Question

Barnes Company applies overhead on the basis of machine hours. Given the...


Question 14 

Barnes Company applies overhead on the basis of machine hours. Given the following data, compute overhead applied and the under- or overapplication of overhead for the period: 


Estimated annual overhead cost  $3,000,000 

Actual annual overhead cost       $2,970,000 

Estimated machine hours           300,000

Actual machine hours  295,000 


1) $2,950,000 applied and $20,000 overapplied 

2) $3,000,000 applied and $20,000 overapplied 

3) $2,950,000 applied and $20,000 underapplied 

4) $2.970,000 applied and neither under- nor overapplied


Question 21 

Activity-based costing uses 

1) one plantwide pool and a single cost driver. 

2) departmental pools and a single cost driver. 

3) numerous cost pools and numerous cost drivers. 

4) one plantwide pool and numerous cost drivers

5 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Q.14. 3)$2,950,000 applied and $20,000 underapllied.

Q.21. 3) numerous cost pools and numerous cost drivers.

Explanation:- Activity-based costing(ABC) is a method that identifies activities in an organization and assigns the cost of each activity to all products and services according to the actual consumption by each.


Add a comment
Know the answer?
Add Answer to:
Barnes Company applies overhead on the basis of machine hours. Given the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT