Question

Pyramid Company applies overhead at a rate of $3.35 per direct labor hour. Using the data...

Pyramid Company applies overhead at a rate of $3.35 per direct labor hour. Using the data that follows for job 128, determine the cost of overhead applied to job 128.

Direct materials

$3,000

Direct labor cost

$5,000

Direct labor hours

500 hours

Machine time

300 hours

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Overhead applied to job 128 = Pre determined overhead rate * Number of direct labor hours

Putting the values in the above formula, we get,

Overhead applied to job 128 = $3.35 * 500 = $1675

Add a comment
Know the answer?
Add Answer to:
Pyramid Company applies overhead at a rate of $3.35 per direct labor hour. Using the data...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Luthan Company uses a plantwide predetermined overhead rate of $23.20 per direct labor-hour. This predetermined rate...

    Luthan Company uses a plantwide predetermined overhead rate of $23.20 per direct labor-hour. This predetermined rate was based on a cost formula that estimated $278,400 of total manufacturing overhead cost for an estimated activity level of 12,000 direct labor- hours. The company incurred actual total manufacturing overhead cost of $266,000 and 12,300 total direct labor-hours during the period. Required: Determine the amount of manufacturing overhead cost that would have been applied to all jobs during the period. Manufacturing overhead applied...

  • 1) 2) 3) Mickley Company's plantwide predetermined overhead rate is $20.00 per direct labor-hour and its...

    1) 2) 3) Mickley Company's plantwide predetermined overhead rate is $20.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 220 $ 120 Required: 1. What is the total manufacturing cost assigned to Job A 500? 2. If Job A 500 consists of 80 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing...

  • Question 1) The company applies overhead at a rate of 120% of direct labor cost. The...

    Question 1) The company applies overhead at a rate of 120% of direct labor cost. The company started job 203 in January and finished the job in February. During that time they used 278 hours of labor at a cost of $17 per hour. They used $123,232 of direct materials in the job. How much overhead should be applied to job 203.

  • 4 Luthan Company uses a plantwide predetermined overhead rate of $23.50 per direct labor-hour. This predetermined...

    4 Luthan Company uses a plantwide predetermined overhead rate of $23.50 per direct labor-hour. This predetermined rate was based on a cost formula that estimated $282,000 of total manufacturing overhead cost for an estimated activity level of 12,000 direct labor- hours 1 points Skipped The company incurred actual total manufacturing overhead cost of $267,000 and 10,600 total direct labor hours during the period. Required: Determine the amount of manufacturing overhead cost that would have been applied to all jobs during...

  • Martin Company applies manufacturing overhead based on direct machine hours. Martin estimates manufacturing overhead and labor...

    Martin Company applies manufacturing overhead based on direct machine hours. Martin estimates manufacturing overhead and labor for the year follows: Estimated manufacturing overhead $120,000 Direct labor hours estimated 5,000 Estimated direct labor costs $50,000 Estimated machine hours 6,000 Assuming the actual manufacturing overhead cost and the actual activities for Job 201 is as follows: Actual manufacturing overhead $ 12,000 Direct labor hours actual incurred 300 Actual direct labor costs totaled $ 9,800 Actual machine hours totaled 400 Instructions (a) Compute...

  • Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour....

    Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour. During 2019, Jackson Company began work on three jobs. Information relating to these three jobs appears below: Job #359 Job #360 Job #361 direct materials .............. $98,000 $75,000 $91,000 direct labor cost ............. $98,600 $79,900 $86,700 direct labor hours ............ 5,100 4,700 5,800 By the end of 2019, job #359 and job #361 had been completed. Job #360 was not completed by the end...

  • Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour....

    Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour. During 2019, Jackson Company began work on three jobs. Information relating to these three jobs appears below: Job #359 Job #360 Job #361 direct materials .............. $98,000 $75,000 $91,000 direct labor cost ............. $98,600 $79,900 $86,700 direct labor hours ............ 5,800 4,700 5,100 By the end of 2019, job #359 and job #361 had been completed. Job #360 was not completed by the end...

  • please help thank you! Mickley Company's plantwide predetermined overhead rate is $18.00 per direct labor-hour and...

    please help thank you! Mickley Company's plantwide predetermined overhead rate is $18.00 per direct labor-hour and its direct labor wage rate is $10.00 per hour. The following information pertains to Job A-500: S 220 Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 50 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2. Unit...

  • Sallie Company applies factory overhead on the basis of a rate per direct labor-hour. The company...

    Sallie Company applies factory overhead on the basis of a rate per direct labor-hour. The company provides you with the following data for the month of May 20X1. Selected inventories have different have the following balances: May 1 May 31 Work in process $78,000 $85,000 Finished goods 81,000 60,000 Prime costs for the month were: Direct Material used 48,000 Direct labor (45,000 actual labor-hours) 294,000 Sales have increased 20 percent over April's net sales of $500,000; as a result, gross...

  • Sallie Company applies factory overhead on the basis of a rate per direct labor-hour. The company...

    Sallie Company applies factory overhead on the basis of a rate per direct labor-hour. The company provides you with the following data for the month of May 20X1. Selected inventories have different have the following balances: May 1 May 31 Work in process $78,000 $85,000 Finished goods 81,000 60,000 Prime costs for the month were: Direct Material used 48,000 Direct labor (45,000 actual labor-hours) 294,000 Sales have increased 20 percent over April's net sales of $500,000; as a result, gross...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework