Question

Question 1 Waterway Furniture Company started construction of a combination office and warehouse building for its own use at

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) Construction loan is specific loan, therefore the whole amount of interest on construction loan is included in avoidable interest and for other two borrowings, we need to calculate weighted average interest rate which is calculated as follows:-

Calculation of Weighted Average Interest Rate (Amounts in $)

Loan Amount of Loan (A) Interest rate (B) Interest expense (A*B)
Short Term loan 1,606,700 8% 128,536
Long Term loan 993,300 9% 89,397
Total 2,600,000 217,933

Weighted Average Interest Rate = Total interest on General loan/Total Amount of General Loan

= ($217,933/$2,600,000)*100 = 8.38%

Calculation of Avoidable Interest (Amounts in $)

Interest on Construction Loan (2,015,800*10%) 201,580
Interest on Balance Accumulated Expenditure [(3,810,800-2,015,800)*8.38%] 150,421
Total Avoidable Interest 352,001

Therefore avoidable interest on this project is $352,001 (It will be capitalized to the cost of building).

b) Cost of Building = $5,195,900+$352,001 = $5,547,901

Depreciation Expense under Straight line = (Cost - Salvage Value)/Useful Life in yrs

= ($5,547,901-$299,200)/30 yrs = $174,957

Therefore the depreciation expense for the year ended December 31, 2018 is $174,957.

Add a comment
Know the answer?
Add Answer to:
Question 1 Waterway Furniture Company started construction of a combination office and warehouse building for its...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 10-7 Flint Furniture Company started construction of a combination office and warehouse building for its own u...

    Exercise 10-7 Flint Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,957,500 on January 1, 2017. Flint expected to complete the building by December 31, 2017. Flint has the following debt obligations outstanding during the construction period. Construction loan-10% interest, payable semiannually, issued December 31, 2016 Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 2018 Long-term loan-9% interest, payable on January 1 of each year. Principal payable...

  • Flint Furniture Company started construction of a combination office and warehouse building for its own use...

    Flint Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,035,800 on January 1, 2017. Flint expected to complete the building by December 31, 2017. Flint has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2016 $1,991,900 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,607,900 Long-term loan-11% interest, payable on January 1 of...

  • Wildhorse Furniture Company started construction of a combination office and warehouse building for its own use...

    Wildhorse Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,000,200 on January 1, 2017. Wildhorse expected to complete the building by December 31, 2017. Wildhorse has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2016 $2,007,800 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,588,200 Long-term loan-11% interest, payable on January 1 of...

  • Larkspur Furniture Company started construction of a combination office and warehouse building for its own use...

    Larkspur Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,004,000 on January 1, 2017. Larkspur expected to complete the building by December 31, 2017. Larkspur has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2016 $1,990,900 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,599,600 Long-term loan-11% interest, payable on January 1 of...

  • Flint Furniture Company started construction of a combination office and warehouse building for its own use...

    Flint Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,024,700 on January 1, 2017. Flint expected to complete the building by December 31, 2017. Flint has the following debt obligations outstanding during the construction period Construction loan-12% interest, payable semiannually, issued December 31, 2016 $2,002,200 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,598,900 Long-term loan-11% interest, payable on January 1 of...

  • Question 3 Headland Furniture Company started construction of a combination office and warehouse building for its...

    Question 3 Headland Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $9,500,000 on January 1, 2020. Headland expected to complete the building by December 31, 2020. Headland has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of...

  • Stellar Furniture Company started construction of a combination office and warehouse building for its own use...

    Stellar Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $11,000,000 on January 1, 2020. Stellar expected to complete the building by December 31, 2020. Stellar has the following debt obligations outstanding during the construction period. $4,400,000 Construction loan-12% interest, payable semiannually, issued December 31, 2019 3,080,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of...

  • Carla Furniture Company started construction of a combination office and warehouse building for its own use...

    Carla Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $6,000,000 on January 1, 2020. Carla expected to complete the building by December 31, 2020. Carla has the following debt obligations outstanding during the construction period. Construction loan-14% interest, payable semiannually, issued December 31, 2019 $2,400,000 Short-term loan-12% interest, payable monthly, and principal payable at maturity on May 30, 2021 1,680,000 Long-term loan-13% interest, payable on January 1 of...

  • Sheridan Furniture Company started construction of a combination office and warehouse building for its own use...

    Sheridan Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,500,000 on January 1, 2020. Sheridan expected to complete the building by December 31, 2020. Sheridan has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of each year....

  • Oriole Furniture Company started construction of a combination office and warehouse building for its own use...

    Oriole Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,500,000 on January 1, 2020. Oriole expected to complete the building by December 31, 2020. Oriole has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,400,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 3,780,000 Long-term loan-11% interest, payable on January 1 of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT