period | cash flows | salvage value | PV factor @15% | present values | ||
0 | -100 | 1 | -100 | |||
1 | -400 | 0.8696 | -347.84 | |||
2 | 150 | 0.7561 | 113.415 | |||
3 | 250 | 0.6575 | 164.375 | |||
4 | 350 | 0.5718 | 200.13 | |||
5 | 350 | 0.4972 | 174.02 | |||
6 | 200 | 100 | 0.4323 | 129.69 | ||
NPV | 333.79 | |||||
A3-2 A project has costs and incomes as shown on the diagram in thousands of dollars....
A3-2 A project has costs and incomes as shown on the diagram in thousands of dollars. C Capital, OC Operating Cost, and L salvage or liqui- dation value of the assets upon termination of the project. 1-100 1-250 1-375 1=500 1=500 1=400 C=500 OC-100 OC=125 OC=150 OC=150 °C-200 C= 100 L= 1 00 6 4 The investor's minimum rate of return is 15%. Calculate the before- tax cash flow (BTCF) and then determine the ROR, NPV, PVR, and Growth ROR...
Question 2. Consider the market for burritos in a hypothetical Canadian city, blessed with thousands of students and dozens of small burritos stands. The demand and supply schedules are shown in the table. Price ($) Quantity Demanded (Burritos) Quantity Supplied (Burritos) 0.0 500 125 1.0 400 175 1.50 350 200 2.00 300 225 2.50 250 250 3.00 200 275 3.50 150 300 4.00 100 325 5.00 0 375 a) Graph the demand and supply curves. What is the free -market...
40kN Uniform Load W kN/m X Span L L/2 Figure 1 SPAN L 6 W 11Kn/m Beam is 200 UB 18.2 Use the diagram above and the W and L values assigned to you to: a) Use your shear force diagram to calculate the Maximum longitudinal Shear Stress and where it occ Ccurs. b) Calculate the longitudinal Shear Stress at d/4 from the neutral axis. Check Figures 283 below this table BENDING MOMENT DIAGLAM Kp/m f:40 zm 7.5 KN-M 90...
As you know from Project 4, McCormick & Company is
considering building a new factory in Largo, Maryland. McCormick
& Company decided to offer $4,424,000 to obtain the land for
this project. The new factory will require an initial investment of
$350 million to build the new plant and purchase equipment.
You have been asked to continue your work from project 4 with a
full analysis of the proposed factory, including the start-up
costs, the projected net cash flows from...
Because of its inability to control film and personnel
costs in its radiology department, Sanger General Hospital wants to
replace its existing picture archive and communication (PAC) system
with a newer version. The existing system, which has a current book
value of $2,250,000, was purchased three years ago for $3,600,000
and is being depreciated on a straight-line basis over an
eight-year life to a salvage value of $0. This system could be sold
for $800,000 today. The new PAC system...
find v belt drive
design power
select belt type
determine shive size (belt speed 4000 ft/min)
find shive size from power rating figure
find rated power
find estimated centre distance
find belt length (by selecting standard belt length)
calculate actual centre distance
find contact angle for small shieve
determine correct factors
calculate correct power per belt
no. of belt needed
V-Belt Designing Sample Problem . Given: A 4 cylinder diesel engine runs at 80 hp, 1800 rpm, to drive a...