Question

6. What is the primary goal of accounting? A. To set long-term goals and objectives. B. To arrange for the necessary resource
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solutions:

6. C. To provide information for decision making

7. C. Overhead Over-applied by $12500

Predetermined Ovrehead rate = 250000/20000 = $12.5

Overhead Applied = 19000*$12.5 = 237500

Actual Overhead = 225000

Overapplied Overhead = 237500-225000 = $12500

8. C. Decrease Cost of Goods Sold

9. B. $1500 per batch

Inspection Cost = $90000

Total Number of Batches = 60

Cost of Inspection per batch = $90000/60 = $1500

10. C. Cost of Goods Sold

12. A. are incurred to prevent the quality problems from occuring in the first place

Add a comment
Know the answer?
Add Answer to:
6. What is the primary goal of accounting? A. To set long-term goals and objectives. B....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 6. What is the primary goal of accounting? A. To set long-term goals and objectives. B....

    6. What is the primary goal of accounting? A. To set long-term goals and objectives. B. To arrange for the necessary resources to achieve a plan. C. To provide information for decision making. D. To motivate employees to work towards a plan's success. 7. Manufacturing overhead was estimated to be $250,000 for the year along with 20,000 direct labor hours. Actual manufacturing overhead was $225.000, and actual direct labor hours were 19.000. Which of the following would be correct? A....

  • 6. What is the primary goal of accounting? A. To set long-term goals and objectives. B....

    6. What is the primary goal of accounting? A. To set long-term goals and objectives. B. To arrange for the necessary resources to achieve a plan. C. To provide information for decision making. D. To motivate employees to work towards a plan's success. 1. Manufacturing overhead was estimated to be $250,000 for the year along with 20,000 direct labor hours Actual manufacturing overhead was $225.000, and actual direct labor hours were 19.000. Which of the following would be correct? A....

  • 6. s (Product C and Product 2) using two different activities Machining, which uses machine hours...

    6. s (Product C and Product 2) using two different activities Machining, which uses machine hours as an . The cost of Machining is $945,000, while the cost of Inspection is Washington, Inc. produces two different products (Product C and Product 2) using two different actvities Machining activity driver, and Inspection, which uses number of batches as an activity driver $37.370 The activity drivers are used as follows Machine hours Number of batches Product C 1,900 53 Product 2 3,500...

  • COVID 19 Co. produces two different products (Product Yand Product B) using two different activities Machining,...

    COVID 19 Co. produces two different products (Product Yand Product B) using two different activities Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The activity rate for Machining is $125 per machine hour, and the activity rate for Inspection is $500 per batch. The activity drivers are used as follows: Product Y Product B Total Machine hours 1,000 3.000 4,000 Number of batches 45 15 60 What is...

  • COVID 19 Co produces two different products (Product Yand Product B) using two different activities. Machining,...

    COVID 19 Co produces two different products (Product Yand Product B) using two different activities. Machining, which uses machine hours as an activity driver and Inspection, which uses number of batches as an activity driver. The activity rate for Machining is $125 per machine hour, and the activity rate for Inspection is $500 per batch. The activity drivers are used as follows: Product Y Product B Total Machine hours 1,000 3.000 4.000 Number of batches 45 15 60 What is...

  • 8.Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing...

    8.Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs...

  • drivers are as follows: Design Engineering Hours) Machining Machine Hours) Inspection (Batches) Cost $164,406 $583,800 $...

    drivers are as follows: Design Engineering Hours) Machining Machine Hours) Inspection (Batches) Cost $164,406 $583,800 $ 25,650 Usage by Product A 208 1,130 38 Usage by Product B 309 3,040 16 49 Walnut manufactures 10,800 units of Product A and 6,600 units of Product B per month. Each unit of Product A uses $48 of direct materials and $20 of direct lobor, while each unit of Product Buses $65 of direct materials and $26 of direct labor. Required: a. Calculate...

  • COVID Co. produces two different products (Product Y and Product B) using two different activities: Machining,...

    COVID Co. produces two different products (Product Y and Product B) using two different activities: Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The cost of Machining is $500,000, while the cost of Inspection is $30,000. Product Y uses 20% of total machine hours and 75% of total batches. What is the total Machining cost assigned to Product B? Select one: a. $400,000 O b $22,500 C. $7.500...

  • COVID Co. produces two different products (Product Y and Product B) using two different activities: Machining,...

    COVID Co. produces two different products (Product Y and Product B) using two different activities: Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The cost of Machining is $500,000, while the cost of Inspection is $30,000. Product Y uses 20% of total machine hours and 75% of total batches. What is the total Machining cost assigned to Product B? Select one: a. $400,000 O b $22,500 C. $7.500...

  • Answers for the questions: A) 695 B) 149,425 C) 9,425 (Overapplied overhead cost) D) 338,950 E)...

    Answers for the questions: A) 695 B) 149,425 C) 9,425 (Overapplied overhead cost) D) 338,950 E) 209,025 (Chapter 4) Chapter 4 Problem 1 Please use the following information to answer questions G-e: Gateway hod only one lob in process during August (Job 2922) and had no finished goods inventory on August 14 Job 2922 was started in July and finished during August. Data pertaining to the job is as follows: Job 2922 Beginning WIP balance on August Materials ($172,000 wos...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT