Question

2. Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours....

2.

Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:


  
  Machine-hours required to support estimated production 158,000
  Fixed manufacturing overhead cost $ 650,000
  Variable manufacturing overhead cost per machine-hour $ 4.40
Required:
1.

Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.)

     

2.

During the year, Job 400 was started and completed. The following information was available with respect to this job:

   

  
  Direct materials requisitioned $ 310
  Direct labor cost $ 240
  Machine-hours used 35


Compute the total manufacturing cost assigned to Job 400. (Do not round intermediate calculations and round final answer to 2 decimal places.)

     

3-a.

During the year the company worked a total of 146,000 machine-hours on all jobs and incurred actual manufacturing overhead costs of $1,246,960. What is the amount of underapplied or overapplied overhead for the year? (Use the overhead rate determined in requirement 1.)

       

3-b.

If this amount were closed out entirely to Cost of Goods Sold, would net operating income increase or decrease?

Increase
Decrease
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Fixed manufacturing Overhead Cost = $650,000 Variable manufacturing overhead Cost = $4.40 x 158,000 = $695,200 Total manufa. Actual manufacturing overhead Cost&= $1,246,960 Applied manufacturing overhead Cost &= $ 1,242,460 [146,000 $2.51] - $1,24

Add a comment
Know the answer?
Add Answer to:
2. Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 100,000 Fixed manufacturing overhead cost $ 650,000 Variable manufacturing overhead cost per machine-hour $ 3.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 158,000 Fixed manufacturing overhead cost $ 651,000 Variable manufacturing overhead cost per machine-hour $ 4.30 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 158,000 652,000 $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job Direct materials Direct labor...

  • Moody Corporation uses a job-order costing system with a plant wide overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plant wide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production…………100,000 Fixed manufacturing overhead cost……………………………….$650,000 Variable manufacturing overhead cost per machine-hour…………$3.0 Required: 1. Compute the predetermined overhead rate During the year, Job 400 was started and completed. The following information was available with respect to the job: Direct materials requisitioned…………………..$450 Direct labor cost………………………………...$210 Machine-hours used……………………………….40 2. Compute...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 155,000 $651,000 4.40 Required 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job Direct materials Direct labor cost...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 151,000 Fixed manufacturing overhead cost $ 657,000 Variable manufacturing overhead cost per machine-hour $ 4.30 Required: 1. Compute the plantwide predetermined overhead rate. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Compute the plantwide predetermined...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 158,000 $ 652,000 4.90 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct labor...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: ots Machine-hours required to support estimated production 152, eee Fixed manufacturing overhead cost $659,800 Variable manufacturing overhead cost per machine-hour $ 4.30 - eBook Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job!...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 158,000 Fixed manufacturing overhead cost $ 655,000 Variable manufacturing overhead cost per machine-hour $ 4.60 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 157,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT