Cost of Goods manufactured schedule
For the month ended June 30,2017
Work in process,June 1 3100
Direct materials used 22340
Direct labor 41010
Manufacturing overhead
Indirect factory labor 5440
Factory utilities 480
Depreciation, factory equipment 1500
Maintenance, factory equipment 1840
Indirect materials 2820
Factory manager's salary 3640
Total Manufacturing overhead 15720
Total Manufacturing costs 79070
Total cost of work in process 82170
Less: Work in process, June 30 4760
Cost of goods manufactured 77410
Add a comment
Know the answer?
Add Answer to:
Thank you! Grouper Corporation has the following cost records for June 2017. Indirect factory labor Direct...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Thank you! Grouper Corporation has the following cost records for June 2017. Indirect factory labor Direct materials us...

    Thank you! Grouper Corporation has the following cost records for June 2017. Indirect factory labor Direct materials used Work in process, 6/1/17 Work in process, 6/30/17 Finished goods, 6/1/17 Finished goods, 6/30/17 $5,440 Factory utilities 22,340 Depreciation, factory equipment 3,100 Direct labor 4,760 Maintenance, factory equipment 5,900 Indirect materials 7,690 Factory manager's salary $480 1,500 41,010 1,840 2,820 3,640 Prepare an income statement through gross profit for June 2017 assuming sales revenue is $87,610.

  • help with read part Cepeda Corporation has the following cost records for June 2020. Indirect factory...

    help with read part Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $5,440 22,340 3,100 4,760 5,900 7,690 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $480 1,500 41,010 1,840 2,820 3,640 (a) Prepare an income statement through gross profit for June 2020 assuming sales revenue is $87,610. CEPEDA CORPORATION Income...

  • Blue Corporation has the following cost records for June 2017. Indirect factory labor Direct materials used...

    Blue Corporation has the following cost records for June 2017. Indirect factory labor Direct materials used Work in process, 6/1/17 Work in process, 6/30/17 Finished goods, 6/1/17 Finished goods, 6/30/17 $5,220 Factory utilities 22,500 Depreciation, factory equipment 3,820 Direct labor 4,360 Maintenance, factory equipment 5,420 Indirect materials 8,300 Factory manager's salary $510 1,720 42,400 1,960 2,430 3,980 Prepare a cost of goods manufactured schedule for June 2017 BLUE CORPORATION Cost of Goods Manufactured Schedule For the Year Ended June 30,...

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,760 Factory utilities...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,760 Factory utilities $470 Direct materials used 22,680 Depreciation, factory equipment 1,540 Work in process, 6/1/20 3,540 Direct labor 42,930 Work in process, 6/30/204,880 Maintenance, factory equipment 1,850 Finished goods, 6/1/20 5,940 Indirect materials 2,820 Finished goods, 6/30/20 7,940 Factory manager's salary 3,120 (a) Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule Save for Later

  • Cepeda Corporation has the following cost records for June 2017 Indirect factory labor Direct materials used...

    Cepeda Corporation has the following cost records for June 2017 Indirect factory labor Direct materials used Work in process, 6/1/17 Work in process, 6/30/17 Finished goods, 6/1/17 Finished goods, 6/30/17 $5,400 21,100 3,860 3,980 6,050 7,930 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $460 1,620 41,620 1,990 2,910 3,960 CEPEDA CORPORATION Cost of Goods Manufactured Schedule Prepare an income statement through gross profit for June 2017 assuming sales revenue is $88,030. CEPEDA...

  • Exercise 14-12 Cepeda Corporation has the following cost records for June 2017, Indirect factory labor $4,640...

    Exercise 14-12 Cepeda Corporation has the following cost records for June 2017, Indirect factory labor $4,640 Factory utilities Direct materials used 22,900 Depreciation, factory equipment Work in process, 6/1/17 4,010 Direct labor Work in process, 6/30/17 4,570 Maintenance, factory equipment Finished goods, 6/1/17 5,690 Indirect materials Finished goods, 6/30/17 8,080 Factory manager's salary $490 1,660 41,660 1,820 2,730 3,990 Prepare a cost of goods manufactured schedule for June 2017. Prepare a cost of goods manufactured schedule for June 2017. CEPEDA...

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,600 Factory utilities...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,600 Factory utilities $410 1.500 Direct materials used 21,000 Depreciation, factory equipment 41,000 Work in process. 6/1/20 Work in process, 6/30/20 3,100 Direct labor 3.900 Maintenance, factory equipment 1.810 Finished goods, 6/1/20 Finished goods, 6/30/20 5.100 7,600 Indirect materials Factory manager's salary 2,100 3,100 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule

  • Waterway Corporation has the following cost records for June 2020. Indirect factory labor $4,760 Factory utilities...

    Waterway Corporation has the following cost records for June 2020. Indirect factory labor $4,760 Factory utilities $470 Direct materials used 22,680 Depreciation, factory equipment 1,540 Work in process, 6/1/20 3,540 Direct labor 42,930 Work in process, 6/30/20 4,880 Maintenance, factory equipment 1,850 Finished goods, 6/1/20 5,940 Indirect materials 2,820 Finished goods, 6/30/20 7,940 Factory manager’s salary 3,120 Prepare a cost of goods manufactured schedule for June 2020. WATERWAY CORPORATION Cost of Goods Manufactured Schedule For the Month Ended June 30,...

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $4,750 21,330 3,400 4,540 6,090 8,470 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $440 1,590 42,300 1,900 2,140 3,360 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule For the Year Ended June 30,...

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $5,070 22,870 3,260 3,910 6,070 7,840 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $430 1,570 41,420 1,900 2,400 3,680 Prepare an income statement through gross profit for June 2020 assuming sales revenue is $87,760. CEPEDA CORPORATION Income Statement (Partial) $ $ +...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT