2. A company has the following information for Job Alpha during July: Units produced Actual materials used (and purchased) 56

a. If the company uses a normal costing system, calculate the costs incurred by Job Alpha in July.

b. If the company uses a standard costing system, calculate the costs incurred by Job Alpha in July.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Requirement a: Compute the costs incurred under normal costing system as follows

Particulars Amount
Direct material (7,831 lbs. × $13.30 per lbs.) $104,152.00
Direct labor (2,978 hours × $38 per hour) $113,164.00
Overhead allocated (2,978 hours × ($6.60 + $4.40)) $32,758.00
Cost incurred for the job $250,074.00

Requirement b: Compute the costs incurred under standard costing system as follows

Particulars Amount
Direct material (565 units × 15.4 lbs. × $12.10 per lbs) $105,282.10
Direct labor (565 units × 6.20 hours × $33 per hour) $115,599.00
Overhead allocated (565 units × 6.20 hours × ($6.60 + $4.40)) $38,533.00
Cost incurred for the job $259,414.10
Add a comment
Know the answer?
Add Answer to:
a. If the company uses a normal costing system, calculate the costs incurred by Job Alpha...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • a. Calculate the materials' flexible budget for Job Alpha in July. b. Calculate the materials price...

    a. Calculate the materials' flexible budget for Job Alpha in July. b. Calculate the materials price variance for Job Alpha. c. Calculate the materials quantity variance for job Alpha in July. d. Calculate the direct labor flexible budget for Job Alpha in July. 2. A company has the following information for Job Alpha during July: Units produced Actual materials used (and purchased) Actual Materials Cost Actual labor hours incurred Actual labor rate 565 7,831 lbs. 13.30 per pound 2,978 38.00...

  • Snappy Company has a job-order costing system and uses a predetermined overhead rate based on direct...

    Snappy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $108,000 and 45,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $3,050 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Snappy had worked a total of 51,000...

  • Kansas Company uses a job costing accounting system for its production costs. The company uses a...

    Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows. Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,200,000 $ 1,440,000 $ 1,680,000 Fixed overhead costs 702,000 702,000 702,000 Total overhead $ 1,902,000 $ 2,142,000 $ 2,382,000 The expected volume is 180,000 direct...

  • Haughton Company uses a job costing system for its production costs and a predetermined factory overhead...

    Haughton Company uses a job costing system for its production costs and a predetermined factory overhead rate based on direct labor costs to apply factory overhead to all jobs. During the month of July, the firm processed three jobs: X13, X14, and X15, of which X13 was started in June. July 1 Inventories Direct Materials Work-in-Process Finished Goods $ 36,500 41,000 Cost of Goods Sold Direct materials purchased in July 55,000 Materials issued to production: X13 x14 x15 16,380 24,220...

  • Kansas Company uses a job costing accounting system for its production costs. The company uses a...

    Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours Variable overhead costs Fixed overhead costs Total overhead 150,000 $1,050,000 648,000 $1,698,000 180,000 $1,260,000 648,000 $1,908,000 210,000 $1,470,000 648,000 $2,118,000 The expected volume is 180,000 direct labor-hours for the entire year. The...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 1,620,000 Job Omega Direct...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $19.50 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 55,900 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 2,230,000 Job Omega Direct...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 1,620,000 Job Omega Direct...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.50 per hour. During the year, the company started and completed only two jobs-Job Alpha, which used 68,700 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below. Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost $ 1,722,000 Job Omega Direct materials Direct labor...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $19.50 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 55,900 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost $ 2,230,000 Job Omega Direct materials Direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT