Pane Company produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the curren
Usage Overhead Cost Category (Activity Cost Pool) Supervision Depreciation of machinery Assembly line preparation Driver Dire
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans. A. Assigned the 3 cost as per ABC as under:

CALCULATION OF TOTAL COST (USING ABC METHOD)
ROUND AGE SQUARED AG TOTAL
A. DIRECT MATERIAL 9600 21800 31400
B. DIRECT LABOUR 6100 11900 18000
C. OVERHEAD
SUPERVISION 732 1428 2160
DEPRECIATION (MACHINE HRS) 9613.33 19226.67 28840
ASSEMBLY LINE PREP. 5704.00 17296.00 23000
ASSIGNED COST (16049.33) (37950.67) 54000
TOTAL COST 31749.33 71650.67 103400
PRODUCION IN SQ FT 10400 14100
B. PER FIT COST 3.052820192 5.081607801
NOTE: 1.SUPERVISION COST WILL BE SHARED IN THE RATION OF DIRECT LABOUR
ie. 61:119
2.DEPRECIATION IS TO SHARED BASED ON MACHINE HOURS USED. 4:8 OR 1:2
3.ASSEMBLY LINE PREPERATION EXP TO BE SHARED AS PER SET UP NUMBER
31:94

ANS. b. Average Cost will be as above 3.0528 & 5.0816 respectivly as calculated above.

Add a comment
Know the answer?
Add Answer to:
Pane Company produces two types of glass shelving, rounded edge and squared edge, on the same...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the current period, the company reports the following data. Direct materials Direct labor Overhead (382% of direct labor cost) Total cost Quantity produced Average cost per ft. (rounded) Rounded Edge $ 9,500 6.100 18,388 $ 33,982 10,688 ft. $ 3.20 Squared Edge Total $ 21,500 $ 31,000 11,900 18,00 35.700 54,00 $ 69,182 $183,888 14,288 ft. $ 4.87 Glassworks's controller wishes...

  • Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the current period, the company reports the following data. Direct materials Direct labor Overhead (3008 of direct labor cost) Total cost Quantity produced Average cost per ft. (rounded) Rounded Edge $ 9, 700 6.100 18,300 $34,100 10,300 ft. $ 3.31 Squared Edge Total $21,700 $ 31,400 11.900 18.000 35,700 54,000 $69,300 $103,400 14,000 ft. S 4.95 Glassworks's controller wishes to apply...

  • Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the current period, the company reports the following data. Glassworks's controller wishes to apply activity-based costing (ABC) to allocate the $54,000 of overhead costs incurred by the two product lines to see whether cost per foot would change markedly from that reported above. She has collected the following information. She has also collected the following information about the cost drivers for...

  • Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the current period, the company reports the following data. ota Direct materials Direct labor Overhead (300% of direct labor cost) Total cost Quantity produced Average cost per ft. (rounded) 6,100 18,300 34,100 10,300 ft. 11,980 5,700 A 18,000 54,000 69,300 103,400 14,000 ft. $ 3.31 4.95 Glassworks's controller wishes to apply activity-based costing (ABC) to allocate the $54,000 of overhead costs...

  • Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the current period, the company reports the following data Direct materials Direct labor Overhead (300x of direct labor cost) Total cost Quantity produced Average cost per ft. (rounded) Rounded Edge $ 9,600 6,100 18,309 534,000 10,700 ft. $ 3.18 Squared Edge Total $21,800 $ 31,400 11,900 18.000 35,700 54,000 569,400 $103, 400 14,200 ft. Glassworks's controller wishes to apply activity-based costing...

  • Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the current period, the company reports the following data. Direct materials Direct labor Overhead (300% of direct labor cost) Total cost Quantity produced Average cost per ft. (rounded) Rounded Edge $ 9,600 6,200 18.600 $34,400 10,500 ft. $ 3.28 Squared Edge Total $21,500 $ 31,100 11,900 18,100 35,700 54,300 $69,100 $103,500 14,200 ft. $ 4.87 Glassworks's controller wishes to apply activity-based...

  • Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the current period, the company reports the following data. Rounded Edge Squared Edge $21,700 11,900 35,700 $69,300 Total Direct materials $9,400 31,100 17,900 53,700 Direct labor 6,000 Overhead (300% of direct labor cost) 18,000 $33,400 $102,700 Total cost 10,600 ft. $ 3.15 Quantity produced 14,100 ft 4.91 Average cost per ft. (rounded) Glassworks's controller wishes to apply activity-based costing (ABC) to...

  • Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the current period, the company reports the following data. Direct materials $ 9,600 $ 21,600 $ 31,200 Direct labor 6,000 11,900 17,900 Overhead (300% of direct labor cost) 18,000 35,700 53,700 Total cost $ 33,600 $ 69,200 $ 102,800 Quantity produced 10,400 ft. 14,000 ft. Average cost per ft. (rounded) $ 3.23 $ 4.94    Glassworks's controller wishes to apply activity-based...

  • Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and squared edge, on the same production line. For the current period, the company reports the following data. Rounded Edge $ 9,300 6.200 Direct materials Direct labor Overhead (300 of direct labor cost) Total cost Quantity produced Average cost per ft. (rounded) 18,600 $34,100 10,600 ft. Squared Edge Total $21.500 11.00 18.000 35,400 $103,100 14,100 ft. Glassworks's controller wishes to apply activity based costing (ABC) to allocate the $54,000 of...

  • Glassworks Inc. produces two types of glass shelving, rounded edge and scared edge, on the same...

    Glassworks Inc. produces two types of glass shelving, rounded edge and scared edge, on the same production line. For the current period, the company reports the following data Over 1000 of direct labe ) Quantity pod Average cost per t rouded Glassworks's controller wishes to apply activity based costing (ABC) to allocate the $54000 of overhead costs incurred by the two product lines to see whether cost per foot would change markedly from that reported above. She has collected the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT