Question

Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. TStandard labor-hours allowed Standard labor cost allowed Labor spending variance 4. Labor rate variance Labor efficiency vari

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER

1
Standard labor-hours allowed = 19,800*(24/60)= 7,920
2
Standard labor cost allowed =7,920*5.80= $45,936
3
Labor spending variance = 47,994-45,936= $2,058 U
4
Labor rate variance = 47,994 -(8,420*5.80)= $842 F
Labor efficiency variance = 5.80*(8,420-7,920)= $2,900 U
5
Variable overhead rate variance = 45,468-(8,420*4.50)= $7,578 U
Variable overhead efficiency variance = 4.50*(8,420-7,920)= $2,250 U

_____________________________________________

If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating.

*****************THANK YOU**************

Add a comment
Know the answer?
Add Answer to:
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its cos...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 24 minutes $5.80 $2.32 During August, 8,420 hours of direct labor time were needed to make 19,800 units of the Jogging Mate. The direct labor cost totaled $47,152 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 30 minutes Standard Rate per Hour $5.80 Standard Cost $2.90 During August, 10,520 hours of direct labor time were needed to make 19,800 units of the Jogging Mate. The direct labor cost totaled $59,964 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 27 minutes $6.40 $2.88 During August, 9,470 hours of direct labor time were needed to make 19,800 units of the Jogging Mate. The direct labor cost totaled $58,714 for the month. Required: 1. What is the standard labor-hours allowed...

  • 0 Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards...

    0 Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Standard Rate per Hour $6.40 Standard Cost $3.20 30 minutes During August, 10.500 hours of direct labor time were needed to make 19,800 units of the Jogging Mate. The direct labor cost totaled $66,150 for the month 1 0 Required: 1. What is the standard...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 24 minutes Standard Rate per Hour $5.80 Standard Cost $2.32 During August, 8,540 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $48,678 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 24 minutes Standard Rate Standard per Hour Cost $5.80 $5.80 $2.32 During August, 8,400 hours of direct labor time were needed to make 19,500 units of the Jogging Mate. The direct labor cost totaled $47,040 for the month. Required: 1. What is the standard labor-hours...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 24 minutes $6.00 $2.40 During August, 8,330 hours of direct labor time were needed to make 19,300 units of the Jogging Mate. The direct labor cost totaled $48,314 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 27 minutes $6.20 $2.79 During August, 9,580 hours of direct labor time were needed to make 19,600 units of the Jogging Mate. The direct labor cost totaled $57,480 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: ints Standard Hours 24 minutes Standard Rate Standard per Hour Cost $6.20 $2.48 eBook During August, 8,700 hours of direct labor time were needed to make 19,800 units of the Jogging Mate. The direct labor cost totaled $53,070 for the month. Hint Print eferences Required: 1. What...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 30 minutes Standard Rate per Hour $6.00 Standard Cost $3.00 During August, 10,690 hours of direct labor time were needed to make 20,000 units of the Jogging Mate. The direct labor cost totaled $63,071 for the month. Required: 1. What is the standard labor-hours allowed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT