Question

EXERCISE 11–3 Measures of Internal Business Process Performance [LO11–3] Guided Example 11-3 Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:

Inspection time . . . . . . . . . Wait time (from order to start of production) ........ Process time .... Move time ...... Q

Compute the throughput time.

Compute the manufacturing cycle efficiency (MCE) for the quarter.

What percentage of the throughput time was spent in non–value-added activities?

Compute the delivery cycle time.

If by using Lean Production all queue time during production is eliminated, what will be the new MCE?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Inspection time 0.3
Process time 2.7
Move time 1.0
Queue time 5.0
Throughput time 9.0 days
2
Process time 2.7
Divide by Throughput time 9.0
Manufacturing cycle efficiency (MCE) 30%
3
Non-value-added throughput time 70% =1-30%
4
Throughput time 9.0
Wait time 14.0
Delivery cycle time 23.0 days
5
New Manufacturing cycle efficiency 67.5% =2.7/(0.3+2.7+1)
Add a comment
Know the answer?
Add Answer to:
EXERCISE 11–3 Measures of Internal Business Process Performance [LO11–3] Guided Example 11-3 Management of Mittel Rhein...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln,...

    Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.7 days 15.2 days 3.2 days 0.7 days 4.0 days Required:...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between w...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.3 days 15.4 days 3.4 days 1.4 days 4.2 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 16.6 days Process time 2.9 days Move time 0.8 days Queue time 4.3 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.6 days Wait time (from order to start of production) 15.6 days Process time 2.9 days Move time 0.8 days Queue time 4.5 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.6 days Wait time (from order to start of production) 15.2 days Process time 2.9 days Move time 1.2 days Queue time 4.1 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.3 days 16.7 days 3.0 days 1.1 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 16.5 days Process time 3.1 days Move time 1.1 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.6 days 16.5 days 2.7 days 1.3 days 4.1 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 16.4 days 3.0 days 0.7 days 3.7 days Required: 1. Compute the throughput time. (Round your answer to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT