Question

Erie Company manufactures a small mp3 player called the Jogging Mate. The company uses standards to control its costs. The la2. Break down the difference in cost from (1) above into a labor rate variance and a labor efficiency variance. (Indicate the3. The budgeted variable manufacturing overhead rate is $4.1 per direct labor-hour. During August, the company incurred $51,8

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) Schedule

Number of unit manufactured 19400
Standard labor time per unit 0.50
Standard labor hour allowed 9700
standard labor cost per hour 6.20
Total Standard labor cost 60140
Actual labor cost 63257
Total Standard labor cost 60140
Total labor variance 3117 U

2) Labor rate variance = (6.2*10370-63257) = 1037 F

Labor efficiency variance = (9700-10370)*6.2 = 4154 U

3) variable overhead rate variance = (4.1*10370-51850) = 9333 U

Variable overhead efficiency variance = (9700-10370)*4.1 = 2747 U

Add a comment
Know the answer?
Add Answer to:
Erie Company manufactures a small mp3 player called the Jogging Mate. The company uses standards to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Erie Company manufactures a small mp3 player called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a small mp3 player called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate mp3 player are as follows: Standard Hours   Standard Rate per Hour   Standard Cost 30 minutes   $6.00   $3.00 During August, 10,380 hours of direct labor time were needed to make 19,200 units of the Jogging Mate. The direct labor cost totaled $61,242 for the month. Required: 1.   According to the standards,...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 27 minutes Standard Rate per Hour $5.60 Standard Cost $2.52 During August, 9,240 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $50,820 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 24 minutes Standard Rate per Hour $5.80 Standard Cost $2.32 During August, 8,540 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $48,678 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 24 minutes Standard Rate per Hour $6.20 Standard Cost $2.48 During August, 8,460 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $50,760 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 27 minutes $6.40 $2.88 During August, 9,460 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $58,652 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 30 minutes Standard Rate per Hour $5.60 Standard Cost $2.80 During August, 10,280 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $56,540 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 24 minutes $6.00 $2.40 During August, 8,440 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $48,952 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 30 minutes Standard Rate per Hour $5.60 Standard Cost $2.80 During August, 10,280 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $56,540 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erle Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erle Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 24 minutes Standard Rate per Hour $6.20 Standard Cost $2.48 During August, 8,270 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $49,620 for the month. Required: 1. What is the standard labor-hours allowed...

  • Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

    Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours 30 minutes Standard Rate per Hour $6.00 Standard Cost $3.00 During August, 10,690 hours of direct labor time were needed to make 20,000 units of the Jogging Mate. The direct labor cost totaled $63,071 for the month. Required: 1. What is the standard labor-hours allowed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT