Escuha Company | ||||
Answer 1 | ||||
Calculation of Plant wide OH Rate | Department 1 | Department 2 | Total | Note |
Overhead costs | 894,500.00 | 791,000.00 | 1,685,500.00 | A |
Direct Labor Hours | 186,630.00 | 927,670.00 | 1,114,300.00 | B |
Predetermined OH Rate | 1.51 | C=A/B |
Overhead cost per unit | Scientific | Business | Note |
Direct Labor Hours | 101,300.00 | 1,013,000.00 | D |
Predetermined OH Rate | 1.51 | 1.51 | See C |
Allocated OH | 152,963.00 | 1,529,630.00 | E=C*D |
Units produced | 72,000.00 | 720,000.00 | F |
Overhead cost per unit | 2.12 | 2.12 | G=E/F |
Answer 2 | |||
Calculation of Departmental OH Rate | Department 1 | Department 2 | |
Overhead costs | 894,500.00 | 791,000.00 | See A |
Direct Labor/ Machine Hours | 382,120.00 | 927,670.00 | H |
Predetermined OH Rate | 2.34 | 0.85 | I=A/H |
Overhead cost per unit | Scientific | Business | |
Machine Hours | 23,300.00 | 358,820.00 | J |
Predetermined OH Rate- Dept. 1 | 2.34 | 2.34 | See I |
Allocated OH- Dept. 1 | 54,522.00 | 839,638.80 | K=J*I |
Labor Hours | 26,100.00 | 901,570.00 | L |
Predetermined OH Rate- Dept. 1 | 0.85 | 0.85 | See I |
Allocated OH- Dept. 2 | 22,185.00 | 766,334.50 | M=L*I |
Total Allocated OH | 76,707.00 | 1,605,973.30 | N=K+M |
Units produced | 72,000.00 | 720,000.00 | See F |
Overhead cost per unit | 1.07 | 2.23 | O=N/F |
Calculation of Departmental OH Rate | Department 1 | Department 2 | |
Overhead costs | 894,500.00 | 791,000.00 | See A |
Direct Labor/ Machine Hours | 186,630.00 | 139,280.00 | P |
Predetermined OH Rate | 4.79 | 5.68 | Q=A/P |
Overhead cost per unit | Scientific | Business | |
Labor Hours | 75,200.00 | 111,430.00 | R |
Predetermined OH Rate- Dept. 1 | 4.79 | 4.79 | See Q |
Allocated OH- Dept. 1 | 360,208.00 | 533,749.70 | S=R*Q |
Machine Hours | 24,100.00 | 115,180.00 | T |
Predetermined OH Rate- Dept. 1 | 5.68 | 5.68 | See Q |
Allocated OH- Dept. 2 | 136,888.00 | 654,222.40 | U=Q*T |
Total Allocated OH | 497,096.00 | 1,187,972.10 | V=S+U |
Units produced | 72,000.00 | 720,000.00 | See F |
Overhead cost per unit | 6.90 | 1.65 | W=V/F |
Answer 3 |
|
|
||||||||
Calculation of ABC rates for overhead | X | Y | Z=X+Y | AA | AB | AC=AB+AC | AD=Z/AC | |||
Activity cost pool | Cost Driver | Department 1 | Department 2 | Cost | Scientific | Business | Quantity | ABC rates | ||
Setups | Production runs | 227,500.00 | 227,500.00 | 455,000.00 | 100.00 | 150.00 | 250.00 | 1,820.00 | ||
Inspection | Inspection hours | 190,000.00 | 190,000.00 | 380,000.00 | 2,000.00 | 3,000.00 | 5,000.00 | 76.00 | ||
Power | Machine Hours | 268,000.00 | 155,000.00 | 423,000.00 | 47,400.00 | 474,000.00 | 521,400.00 | 0.81 | ||
Maintenance | Maintenance hours | 209,000.00 | 218,500.00 | 427,500.00 | 2,250.00 | 9,000.00 | 11,250.00 | 38.00 | ||
Total Cost assigned | 1,685,500.00 |
See AD | See AA | AE=AD*AE | See AB | AF=AD*AB | |||||||
Allocation table | Scientific |
|
|
||||||||
Activity cost pool | Cost Driver | ABC Rates | Activity used | Cost assigned | Activity used | Cost assigned | |||||
Setups | Production runs | 1,820.00 | 100.00 | 182,000.00 | 150.00 | 273,000.00 | |||||
Inspection | Inspection hours | 76.00 | 2,000.00 | 152,000.00 | 3,000.00 | 228,000.00 | |||||
Power | Machine Hours | 0.81 | 47,400.00 | 38,454.55 | 474,000.00 | 384,545.45 | |||||
Maintenance | Maintenance hours | 38.00 | 2,250.00 | 85,500.00 | 9,000.00 | 342,000.00 | |||||
Total Cost assigned | 457,954.55 | 1,227,545.45 | AG | ||||||||
Number of units | 72,000.00 | 720,000.00 | See F | ||||||||
Overhead cost per unit | 6.36 | 1.70 | AH=AG/F |
Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing...
Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 74,000 740,000 Prime costs $258,000 $2,580,000 Direct labor hours 96,200 962,000 Machine hours 51,200 512,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data Department 1 Department 2 Direct labor hours:...
Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 76,000 760,000 Prime costs $253,000 $2,530,000 Direct labor hours 103,400 1,034,000 Machine hours 51,200 512,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...
Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 76,000 760,000 Prime costs $253,000 $2,530,000 Direct labor hours 103,400 1,034,000 Machine hours 51,200 512,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...
Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 78,000 780,000 Prime costs $247,000 $2,470,000 Direct labor hours 96,500 965,000 Machine hours 53,000 530,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...
Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 77,000 770,000 Prime costs $265,000 $2,650,000 Direct labor hours 101,000 1,010,000 Machine hours 49,000 490,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...
Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 74,000 740,000 Prime costs $248,000 $2,480,000 Direct labor hours 102,200 1,022,000 Machine hours 50,000 500,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...
Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 75,000 750,000 Prime costs $249,000 $2,490,000 Direct labor hours 99,700 997,000 Machine hours 50,500 505,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...
Product Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: Scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product Related Data Scientific Business Units produced per year 72,000 720,000 Prime costs $230,000 $2,300,000 Direct labor hours 102,600 1,026,000 Machine hours 48,900 489,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000...
Product-Costing Accuracy, Plantwide and Departmental Rates, ABC 3,000 Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 75,000 750,000 Prime costs $249,000 $2,490,000 Direct labor hours 99,700 997,000 Machine hours 50,500 505,000 Production runs 100 150 Inspection hours 2,000 Maintenance hours 2,250 9,000 Department Data...
Product-Costing Accuracy, Plantwide and Departmental Rates,
ABC
Escuha Company produces two type of calculators: scientific and
business. Both products pass through two producing departments. The
business calculator is by far the most popular. SOLVE PLEASE
Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Units produced...