Question

Which of the following is true if the actual labor rate exceeds the standard labor rate...

Which of the following is true if the actual labor rate exceeds the standard labor rate and the actual labor hours exceed the number of hours allowed?

a.

Materials Usage Variance Unfavorable; Materials Efficiency Variance Favorable

b.

Labor Rate Variance Favorable; Labor Efficiency Variance Favorable

c.

Labor Rate Variance Unfavorable; Labor Efficiency Variance Unfavorable

d.

Materials Usage Variance Favorable; Materials Efficiency Variance Unfavorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

answer : c. Labor Rate Variance Unfavorable ; Labor Efficiency Variance Unfavorable

explanation

labor rate variance

1.the following formula is used to calculate the labor rate variance

labor rate variance =( actual rate - standard rate )*actual hours worked

2. it shows the difference between actual amount paid to the workers and standard amount paid to the worker

3. if the actual rate exceeds the standard rate it is Unfavorable variance

labor efficiency variance

1. labor efficiency variance is used to measure the ability to utilize  the labor in accordance with expectations .

2. the following formula is used for calculating the labor efficiency variance

labor efficiency variance = (actual hours worked - standard hours )* standard rate

3. if the actual hours worked exceeds the standard hours or number of hours allowed it is unfavorable labor efficiency variance

Add a comment
Know the answer?
Add Answer to:
Which of the following is true if the actual labor rate exceeds the standard labor rate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ideal standards O do not allow for machine breakdowns, slack, or lack of skill (even momentarily)....

    Ideal standards O do not allow for machine breakdowns, slack, or lack of skill (even momentarily). demand maximum efficiency. can be achieved only if everything operates perfectly All of these. O None of these. 4.5 points Save Answer QUESTION 13 If the actual labor rate exceeds the standard labor rate and the actual labor hours exceed the number of hours allowed, the labor rate variance and labor efficiency variance will be Labor Rate Labor Efficiency Variance Variance Favorable Favorable Favorable...

  • Question 5 (1 point) Consider the following information: Actual hours used 15,000 Standard hours allowed 15,500...

    Question 5 (1 point) Consider the following information: Actual hours used 15,000 Standard hours allowed 15,500 Actual rate $14.50 per hour Standard rate $15.00 per hour Which of the following are the direct-labor rate variance and the direct-labor efficiency variance, respectively? $7,500 favorable and $7,500 unfavorable $7,750 unfavorable and $7,500 favorable O$7,750 favorable and $7,250 unfavorable $7,500 favorable and $7,250 unfavorable O $7,500 favorable and $7,500 favorable

  • Materials and Labor Variances At the beginning of the year, Craig Company had the following standard...

    Materials and Labor Variances At the beginning of the year, Craig Company had the following standard cost sheet for one of its plastic products: Direct materials (5 lbs. @ $4.00) $20.00 Direct labor (2 hrs. @ $15.00) 30.00 Standard prime cost per unit $50.00 The actual results for the year are as follows: Units produced: 500,000. Materials purchased: 3,500,000 pounds @ $5.35. Materials used: 3,000,000 pounds. Direct labor: 950,000 hours @ $12.96. Required: 1. Compute price and usage variances for...

  • At the beginning of the year, Craig Company had the following standard cost sheet for one of its plastic products: Direct materials (5 lbs. @ $4.00) $20.00 Direct labor (2 hrs. @ $15.00) 30.00 Standard prime cost per unit $50.00 The actual results for th

    At the beginning of the year, Craig Company had the following standard cost sheet for one of its plastic products:Direct materials (5 lbs. @ $4.00)$20.00Direct labor (2 hrs. @ $15.00)30.00Standard prime cost per unit$50.00The actual results for the year are as follows:Units produced: 400,000.Materials purchased: 2,060,000 pounds @ $3.95.Materials used: 2,100,000 pounds.Direct labor: 825,000 hours @ $14.85.Required:1.  Compute price and usage variances for materials. Enter amounts as positive numbers and select Favorable or Unfavorable.Material price variance$fill in the blank 1Favorable Material...

  • Which of the following will result in an unfavorable direct labor PRICE variance? when actual direct...

    Which of the following will result in an unfavorable direct labor PRICE variance? when actual direct labor hours exceed standard direct labor hours when actual direct labor hours are less than standard direct labor hours when the actual direct labor rate exceeds the standard direct labor rate when the actual direct labor rate is less than the standard direct labor rate

  • The following data reflect the current month's activity for Vickers Corporation. Actual total direct labor Actual...

    The following data reflect the current month's activity for Vickers Corporation. Actual total direct labor Actual hours worked Standard labor-hours allowed for actual output (flexible budget) Direct labor price variance Actual variable overhead Standard variable overhead rate per standard direct labor-hour $671,460 38,000 36,900 $ 12,540 F $154,500 $ 4.10 Variable overhead is applied based on standard direct labor-hours allowed. Required: Compute the labor and variable overhead price and efficiency variances. (Indicate the effect of each variance by selecting "F"...

  • 5) The following information is presented for the Maybeel Manufacturing Company. - Direct labor rate standard...

    5) The following information is presented for the Maybeel Manufacturing Company. - Direct labor rate standard is $11.55. - Direct labor efficiency standard is 2.5 hours per unit. - Budgeted production is 1,200 units. - Production required 2,910 direct labor hours at a cost of $33,174. - Actual production is 1,150 units. What is the direct labor efficiency variance? A) $404.25 Favorable B) $1,039.50 Unfavorable C) $404.25 Unfavorable D) $1,039.50 Favorable

  • questions 11 & 12 550,523 Selling and administrative expenses$ 30,654 The selling and administrative expenses in...

    questions 11 & 12 550,523 Selling and administrative expenses$ 30,654 The selling and administrative expenses in the planning budget for May would be: a. $30,840 b. $30,864 C. $35,294 d. $35,318 e. None of the above 11. At Stolen Horse Corporation, indirect labor is a variable cost that varies with direct labor hours. Last month's flexible budget performance report showed that actual indirect labor cost totaled $2,056 for the month and 5,140 direct labor hours were actually worked. The report...

  • 10 Direct materials Standard per unit Actual $ 4 per pound Used 15 Materials quantity variance...

    10 Direct materials Standard per unit Actual $ 4 per pound Used 15 Materials quantity variance $ 3 2 pounds pounds Produced 10 finished units (AQ used - SQ allowed) SP A B C D 15 20 39 78 2 pt Variance is A favorable B unfavorable SQ allowed Standard per unit actual units 11 FACTORY OVERHEAD Machine Hours Budgeted $50 Standard allowed 16 Actual 180 Actual Variable factory overhead (activity base) rate per machine hour $10 Efficiency variance 10...

  • The following information describes a company's direct labor usage in a recent period. Actual direct labor...

    The following information describes a company's direct labor usage in a recent period. Actual direct labor hours used (AH) Actual direct labor rate per hour (AR) Standard direct labor rate per hour (SR) Standard direct labor hours for units produced (SH) 55,000 $ 14 $ 12 56,200 AH = Actual Hours SH = Standard Hours AR = Actual Rate SR = Standard Rate Compute the direct labor rate and efficiency variances for the period and classify each as favorable, unfavorable...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT