Exercise #3: High / Low Method Using the information below, (a) calculate the variable and fixed-cost elements using the high
0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a) Variable cost per unit = ($14,740 - $11,100) / (9,800 - 7,000) = $1.30 per unit

Fixed cost = $14,740 - ($1.30 × 9,800) = $2,000

(b) Total cost to produce 8,000 units = ($1.30 × 8,000) + $2,000 = $12,400

Add a comment
Know the answer?
Add Answer to:
Exercise #3: High / Low Method Using the information below, (a) calculate the variable and fixed-cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4. High-Low Method: Using the information below and the high-low method, estimate the fixed cost and...

    4. High-Low Method: Using the information below and the high-low method, estimate the fixed cost and the variable cost of shipping, resulting in the cost formula for shipping expense. Total Shipping Expense $1,800 $2,300 $1,700 $2,000 $2.300 $2,700 $1,200 Units Shipped Month 3 January February March April May June 6 4 5 7 2 July Using the above information, what if 9 units were shipped in August?

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,590 430 February 7,100 500 March 7,631 530 April 8,240 400 May 9,887 460 June 8,590 360 July 11,864 590 August 7,600 330 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the...

  • Using High-Low to Calculate Fixed Cost Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,490 510 February 7,000 590 March 7,531 620 April 8,140 470 May 9,787 550 June 8,490 430 July 12,708 700 August 7,500 390 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month   Labor Cost($)   Employee Hours     January      9,490         380     February      7,000         440     March      7,531         460     April      8,140         350     May      9,787         410     June      8,490         320     July      11,042     ...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month January February March Labor Cost($) Employee Hours 9,490 7,000 7,531 8,140 9,787 8,490 April May June July 13,416 7,500 August Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant In your calculations, round the variable rate per employee hour to the nearest...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,590 550 February 7,100 630 March 7,631 670 April 8,240 500 May 9,887 590 June 8,590 460 July 13,380 760 August 7,600 420 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,490 570 February 7,000 660 March 7,531 700 April 8,140 May 9,787 620 480 June 8,490 July 13,520 790 August 7,500 440 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the variable...

  • #1 #2 #3 Please show work Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate,...

    #1 #2 #3 Please show work Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 290 9,490 7,000 February 330 March 7,531 April 8,140 May 9,787 310 240 June 8,490 July 10,776 400 August 7,500 220 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month   Labor Cost($)   Employee Hours     January      9,290         310     February      6,800         360     March      7,331         380     April      7,940         290     May      9,587         340     June      8,290         260     July      10,378     ...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,290 510 February 6,800 590 March 7,331 620 April 7,940 470 May 9,587 550 June 8,290 430 July 12,508 700 August 7,300 390 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT