Answer:
Determine the Activity rate for each activity pool | |||
total Cost pool | Total Activity | Activity rate = Cost pool/Activity | |
Labor Related | 137100 | 4200 | 32.64 |
Machine Setup | 64650 | 1400 | 46.18 |
Order size | 1011170 | 5600 | 180.57 |
Activity rate = Cost pool / Activity | |||
Product A7 | |||
Activity Rate | Activity | OH allocated = Activity*rate | |
labor Related | 32.64 | 1000 | 32640 |
Machine Setup | 46.18 | 500 | 23090 |
Order Size | 180.57 | 3100 | 559767 |
Total Overhead cost Allocated to A7 | 615497 |
Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected...
Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product E1 1,000 10.0 10,000 Product A7 200 5.0 1,000 Total direct labor-hours 11,000 The direct labor rate is $25.00 per DLH. The direct materials cost per unit for each product is given below: Direct Materials Cost...
Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product E1 1,200 8.0 9,600 Product A7 200 4.0 800 Total direct labor-hours 10,400 The direct labor rate is $27.20 per DLH. The direct materials cost per unit for each product is given below: Direct Materials Cost...
Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product E1 1,200 2.0 2,400 Product A7 400 1.0 400 Total direct labor-hours 2,800 The direct labor rate is $23.60 per DLH. The direct materials cost per unit for each product is given below: Direct Materials Cost...
Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHS) required to produce that output appear below: Direct Total Labor- Direct Expected Hours Per Labor- Production Unit Hours 1,200 2.0 2,400 400 1.0 2,800 Product 31 Product A7 Total direct labor-hours 400 The direct labor rate is $23.60 per DLH. The direct materials cost per unit for each product is given below: Direct...
32) Snavely, Inc., manufactures and sells two products: Product El and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Direct Labor- Total Direct Production Hours Per Unit Labor-Hours Product E1 800 Product A7 300 600 Total direct labor-hours 4,600 4,000 2.0 The direct labor rate is $18.40 per DLH. The direct materials cost per unit for each product is given below: Product E1...
51) Snavely, Inc., manufactures and sells two products Product El and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Direct Labor- Total Direct Production Hours Per Unit Labor-Hours Product E1 800 4,000 Product A7 300 2.0 600 Total direct labor-hours 4,600 The direct labor rate is $18.40 per DLH. The direct materials cost per unit for each product is given below: Direct Materials...
Please help Accounting question Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHS) required to produce that output appear below: Direct Labor-Hours Per Unit Total Direct Labor- Hours 4,800 800 5,600 Expected Production 600 200 Product E1 Product A7 Total direct labor-hours 8.0 4.0 The direct labor rate is $2710 per DLH. The direct materials cost per unit for each product is...
3 SMavery, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Direct Labor- Hours Per Expected Production 800 300 Unit Product Ei Product A7 Total Direct Labor- Hours 4,000 600 4,600 5.0 2.0 Total direct labor-hours The direct labor rate is $18.40 per DLH. The direct materials cost per unit for each product is given below:...
Seved Help Save& Exit Submit Snavely, Inc., manufactures and sells two products: Product E1 and Product A7 Data concerning the expected production of each product and the expected total direct labor-hours (DLHS) required to produce that output appear below Direct Total Labor- Direct Expected Labor- Hours Per 06 Production Unit Hours Product E1 900 2.0 1,800 Product A7 600 1.0 600 Total direct labor-hours 2,400 The direct labor rate is $24.10 per DLH. The direct materials cost per unit for...
Hello could someone please help me answer this question Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHS) required to produce that output appear below: Direct Labor-Hours Per Unit Expected Production 1,000 300 Total Direct Labor- Hours 4,000 600 4,600 4.0 Product E1 Product A7 Total direct labor-hours 2.0 The direct labor rate is $25.20 per DLH. The direct materials cost per...