Question

Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October. The Input standards

Q5. What is the direct material efficiency variance? _________ Show calculation below.

Q6.     Given the info above, what is the direct labor rate variance? _________ Show calculation below.

Q7. Given the info above, the fixed overhead controllable variance is: _________ Show calculation below.

Q8. What is the variable overhead controllable variance? _________ Show calculation below.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution 5:

direct material efficiency variance = (SQ - AQ) *SP = (4800 - 5100)*$7 = $2,100 U

Solution 6:

Actual rate of labor = $92,500 / 7400 = $12.50 per hour

Direct labor rate variance = (SR - AR) * AH = ($12 - $12.50) * 7400 = $3,700 U

solution 7:

fixed overhead controllable variance = Budgeted fixed overhead - Actual fixed overhead = $20,000 - $21,000 = $1,000 U

Solution 8:

Variable overhead controllable variance = Standard cost of variable overhead - Actual cost of variable overhead

= (4800*$12) - $59,700 = $2,100 U

Add a comment
Know the answer?
Add Answer to:
Q5. What is the direct material efficiency variance? _________ Show calculation below. Q6.     Given the info...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October....

    Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October. The Input standards were: Std Quantity x Std Price per input =Std Cost per Output U Direct materials 1 lb./Output unit x $7/b. = $7 per output unit Direct labor 1.6 hrs. /Output unit x $12/hr. = $19.20 per unit Variable manufacturing (Mfg.) overhead 1.6 hrs. x $7.50 per hr = $12 per unit Fixed mfg. overhead (Budget $20,000) 1.6 hrs.. x $2.50 per...

  • Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October....

    Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October. The Input standards were: Std Quantity x Std Price per input =Std Cost per Output U Direct materials 1 lb./Output unit x $7/lb. = $7 per output unit Direct labor 1.6 hrs. /Output unit x $12/hr. = $19.20 per unit Variable manufacturing (Mfg.) overhead 1.6 hrs. x $7.50 per hr = $12 per unit Fixed mfg. overhead (Budget $20,000) 1.6 hrs.. x $2.50 per...

  • Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October....

    Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October. The Input standards were: Std Quantity * Std Price per input =Std Cost per Output U Direct materials 1 lb./Output unit x $7/lb. = $7 per output unit Direct labor 1.6 hrs. /Output unit x $12 /hr. = $19.20 per unit Variable manufacturing (Mfg.) overhead 1.6 hrs. * $7.50 per hr = $12 per unit Fixed mfg. overhead (Budget $20,000) 1.6 hrs.. x $2.50...

  • 9F P11-1A Practice Questions.docx Download Accessibility Mode Print Find IF Immers Rogen uses the standard cost...

    9F P11-1A Practice Questions.docx Download Accessibility Mode Print Find IF Immers Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October. The input standards were: Std Quantity x Std Price per input =Std Cost per Output U Direct materials 1 lb./Output unit x $7 /lb. = $7 per output unit Direct labor 1.6 hrs. /Output unit x $12/hr. - $19.20 per unit Variable manufacturing (Mfg.) overhead 1.6 hrs. x $7.50 per hr = $12...

  • I need help with finding what formulas to use and how to solve these two questions. 1. What is the direct labor rate variance? 2. What is the fixed overhead volume variance amount? The given: Martin C...

    I need help with finding what formulas to use and how to solve these two questions. 1. What is the direct labor rate variance? 2. What is the fixed overhead volume variance amount? The given: Martin Co. gathered the following actual results for the current month: Actual Units produced 3,000 Direct materials purchased and used (5,400 lbs.) $21,600 Direct labor cost (4,600 hours actual) $36,800 Manufacturing overhead costs incurred: $37,650 [=Variable $16,250 and Fixed $21,400] Machine hours (610 hours actual)...

  • 2. Compute the direct labor cost variance, including its rate and efficiency variances. Standard Cost Actual...

    2. Compute the direct labor cost variance, including its rate and efficiency variances. Standard Cost Actual Cost $ $ 0 0 0 0 3. Compute the overhead controllable and volume variances. Controllable Variance Actual overhead Budgeted overhead Controllable variance Fixed overhead volume variance Budgeted fixed overhead Fixed overhead cost applied Fixed overhead volume variance Check my work 1 ! Required information 12.5 [The following information applies to the questions displayed below.] points Trico Company set the following standard unit costs...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 64,000 units per quarter. The following flexible budget...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $144.00 128.00 72.00 96.00 $440.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 59.000 units per quarter. The following flexible budget information is...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) Direct labor (8 hrs. @ $15 per hr.) Factory overhead-Variable (8 hrs. @ $6 per hr.) Factory overhead-Fixed (8 hrs. @ $9 per hr.) Total standard cost $ 153.00 120.00 48.00 72.00 $ 393.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 65,000 units per quarter. The following flexible budget...

  • Trico Company set the following standard unit costs for its single product.      Direct materials (29...

    Trico Company set the following standard unit costs for its single product.      Direct materials (29 Ibs. @ $3 per Ib.) $ 87.00   Direct labor (6 hrs. @ $6 per hr.) 36.00   Factory overhead—variable (6 hrs. @ $4 per hr.) 24.00   Factory overhead—fixed (6 hrs. @ $5 per hr.) 30.00      Total standard cost $ 177.00    The predetermined overhead rate is based on a planned operating volume of 70% of the productive capacity of 60,000 units per quarter. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT