job 201 | job202 | total | ||||||
Beginning work in process | 16,500 | 16,500 | ||||||
Cost added during the year | ||||||||
Direct materials | 11,000 | 21,100 | 32,100 | |||||
Direct labor | 2,100 | 10,200 | 12,300 | |||||
OH applied | 3016 | 10114 | 13130 | |||||
total cost added | 16,116 | 41,414 | 57,530 | |||||
total cost of job | 32,616 | 41,414 | 74,030 | |||||
Raw Materials | work in process inventory | |||||||
1-Jan | 38,000 | 1-Jan | 16,500 | |||||
a | 67,000 | 38,000 | b | b | 32,100 | 32,616 | f | |
c | 12,300 | |||||||
31-Jan | 67,000 | d | 13130 | |||||
31-Jan | 41,414 | |||||||
Finished goods inventory | cost of goods sold | |||||||
1-Jan | 26,000 | 1-Jan | ||||||
f) | 32,616 | 26,000 | g) | g) | 26,000 | |||
end bal | 32,616 | end bal | 26,000 | |||||
Manufacturing overhead | Sales revenue | |||||||
1-Jan | 1-Jan | |||||||
b) | 5,900 | 13130 | d) | 51,000 | g) | |||
c) | 4,300 | |||||||
e) | 12,400 | |||||||
31-Jan | 9,470 | 51,000 | 31-Jan | |||||
Miscellaneous accounts | ||||||||
1-Jan | ||||||||
g) | 51,000 | 67,000 | a) | |||||
16,600 | c) | |||||||
12,400 | e) | |||||||
45,000 | ||||||||
2) | ending balances | |||||||
a | Raw materials inventory | 67,000 | ||||||
b | work in process inventory | 41,414 | ||||||
c | finished goods inventory | 32,616 | ||||||
d | cost of goods sold(unadjusted) | 26,000 | ||||||
e | manufacturing overhead | 9,470 | ||||||
3) | job | total cost | ||||||
number | of job | |||||||
201 | 32,616 | |||||||
202 | 41,414 | |||||||
Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company...
Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow (ignore any accounts that are not listed). During January, the company had the following transactions: (a) Purchased $70,000 worth of materials on account. (b) Recorded materials issued to production as follows: Job Number 201 202 Indirect...
Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow (ignore any accounts that are not listed) During January, the company had the following transactions (a) Purchased $70,000 worth of materials on account (b) Recorded materials issued to production as follows: Job Number 201 202 Indirect...
Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow (ignore any accounts that are not listed). During January, the company had the following transactions: (a) Purchased $61,000 worth of materials on account (b) Recorded materials issued to production as follows: Job Number 201 202 Indirect...
Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow ignore any accounts that are not listed). During January, the company had the following transactions: (a) Purchased $62,000 worth of materials on account. (b) Recorded materials issued to production as follows: Job Number 201 202 Indirect...
Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow (ignore any accounts that are not listed). Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not...
E2-18 Recording Manufacturing Costs [LO 2-3, 2-4, 2-5] Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow (ignore any accounts that are not listed). During January, the company had the following transactions: (a) Purchased $60,000 worth of materials on account. (b) Recorded materials issued to...
Just need to answer required 1. Thank you Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow (ignore any accounts that are not listed). During January, the company had the following transactions: (a) Purchased $61,000 worth of materials on account. (b) Recorded materials issued to...
What are the transactions on the t-accounts and compute the ending balance Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow (ignore any accounts that are not listed) During January, the company had the following transactions (a) Purchased $68,000 worth of materials on account. (b)...
Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow (ignore any accounts that are not listed). During January, the company had the following transactions:(a) Purchased $63,000 worth of materials on account.(b) Recorded materials issued to production as follows: Job NumberTotal Cost201$11,50020220,400Indirect materials5,900$37,800 (c) Recorded factory payroll costs from...
I need help with question 4 Sampson Company uses a job order cost system with overhead applied based on direct labor hours. See estimated amounts below. Note the beginning balances for Finished Goods (Job 101) and Work-in-Process (Jobs 102 & 103) for the costs accumulated to date. Also note, the beginning balances in the other balance sheet accounts. Estimated Overhead for 2014 720,000 Estimated Direct Labor Hours for 2014 24,000 During January the comapny had the following transactions: Purchased $10,000...