Period Cash Flow Cumulative Cash flow
0 -250 -250
1 10 -240
2 10 -230
3 10 -220
4 90 -130
5 90 -40
6 90 50
7 100 150

Payback period = Year before full recover ie Year 5 + (Unrecovered Cost at start of the Year ie 40 )/(Cash flow during the Year ie 90)

=5+40/90

=5.4 Years

Add a comment
Know the answer?
Add Answer to:
What is the payback period of a project with the following expected cash inflows (in millions)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT