Question

Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg, bal Jan 6,300 6,700 4,690 6,700 9,2
(2) If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year? (Round
0 0
Add a comment Improve this question Transcribed image text
Answer #1

In the books of ..............:

Date Account Titles and Explanations Debit Credit
$ $
Jan 31 Work in Process Inventory 9,300
Raw Materials Inventory 9,300
To record raw materials used
Jan 31 Work in Process Inventory 14,000
Factory Labor 14,000
To record factory labor used
Jan 31 Work in Process Inventory 11,200
Manufacturing Overhead 11,200
To record manufacturing overhead applied
Add a comment
Know the answer?
Add Answer to:
Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg, bal Jan...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For 2,000 Units Job No. 92 Manufacturing Direct Direct Labor Overhead Date Materials Beg, bal. Jan....

    For 2,000 Units Job No. 92 Manufacturing Direct Direct Labor Overhead Date Materials Beg, bal. Jan. 1 5,000 6,000 4,200 6,000 12 8,000 6,400 25 2,000 27 4,000 3,200 13,000 18,000 13,800 Cost of completed job: Direct materlals $13,000 Direct labor 18,000 Manufacturing overhead 13,800 $44,800 Total cost Unit cost ($44,800 - 2,000) $22.40 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work in Process Inventory on January 1 if...

  • Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan....

    Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 7,000 4,900 5,700 7,000 10,000 8,500 2,200 4,000 21,000 3,400 16,800 14,900 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,700 = 2,000) $14,900 21,000 16,800 $52,700 $26.35 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work in Process Inventory on January 1 if this was the...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 6,700 4,690 6,300 6,700 CON 9,200 7,360 2,600 4,800 20,700 3,840 15,890 15,600 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,190 + 2,000) $15,600 20,700 15,890 $52,190 $26.10 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 6,300 6,700 4,690 Jan. 1 8 12 25 27 6,700 9,200 7,360 2,600 4,800 3,840 15,60020,700 15,890 Cost of completed job Direct materials $15,600 20,700 15,890 $52,190 $26.10 Direct labor Manufacturing overhead Total cost Unit cost ($52,190 2,000) (a) On the basis of the foregoing data, answer the following questions (1) What was the...

  • CALCULATOR FULL Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg....

    CALCULATOR FULL Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal 6,000 4,200 5,000 6,000 8,000 2,000 4,000 18,000 13,000 13,800 $13,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (44,800 2,000) $44.800 On the basis of the foregoing data, answer the following (a) What was the balance in Work in Process Invente Balance in Work in Process Inventory on January (b) of manufacturing overhead is applied on...

  • A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Materials Labor Direct Manufacturing Date Overhead Beg. bal. 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Manufacturing overhead Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor Direct Materials 5,200 7,000 For 2,000 Units Manufacturing Overhead 4,900 7,000 Date Beg. bal. Jan. 1 8 12 25 27 10,000 8,000 2,900 5,000 4,000 16,900 15,100 22,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($54,000 = 2,000) $15,100 22,000 16,900 $54,000 $27.00 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead 4,900 Date 7,000 Beg. bal. Jan. 1 8 6,000 7,000 12 10,000 8,500 25 2,500 27 4,000 3,400 16,800 15,500 21,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($53,300 = 2,000) $15,500 21,000 16,800 $53,300 $26.65 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • Ajob order cost sheet for Sunland Company is shown below. Job No. 92 Direct Materials Direct...

    Ajob order cost sheet for Sunland Company is shown below. Job No. 92 Direct Materials Direct Labor Date For 2,000 Units Manufacturing Overhead 4.900 5,500 Beg. bal. Jan. 1 8 7.000 7.000 9,000 7,200 12 25 27 2.900 4,000 20,000 3.200 15,300 15,400 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($50,700 2.000) $15,400 20,000 15,300 $50.700 $25.35 (a) On the basis of the foregoing data, answer the following questions. (1) What was the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT