Question

FOR THIS AND THE NEXT 4 QUESTIONS. (Investment Timing Option): Williams Industries, Inc. is interested in...

  1. FOR THIS AND THE NEXT 4 QUESTIONS. (Investment Timing Option): Williams Industries, Inc. is interested in building a new manufacturing plant in Nairobi, Kenya. The estimated initial cost of the project is $12 million. The company expects the investment will produce positive cash flows of $2.35 million per year for 9 years and $5 in the 10th and final year. The project's cost of capital is 11%. What is the project's net present value? It is recommended that you perform this analysis on spreadsheet.

    $2.773 million

    -$5.809 million

    -$4.715 million

    $11.557 million

    $9.38 million

    $2.814 million

    None of the above

  2. With respect to the above problem, Williams Industries actually expects cash flows to be much higher or lower depending on whether the Kenyan government imposes heavy tariffs on imported machine parts. As it stands, the company would not know until after 2 years if the tariffs will be imposed. There is a 70 percent chance the tariffs will be imposed, in which case the re-estimated annual cash flows (for 9 years) will only be $0.8 million. If the tariffs are not imposed, however, the re-estimated annual cash flows will be $4 million. Given this additional information, the company is contemplating whether to proceed with the project today or wait for 2 years to find out if the tariff will be imposed. At any time the project is begun, the investment period will still be 10 years. Also, the project cost remains $12 million and Year 10 cash flow (CF10) is still estimated to be $5 million. Cost of capital is 11%.
    If the company waits for 2 years to begin the project, calculate the NPV of the project today (i.e. at time zero), assuming the case where the government imposes the import tariffs. It is recommended that you perform this analysis on spreadsheet. However your may also use a financial calculator.

    $2.773 million

    -$5.809 million

    -$4.715 million

    $11.557 million

    $9.38 million

    $2.814 million

    None of the above

  3. If the company waits for 2 years to begin the project, calculate the NPV of the project today (i.e. at time zero), assuming the case where the government decides NOT to impose the import tariffs. Again, it is recommended that you perform this analysis on spreadsheet.

    $2.773 million

    -$5.809 million

    -$4.715 million

    $11.557 million

    $9.667 million

    $2.814 million

    None of the above

  4. What is the EXPECTED NPV if the firm decides to wait for two years? Please give this a thought.

    $2.773 million

    -$5.809 million

    -$4.715 million

    $11.557 million

    $9.38 million

    $2.9 million

    None of the above

  5. This problem is an example of investment timing option (ITO). In general, under what condition should the company proceed with the project today instead of waiting until the later time?

    The company should wait if the NPV of starting the project today exceeds the NPV of the case where the tariff is NOT imposed

    The company should wait if the NPV of starting the project today exceeds the NPV of the case where the tariff is imposed

    The company should wait if the NPV of starting the project today is LESS than the expected NPV of waiting

    The company should wait if the NPV of starting the project today is MORE than the expected NPV of waiting

    None of the above

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 1:

Correct answer is:

$2.773 million

Explanation:

Using excel function NPV:

10 Year Cash flows (in million S) Cost of capital = 2 4 6 7 9 ($12.000 $2.350$2.350 $2.350 $2.350 $2.350 $2.350 $2.350 $2.350 $2.350 $5.000 11% NPV $2.773 million

As such option A is correct and other options B, C, D, E, F and G are incorrect.

Answer 2:

Correct answer is:

- $4.715 million

Explanation:

Year Cash flows (in million $)$O Cost of capital 11% 0 4 5 9 10 12 $0 ($12.0001 so.800| $0.800| SO.800| $0.800. SO.800| $0.800 SO 800 SO 800. SO 800-SS000 NPV at end of year 2 $5.809million NPV today $4.715 milonNPV at the end of year calculated using NPV function of excel = -$5.809 million

NPV today = - $5.809 / (1 + 11%) ^2 = - $4.715

As such option C is correct and other options A, B, D, E, F and G are incorrect.

Answer 3:

Correct answer is:

$9.667 million

Explanation:

10 eseN Cash flows (in million $ Cost of capital NPV at end of year 2 0 4 5 6 12 9a) $0($12.000) $4.000 $4.000 $4.000 $4.000 $4.000 $4.000$4.000 $4.000 $4.000 $5.000 $11.909llion NPV today9.666 million

Closest option is option E.

As such option E is correct and other options A, B, C, D, F and G are incorrect.

Answer 4:

Correct answer is:

None of the above

Explanation:

Expected cash flow (from project start year to 9th year) = 70% * 0.8 + 30% * 4 = $1.76 million per year

Year Cash flows (in million S Cost of capital NPV at end of year 2 NPV today 10 0 S0 2 6 7 12 s0 $12.000) $1.760 $1.760 $1.760 $1.760 $1.760$1.760 $1.760 $1.760 $1.760 $5.000 11% $0.494 million -$0.401 millionExpected NPV at the end of year 2 = - $0.494 million

Expected NPV today = - $0.401 million

As such option G is correct and other options A, B, C, D, E and F are incorrect.

Answer 5:

Correct answer:

The company should wait if the NPV of starting the project today is LESS than the expected NPV of waiting

Explanation:

In cost benefit analysis, the scenario which results higher NPV should be accepted. As such if expected NPV of waiting is higher than NPV of starting project today, the company should wait.

As such option C is correct and other options A, B, D and E are incorrect.

Add a comment
Know the answer?
Add Answer to:
FOR THIS AND THE NEXT 4 QUESTIONS. (Investment Timing Option): Williams Industries, Inc. is interested in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT