Reconstruction of pavement should be started in 2020 as Reconstruction cost will be $275000 and interest rate will be 6% so interest rate for 1st year will be 16500, end of year benefit in 2020 is 18000 which is more than interest cost for viability of the project. BCA for the project is more than 1 if construction start in 2020 and the same have useful life of 15 years. Realisation after interest component will be more than $275000 in 15 years considering interest @ 6% and realisation increasing $2000 per year and so on.