||
CALCULAITON OF THE EQUIVALENT UNITS OF PRODUCTION IN THE MONTH OF JULY | ||||
Particulars | Units | % Complete | Equivalent Units | |
Opening Inventory (Pending for completion) | 1100 | 70% | 770 | |
Add: Lamps Transferred to Finished Goods | 4600 | 100% | 4600 | |
Ending , Work-in-process | 800 | 80% | 640 | |
Total Equivalent units | 6010 | |||
Total Equivalent units in the month of June | ||||
Cost Categories | ||||
Body Materials | 6010 | Units | ||
Wiring materials | 6010 | Units | ||
Labour & Overhead | 6010 | Units | ||
throughout the manutacturing process, brite laeas uses process costing and naa the tollowing unıt production intormation...
Explanations for each answer is appreciated. Brite ldeas, Inc., mass-produces reading lamps. Materials used in constructing the body of the lamp are added at the start of the process, while the materials used in wiring the lamps are added at the halfway point. All labor and overhead are added evenly throughout the manufacturing process. Brite Ideas uses process costing and had the following unit production information available for the months of June and Julv June Jul Number of lamps in...
Brite Ideas, Inc., mass-produces reading lamps. Materials used in constructing the body of the lamp are added at the start of the process, while the materials used in wiring the lamps are added at the halfway point. All labor and overhead are added evenly throughout the manufacturing process. Brite Ideas uses process costing and had the following unit production information available for the months of June and July. June July Number of lamps in beginning work in process 800 1,200...
11 Exercise 9 - Your Co. uses process costing to account for production costs. Direct labor is added evenly throughout the process and direct materials is added at the beginning of the process. During June, the assembly department transferred 315 units to finished goods. Beginning WIP inventory was 30 units with $150 direct materials and $300 direct labor. Ending WIP inventory consists of 60 units that are 60% complete with respect to labor. $1500 direct materials were incurred in June...
Brite Toothbrushes has gathered the following information to complete its Production Report for the month of April. Assume all materials are added at the beginning of the process. (I appreciate any help that is given. Thanks in advance!) Brite Toothbrushes has gathered the following information to complete its Production Report for the month of April. Assume all materials are added at the beginning of the process. Required: Using the provided information, complete the report. (Round cost per Equivalent Units to...
Problem 3 Beniaku Corporation has two production departments and uses a process cost system. The following data is available as to the costs of production and the number of units worked on during the month of June, 2019: Department A: Costs in Beginning Work in Process Direct materials Direct labor Manufacturing overhead Costs incurred during June: Direct materials Direct labor Manufacturing overhead $19,300 $54,200 $16,800 $161,500 $140,800 $67,200 Units worked on during June: Work-in-process, June 1 (30% complete as to...
Pureform, Inc., uses the FIFO method in its process costing system. It manufactures a product that passes through two departments. Data for a recent month for the first department follow: Materials $ 49,700 $ Labor 10,600 Overhead $ 24,300 Work in process inventory, beginning Units started in process Units transferred out Work in process inventory, ending Cost added during the month Units 61,000 579,000 600,000 40,000 $ 894,815 $ 289,225 $ 347,070 The beginning work in process inventory was 70%...
Pureform, Inc., uses the FIFO method in its process costing system. It manufactures a product that passes through two departments Data for a recent month for the first department follow: Materials $ 82,500 Labor $ 24,900 Overhead $ 35,800 Work in process inventory, beginning Units started in process Units transferred out Work in process inventory, ending Cost added during the month Units 69,000 659, eee 60.AP 48,eee $1,044, 68e $ 160,925 $ 482,775 The beginning work in process inventory was...
Pureform, Inc., uses the FIFO method in its process costing system. It manufactures a product that passes through two departments. Data for a recent month for the first department follow: Units Materials Labor Overhead Work in process inventory, beginning 65,000 $ 68,500 $ 5,700 $ 21,400 Units started in process 617,000 Units transferred out 610,000 Work in process inventory, ending 72,000 Cost added during the month $ 1,484,100 $ 268,290 $ 327,910 The beginning work in process inventory was 75%...
Pureform, Inc., uses the FIFO method in its process costing system. It manufactures a product that passes through two departments. Data for a recent month for the first department follow: Materials $ 84,400 Labor $ 42,200 Overhead $ 55,900 Work in process inventory, beginning Units started in process Units transferred out Work in process inventory, ending Cost added during the month Units 87,000 829,000 850,000 66,000 $ 986,520 $ 491,190 $ 654,920 The beginning work in process inventory was 70%...
Pureform, Inc., uses the FIFO method in its process costing system. It manufactures a product that passes through two departments. Data for a recent month for the first department follow: Materials $ 68,500 Labor 5,700 Overhead $ 21,400 $ Work in process inventory, beginning Units started in process Units transferred out Work in process inventory, ending Cost added during the month Units 65,000 617,000 610,000 72,000 $1,484,100 $ 268,299 $ 327,910 The beginning work in process inventory was 75% complete...