P9-20 (similar to) Question Help Profitability index. Given the discount rate and the future cash flow of each project listed

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans Project A PI: 1.21

Accept, since PI > 1

PROJECT A
Year Project Cash Flows (i) DF@ 8% DF@ 8% (ii) PV of Project ( (i) * (ii) )
1 300000 1/((1+8%)^1) 0.926                  2,77,777.78
2 500000 1/((1+8%)^2) 0.857                  4,28,669.41
3 700000 1/((1+8%)^3) 0.794                  5,55,682.57
4 900000 1/((1+8%)^4) 0.735                  6,61,526.87
5 1100000 1/((1+8%)^4) 0.681                  7,48,641.52
PV                26,72,298.14
Total of PV of Cash Inflows 2672298.14
Cash Outflows 2200000
Profitability Index = 2672298.14 / 2200000 1.21

Ans Project B PI: 1.21

Accept, since PI > 1

PROJECT B
Year Project Cash Flows (i) DF@ 15% DF@ 15% (ii) PV of Project ( (i) * (ii) )
1 1250000 1/((1+15%)^1) 0.870                10,86,956.52
2 1050000 1/((1+15%)^2) 0.756                  7,93,950.85
3 850000 1/((1+15%)^3) 0.658                  5,58,888.80
4 650000 1/((1+15%)^4) 0.572                  3,71,639.61
5 450000 1/((1+15%)^4) 0.497                  2,23,729.53
PV                30,35,165.31
Total of PV of Cash Inflows 3035165.31
Cash Outflows 2500000
Profitability Index = 3035165.31 / 2500000 1.21
Add a comment
Know the answer?
Add Answer to:
P9-20 (similar to) Question Help Profitability index. Given the discount rate and the future cash flow...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Profitability index. Given the discount rate and the future cash flow of each project listed in...

    Profitability index. Given the discount rate and the future cash flow of each project listed in the following table, , use the Pl to determine which projects the company should accept. What is the Pl of project A? Data Table (Round to two decimal places.) (Click on the following icon in order to copy its contents into a spreadsheet.) Cash Flow Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Discount rate Project A - $2,200,000 $700,000...

  • X P9-20 (similar to) Question Help :, use the Pl to determine which projects the company...

    X P9-20 (similar to) Question Help :, use the Pl to determine which projects the company Profitability index. Given the discount rate and the future cash flow of each project listed in the following table, should accept What is the PI of project A? (Round to two decimal places.) 0 X - Data Table (Click on the following icon in order to copy its contents into a spreadsheet.) Cash Flow Year 0 Year 1 Year 2 Year 3 Year 4...

  • P9-13 (similar to) Question Help • Internal rate of return and modified internal rate of return....

    P9-13 (similar to) Question Help • Internal rate of return and modified internal rate of return. Quark Industries has three potential projects, all with an initial cost of $1,900,000. Given the discount rate and the future cash flow of each project in the following table, , what are the IRRs and MIRRs of the three projects for Quark Industries? What is the IRR for project M? 0 Data Table % (Round to two decimal places.) (Click on the following icon...

  • P9-15 Calculating Profitability Index [LO7] Year WN-O Cash Flow -$7,500 3,100 3,300 4,300 a. What is the profitability...

    P9-15 Calculating Profitability Index [LO7] Year WN-O Cash Flow -$7,500 3,100 3,300 4,300 a. What is the profitability index for the cash flows if the relevant discount rate is 6 percent?

  • P9-8 (similar to) EQuestion Help Net present value. Lepton Industries has a project with the following...

    P9-8 (similar to) EQuestion Help Net present value. Lepton Industries has a project with the following projected cash flows: a. Using a discount rate of 9% for this project and the NPV model, determine whether the company should accept or reject this project b. Should the company accept or reject it using a discount rate of 17% ? c. Should the company accept or reject it using a discount rate of 20 %? . (Select from the drop-down menu.) a....

  • P9-15 Calculating Profitability Index [LO7] Year Cash Flow 0 −$8,400 1 3,000 2 3,500 3 4,700...

    P9-15 Calculating Profitability Index [LO7] Year Cash Flow 0 −$8,400 1 3,000 2 3,500 3 4,700 Required : (a) What is the profitability index for the cashflows if the relevant discount rate is 12 percent? (b) What is the profitability index for the cashflows if the relevant discount rate is 17 percent? (c) What is the profitability index for the cashflows if the relevant discount rate is 22 percent?

  • Year WN-O Cash Flow -$7,700 4,000 5,900 2,100 a. What is the profitability index for the...

    Year WN-O Cash Flow -$7,700 4,000 5,900 2,100 a. What is the profitability index for the cash flows if the relevant discount rate is 8 percent? b. What is the profitability index for the cash flows if the relevant discount rate is 19 percent? c. What is the profitability index for the cash flows if the relevant discount rate is 24 percent? A firm evaluates all of its projects by using the NPV decision rule. Year WN=0 Cash Flow -$29,000...

  • Homework: Chapter 9 Homework (Copy) 4 of 9 (5 complete) Score: 0 of 2 pts P9-7...

    Homework: Chapter 9 Homework (Copy) 4 of 9 (5 complete) Score: 0 of 2 pts P9-7 (similar to) Net present value. Quark Industries has a project with the following projected cash flows: a. Using a discount rate of 9% for this project and the NPV model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 16%? c. Should the company accept or reject it using a...

  • All I need help with on this question is the MIRR for all three projects. I...

    All I need help with on this question is the MIRR for all three projects. I have tried both excel and handwriting and can't seem to get it right, so this is my last attempt. Thank you! Since the picture seems hard to see: The values for Project M are 400,000 years 1-5, N is 600,000 years 1-5, and O is 900,000 (Y1), 700,000 (Y2), 500,000 (Y3), 300,000 (Y4), and 100,000 (Y5). The discount rate for M is 8%, N...

  • Comparing all methods. Risky Business is looking at a project with the following estimated cash flow:...

    Comparing all methods. Risky Business is looking at a project with the following estimated cash flow: 5. Risky Business wants to know the payback period, NPV, IRR, MIRR, and Pl of this project. The appropriate discount rate for the project is 9%. If the cutoff period is 6 years for major projects, determine whether the management at Risky Business will accept or reject the project under the five different decision models. What is the payback period for the new project...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT