Nova Company’s total overhead cost at various levels of activity are presented below:
Month | Machine- Hours |
Total Overhead Cost |
|||
April | 52,000 | $ | 182,640 | ||
May | 42,000 | $ | 158,940 | ||
June | 62,000 | $ | 206,340 | ||
July | 72,000 | $ | 230,040 | ||
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is:
Utilities (variable) | $ | 54,600 |
Supervisory salaries (fixed) | 44,000 | |
Maintenance (mixed) | 60,340 | |
Total overhead cost | $ | 158,940 |
Nova Company’s management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $230,040 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $230,040 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)
2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.
3. Express the company’s total overhead cost in the form Y = a + bX.
4. What total overhead cost would you expect to be incurred at an activity level of 47,000 machine-hours?
Dear Student | |||||
Thank you for using homeworklib | |||||
Please find below the answer | |||||
Statementshowing Computations | |||||
Month | Machine hours | Total Overhead Cost |
Utilities at 1.30 per unit | Supervisory salaries | Maintenance = Total - utilities - Sal |
April | 52,000.00 | 182,640.00 | 67,600.00 | 44,000.00 | 71,040.00 |
May | 42,000.00 | 158,940.00 | 54,600.00 | 44,000.00 | 60,340.00 |
June | 62,000.00 | 206,340.00 | 80,600.00 | 44,000.00 | 81,740.00 |
July | 72,000.00 | 230,040.00 | 93,600.00 | 44,000.00 | 92,440.00 |
1) 92,440 | |||||
2) | |||||
Cost at highest level of activity | 92,440.00 | ||||
Cost at Lowest level of activity | 60,340.00 | ||||
Highest level of activity | 72,000.00 | ||||
Lowest Level of activity | 42,000.00 | ||||
Variable cost per unit = (92440- 60340)/(72000 - 42000) | |||||
Variable cost per unit = 32,100/30,000 | |||||
Variable cost per unit = $1.07 | |||||
Fixed Costs = 60340- 42000*1.07 | |||||
Fixed Costs = $15,400 | |||||
Y = 15,400 + 1.07x | |||||
3) Y = 59,400 + 2.37x | |||||
Since fixed cost = 44000 + 15400 | |||||
Variable cost = 1.30 + 1.07 | |||||
4) total overhead cost = 59,400 + 47000 * 2.37 = $170,790 | |||||
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 178,520 May 42,000 $ 155,920 June 62,000 $ 201,120 July 72,000 $ 223,720 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 50,400 Supervisory salaries (fixed) 42,000 Maintenance (mixed) 63,520 Total overhead cost $ 155,920 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 192,050 May 37,000 $ 168,550 June 57,000 $ 215,550 July 67,000 $ 239,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 66,000 Maintenance (mixed) 54,450 Total overhead cost $ 168,550 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 180,200 May 37,000 $ 156,200 June 57,000 $ 204,200 July 67,000 $ 228,200 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 55,000 Maintenance (mixed) 53,100 Total overhead cost $ 156,200 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 193,480 May 38,000 $ 169,880 June 58,000 $ 217,080 July 68,000 $ 240,680 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 45,600 Supervisory salaries (fixed) 67,000 Maintenance (mixed) 57,280 Total overhead cost $ 169,880 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 55,000 $ 183,500 May 45,000 $ 160,500 June 65,000 $ 206,500 July 75,000 $ 229,500 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 45,000 machine-hour level of activity is: Utilities (variable) $ 54,000 Supervisory salaries (fixed) 40,000 Maintenance (mixed) 66,500 Total overhead cost $ 160,500 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 46,000 $ 180,540 May 36,000 $ 156,640 June 56,000 $ 204,440 July 66,000 $ 228,340 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) $ 43,200 Supervisory salaries (fixed) 58,000 Maintenance (mixed) 55,440 Total overhead cost $ 156,640 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 54,000 $ 197,500 May 44,000 $ 172,000 June 64,000 $ 223,000 July 74,000 $ 248,500 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000 machine-hour level of activity is: Utilities (variable) $ 61,600 Supervisory salaries (fixed) 44,000 Maintenance (mixed) 66,400 Total overhead cost $ 172,000 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost April 52,000 $192,320 May 42,000 $166,720 June 62,000 $217,920 July 72,000 $243,520 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 58,800 Supervisory salaries (fixed) 43,000 Maintenance (mixed) 64,920 Total overhead cost $...
ova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 49,000 $ 199,830 May 39,000 $ 173,130 June 59,000 $ 226,530 July 69,000 $ 253,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) $ 58,500 Supervisory salaries (fixed) 55,000 Maintenance (mixed) 59,630 Total overhead cost $ 173,130 Nova Company’s...
Nova Company’s total overhead Nova Company's total overhead cost at various levels of activity are presented below! Month April May June July Total Machine - Overhead Hours Cost 47,000 $187,050 37,000 $159,550 57,000 $214,550 67,000 $242,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 55,500 40,000 64,050 $159,550 Nova Company's...