3) Non - value added throughput time: 66%

Explanation:

If the Manufacturing Cycle Efficiency  is 34%,

then 34% of the throughput time was spent in value-added activities

Consequently, the other 66% ( 100 -34) of the throughput time was spent in non-value-added activities.

5) New Manufacturing Cycle Efficiency:

If all queue time is eliminated, then the throughput time drops to only 4.4 days (0.3 + 2.8 + 1.3).

The MCE becomes:

= Value Added time ÷ throughput time

= 2.8 ÷ 4.4

= 63.6%

Add a comment
Know the answer?
Add Answer to:
Management of Mittel Rhein AG of Koln, Germany, would like to reduce the amount of time...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between w...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.3 days 16.7 days 3.0 days 1.1 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 16.5 days Process time 3.1 days Move time 1.1 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.6 days 16.5 days 2.7 days 1.3 days 4.1 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 16.4 days 3.0 days 0.7 days 3.7 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) 0.4 days 16.0 days 2.9 days 0.6 days 3.6 days Process time Move time Queue time Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection t ime Wait time (from order to start of production) Process time 0.6 days 16.9 days 3.2 days 0.7 days 4.4 days Move time Queue time Required: 1. Compute the throughput time. (Round your answer...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order tostart of production) Process time Move time 0.2 day 17.0 days 3.2 days 0.5 day 3.7 days Queue time Required: 1.Compute the throughput time. (Round your answer to 1 decimal...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.3 days 15.4 days 3.4 days 1.4 days 4.2 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 16.6 days Process time 2.9 days Move time 0.8 days Queue time 4.3 days Required: 1. Compute the throughput time. (Round your answer to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT