Bledsoe Corporation has provided the following data for the month of November:

Beginning Ending
Raw materials $ 26,700 $ 22,700
Work in process $ 18,700 $ 11,700
Finished Goods $ 49,700 $ 57,700

Additional information:

Raw materials purchases $ 73,700
Direct labor cost $ 93,700
Manufacturing overhead cost incurred $ 43,870
Indirect materials included in manufacturing overhead cost incurred $ 4,170
Manufacturing overhead cost applied to Work in Process $ 42,700

Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold.

Required:

Prepare a Schedule of Cost of Goods Manufactured and a Schedule of Cost of Goods Sold.BLEDSOE CORPORATION Schedule of Cost of Goods Manufactured Direct materials: Raw materials available for use Raw materials used in production Total manufacturing costs Cost of goods manufactured

Prepare a Schedule of Cost of Goods Sold. BLEDSOE CORPORATION Schedule of Cost of Goods Sold Beginning finished goods inventory Cost of goods available for sale Unadjusted cost of goods sold Adjusted cost of goods sold

0 0
Add a comment Improve this question Transcribed image text
Answer #1

BLEDSOE CORPORATION

Schedule of Cost of Goods Manufactured

  

Direct Material

Raw material Inventory Beginning

$          26,700.00

Raw material Purchased

$          73,700.00

Raw material available for use

$       1,00,400.00

Less: Raw material Inventory Ending

$          22,700.00

Direct Material Used

$        77,700.00

Direct labor

$        93,700.00

Manufacturing overheads applied

$        42,700.00

Total manufacturing Cost

$    2,14,100.00

Add: Work in process Beginning

$        18,700.00

Total Work in Process

$    2,32,800.00

Less: Work in process Ending

$        11,700.00

Cost of Goods Manufactured

$    2,21,100.00

BLEDSOE CORPORATION

Schedule of cost of good sold

Beginning Finished Goods Inventory

$        49,700.00

Cost of Goods manufactured

$    2,21,100.00

Goods Available for sale

$    2,70,800.00

Less :Ending Finished goods Inventory

$        57,700.00

Unadjusted Cost of Goods Sold

$    2,13,100.00

Underapplied Manufacturing Overheads

$          1,170.00

Adjusted Cost og Goods sold

$    2,14,270.00

Add a comment
Know the answer?
Add Answer to:
Bledsoe Corporation has provided the following data for the month of November: Beginning Ending Raw materials...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • what is the under applied overhead? thanks Bledsoe Corporation has provided the following data for the...

    what is the under applied overhead? thanks Bledsoe Corporation has provided the following data for the month of November: Inventories: Raw materials Work in process Finished Goods Beginning Ending $ 26,700 $22,700 $ 18,700 $11,700 $ 49,700 $57,700 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cost incurred Manufacturing overhead cost applied to Work in Process $73,700 $93,700 $43,870 $ 4,170 $42,700 Any underapplied or overapplied manufacturing overhead is closed...

  • Bledsoe Corporation has provided the following data for the month of November Raw materials Work in...

    Bledsoe Corporation has provided the following data for the month of November Raw materials Work in process Finished Goods Beginning Ending $ 25,300 $21,300 $ 17,300 $10,300 $ 48,300 $56,300 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cost incurred Manufacturing overhead cost applied to Work in Process $72,300 $92,300 $ 42,330 $ 4,030 $ 41,300 Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold....

  • Bledsoe Corporation has provided the following data for the month of November Raw materials Work in...

    Bledsoe Corporation has provided the following data for the month of November Raw materials Work in process Finished Goods Beginning Ending $ 27,000 $23,000 $ 19,000 $12,000 $ 50,000 $58,000 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cost incurred Manufacturing overhead cost applied to Work in Process $74,000 $94,000 $44,200 $ 4,200 $43,000 Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold. $ BLEDSOE...

  • Bledsoe Corporation has provided the following data for the month of November: Raw materials Work in...

    Bledsoe Corporation has provided the following data for the month of November: Raw materials Work in process Finished Goods Beginning Ending $ 26,800 $22,800 $ 18,800 $11,800 $ 49,800 $57,800 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cost incurred Manufacturing overhead cost applied to Work in Process $73,888 $93,800 $43,980 $ 4,180 $42,800 Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold. Required: Prepare...

  • Bledsoe Corporation has provided the following data for the month of November. Raw materials Work in...

    Bledsoe Corporation has provided the following data for the month of November. Raw materials Work in process Finished Goods Beginning Ending $ 26,408 $22,400 $ 18,400 $ 11,400 $ 49,400 $57,400 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cost incurred Manufacturing overhead cost applied to Work in Process $73,400 $93,400 $43, 540 $ 4,140 $42,400 Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold....

  • Bledsoe Corporation has provided the following data for the month of November: Inventories: Raw materials Work...

    Bledsoe Corporation has provided the following data for the month of November: Inventories: Raw materials Work in process Finished Goods Beginning Ending $ 25,400 $21,400 $ 17,400 $10,400 $ 48,400 $56,400 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cost incurred Manufacturing overhead cost applied to Work in Process $72,400 $92,400 $42,440 $ 4,040 $41,400 Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold. Required:...

  • Bledsoe Corporation has provided the following data for the month of November: Raw materials Work in...

    Bledsoe Corporation has provided the following data for the month of November: Raw materials Work in process Finished Goods Beginning Ending $ 26,900 $ 22,900 $ 18,900 $ 11,900 $ 49,900 $57,900 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cost incurred Manufacturing overhead cost applied to work in Process $ 73,900 $ 93,900 $ 44,090 $ 4,190 $ 42,900 Any underapplied or overapplied manufacturing overhead is closed out to...

  • Bledsoe Corporation has provided the following data for the month of November: Raw materials Work in...

    Bledsoe Corporation has provided the following data for the month of November: Raw materials Work in process Finished Goods Beginning Ending $ 25,400 $21,400 $ 17,400 $10,400 $ 48,400 $56,400 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cont incurred Manufacturing overhead cost applied to Work in Process $ 72,400 $92,400 $42,440 $ 4,040 $41,400 Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold. Required:...

  • Bledsoe Corporation has provided the following data for the month of November Raw materials Work in...

    Bledsoe Corporation has provided the following data for the month of November Raw materials Work in process Finished Goods Beginning Ending $ 26,500 $22,500 $ 18,500 $11,500 $ 49,500 $57,500 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cost incurred Manufacturing overhead cost applied to work in Process $73,500 $93,500 $43,650 $ 4,150 $42,500 Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold. Required: Prepare...

  • Bledsoe Corporation has provided the following data for the month of November: Raw materials Work in...

    Bledsoe Corporation has provided the following data for the month of November: Raw materials Work in process Finished Goods Beginning Ending $ 25,300 $21,380 $ 17,300 $10,300 $ 48,300 $56,300 Additional information: Raw materials purchases Direct labor cost Manufacturing overhead cost incurred Indirect materials included in manufacturing overhead cost incurred Manufacturing overhead cost applied to work in Process $72,300 $92,300 $42,330 $ 4,30 $41,300 Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold. Required: Prepare...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT