Answers
Activity Rates |
||
Labor-related |
$ 15.00 |
per DLHs |
Purchase orders |
$ 5.00 |
per orders |
Product testing |
$ 17.00 |
per tests |
Template etching |
$ 25.00 |
per templates |
General factory |
$ 8.00 |
per MHs |
--Working
Activity Cost Pool |
Activity Measure |
Expected Overhead cost |
Expected Activity |
Activity Rates |
||
[A] |
[B] |
[A/B] |
||||
Labor-related |
Direct labor-hours |
$ 28,050.00 |
1,870 |
DLHs |
$ 15.00 |
per DLHs |
Purchase orders |
Number of orders |
$ 2,100.00 |
420 |
orders |
$ 5.00 |
per orders |
Product testing |
Number of tests |
$ 4,420.00 |
260 |
tests |
$ 17.00 |
per tests |
Template etching |
No of templates |
$ 1,250.00 |
50 |
templates |
$ 25.00 |
per templates |
General factory |
Machine-hours |
$ 81,600.00 |
10,200 |
MHs |
$ 8.00 |
per MHs |
Total |
|
Product A |
$ 43,510.00 |
Product B |
$ 21,485.00 |
Product C |
$ 20,400.00 |
Product D |
$ 32,025.00 |
--Working
Expected Activity |
Activity Rates |
Overhead Allocated |
||
Activity Cost Pool |
Product A |
|||
Labor-related |
700 |
$ 15.00 |
per DLHs |
$ 10,500.00 |
Purchase orders |
80 |
$ 5.00 |
per orders |
$ 400.00 |
Product testing |
130 |
$ 17.00 |
per tests |
$ 2,210.00 |
Template etching |
- |
$ 25.00 |
per templates |
$ - |
General factory |
3,800 |
$ 8.00 |
per MHs |
$ 30,400.00 |
Amount of Overhead Cost assigned |
$ 43,510.00 |
|||
Expected Activity |
Activity Rates |
Overhead Allocated |
||
Activity Cost Pool |
Product B |
[A/B] |
||
Labor-related |
170 |
$ 15.00 |
per DLHs |
$ 2,550.00 |
Purchase orders |
60 |
$ 5.00 |
per orders |
$ 300.00 |
Product testing |
55 |
$ 17.00 |
per part types |
$ 935.00 |
Template etching |
36 |
$ 25.00 |
per boards |
$ 900.00 |
General factory |
2,100 |
$ 8.00 |
per MHs |
$ 16,800.00 |
Amount of Overhead Cost assigned |
$ 21,485.00 |
|||
Expected Activity |
Activity Rates |
Overhead Allocated |
||
Activity Cost Pool |
Product C |
[A/B] |
||
Labor-related |
500 |
$ 15.00 |
per DLHs |
$ 7,500.00 |
Purchase orders |
130 |
$ 5.00 |
per orders |
$ 650.00 |
Product testing |
- |
$ 17.00 |
per part types |
$ - |
Template etching |
10 |
$ 25.00 |
per boards |
$ 250.00 |
General factory |
1,500 |
$ 8.00 |
per MHs |
$ 12,000.00 |
Amount of Overhead Cost assigned |
$ 20,400.00 |
|||
Expected Activity |
Activity Rates |
Overhead Allocated |
||
Activity Cost Pool |
Product D |
[A/B] |
||
Labor-related |
500 |
$ 15.00 |
per DLHs |
$ 7,500.00 |
Purchase orders |
150 |
$ 5.00 |
per orders |
$ 750.00 |
Product testing |
75 |
$ 17.00 |
per part types |
$ 1,275.00 |
Template etching |
4 |
$ 25.00 |
per boards |
$ 100.00 |
General factory |
2,800 |
$ 8.00 |
per MHs |
$ 22,400.00 |
Amount of Overhead Cost assigned |
$ 32,025.00 |
Check my work Part 1 of 2 Required Information Exercise 4-11 Contrasting Activity-Based Costing and Conventional...
Check my work Required information [The following information applies to the questions displayed below.] Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $ 28,050 $ 2,100 $ 4,420 $...
Required information [The following information applies to the questions displayed below.) Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $ 28,050 $ 2,100 $ 4,420 $ 1,250 $81,600 Expected...
(The following information applies to the questions displayed below.) Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $ 23,980 $ 530 $ 4,200 $ 1,035 $ 34,400 Expected Activity...
Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $ 43,308 $ 2,160 $ 5,700 $ 1,950 $ 68,600 Expected Activity 2,406 DLHS 540 orders 300 tests 65 templates 9,800...
Required information [The following information applies to the questions displayed below.] Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools: Activity Cost Pool Activity Measure Expected Overhead Cost Expected Activity Labor-related Direct labor-hours $ 19,120 2,390 DLHs Purchase orders Number of orders $ 1,575 525 orders Product testing Number of tests $ 2,430 270 tests Template etching Number of...
Rustles Company recently implemented an activity-based costing system. At the beginning of the year. management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $ 24,585 $ 3.270 $ 3,640 $ 1,050 $ 107,100 Expected Activity 2,235 DLHs 545 orders 280 tests 50 templates 11,900...
Quiz 4 Required information [The following information applies to the questions displayed below.] Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools: Activity Cost Pool Activity Measure Expected Overhead Cost Expected Activity Labor-related Direct labor-hours $ 19,120 2,390 DLHs Purchase orders Number of orders $ 1,575 525 orders Product testing Number of tests $ 2,430 270 tests Template etching...
made the following estimates of cost and activity in the company s tive activity cost pools: Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $30, 115 $ 2,320 $ 6,930 $ 870 $ 65,100 Expected Activity 1,585 DLHS 580 orders 330 tests 30 templates 9,300 MHS 2. The expected activity for the year was distributed among the company's four...
Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $19,125 $ 1,660 $ 3,000 $ 1,470 $59,500 Expected Activity 2,125 DLHS 415 orders 300 tests 70 templates 8,500 MHS Exercise 4-11 Part 2 2. The expected activity for the year was distributed among the company's four products as follows: Product A 450 50 Activity Cost Pool Labor-related (DLHS) Purchase orders...
Exercise 4-5 Assigning Overhead to Products in ABC [LO4-2, L04-3) Sultan Company uses an activity-based costing system At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $311,500 $ 8,840 $ 71,280 $ 63,700 $ 148,eee Expected Activity...