Ans 3.37 years
Year | Cash Flow | Cumulative Cash Flow |
0 | -23900 | -23900 |
1 | 7100 | -16800 |
2 | 7750 | -9050 |
3 | 7150 | -1900 |
4 | 5200 | 3300 |
TOTAL | 3300 | |
Payback Period = | 3 YEARS + 1900/5200 | |
3.37 YEARS |
EXAM - Chap. 1-8 i There is a project with the following cash flows : Year...
There is a project with the following cash flows : Year AWN-o Cash Flow -$23,900 7,100 7,750 7150 5,200 What is the payback period?
There is a project with the following cash flows : Year 1 2 Cash Flow -$25,150 7,300 8,400 7,250 7,850 6,900 3 4 5 What is the payback period? Multiple Choice O 4.00 years O 3.28 years O 3.54 years O 3.85 years 2.70 years
What is the payback period for the following set of cash flows? Cash Flow Year -$ 3,900 1 1,200 2 2,500 3 1,500 4 2.900 Multiple Choice 2.08 years 215 years Multiple Choice 2.08 years 2.15 years 2.13 years 243 years 2.24 years Grohl Co. issued 15-year bonds a year ago at a coupon rate of 8 percent. The bonds make semiannual payments. If the YTM on these bonds is 11 percent, what is the current bond price? Multipte Choice...
Consider the following project cash flows: Year 2 Cash Year 3 Cash Project Year 0 Cash Flow Year 1 Cash Flow Discount Rate Flow Flow A L -113 42 42 / 42 16% The payback period for project A is closest to: O 2.4 years O 2.0 years 2.2 years 0 2.5 years
Problem 8-8 Payback (LO4) The following are the cash flows of two projects: Year Project A Project B 310 140 140 140 140 -$ 310 210 210 210 What is the payback period of each project? (Round your answers to 1 decimal place.) Project Payback Period years years
3. (8 marks) A proposed project has the following cash flows and a required return of 12%. Year Cash Flow -450 250 -75 400 a) What is the payback period? (1.5 marks) 250-450 = -200 -75-200= -275 400-275-125 275/400=0.6875 So, 2.69 years to pay back. b) What is the discounted payback period? (2.5 marks) What is the NPV? (1 mark) d) What is the PI? (1 mark) e) Is it possible for this project to have multiple IRRs? If so,...
What is the payback period for the following set of cash flows? Year Cash Flow 0 −$ 1,900 1 1,500 2 1,900 3 2,000 4 1,900 Multiple Choice 1.27 years 1.16 years 1.21 years 1.51 years 1.23 years
Two mutually exclusive projects have the following projected cash flows: Year Project A Cash flow Project B Cash Flow 0 -$50,000 -$50,000 1 25,625 0 2 25,625 0 3 25,625 0 4 25,625 0 5 15,625 150,000 If the required rate of return on these projects is 20 percent, what are the NPVs of two projects? Which project should be better? If they are standalone projects, what is the choice? If IRRA = 40.36%, IRRB = 24.57%, which project should...
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Project A Project B Year Cash Flow...
What is the payback period for the following set of cash flows? Year Cash Flow 0 −$ 4,100 1 1,900 2 2,600 3 1,500 4 1,100 Multiple Choice : 1.80 years 1.94 years 1.85 years 2.15 years 1.87 years